This problem involves calculating the time required for a combined group of men and women to complete a work, given the time taken by individual groups.
We are given that 10 men can complete the work in 170 days, and 15 women can complete the same work in 170 days. This implies that the work done by 10 men is equivalent to the work done by 15 women.
Let 'M' represent the work rate of one man and 'W' represent the work rate of one woman.
From the problem statement:
Equating the work done:
\( 10 M \times 170 = 15 W \times 170 \)
This simplifies to:
\( 10 M = 15 W \)
Dividing both sides by 5:
\( 2 M = 3 W \)
This relationship tells us the relative work efficiency of men and women. From this, we can express the work rate of a woman in terms of a man's work rate:
\( W = \frac{2}{3} M \)
We need to find the time taken by 20 men and 20 women working together.
First, let's express the combined workforce in terms of a single unit, say, equivalent men.
The combined group consists of 20 men and 20 women. Substitute the equivalent work rate of women:
\( \text{Total Equivalent Men} = 20 M + 20 W \)
\( = 20 M + 20 \left( \frac{2}{3} M \right) \)
\( = 20 M + \frac{40}{3} M \)
\( = \left( \frac{60}{3} + \frac{40}{3} \right) M \)
\( = \frac{100}{3} M \)
So, 20 men and 20 women together have the work capacity equivalent to \( \frac{100}{3} \) men.
The total amount of work can be calculated from the initial condition. Let's use the men's data:
\( \text{Total Work} = 10 \text{ men} \times 170 \text{ days} = 1700 \text{ man-days} \)
Now, we can find the time required for the combined group (\( \frac{100}{3} \) men) to complete this work:
\( \text{Time} = \frac{\text{Total Work}}{\text{Number of Equivalent Men}} \)
\( \text{Time} = \frac{1700 \text{ man-days}}{\frac{100}{3} \text{ men}} \)
\( \text{Time} = 1700 \times \frac{3}{100} \text{ days} \)
\( \text{Time} = 17 \times 3 \text{ days} \)
\( \text{Time} = 51 \text{ days} \)
Alternatively, we could convert the combined workforce to equivalent women:
\( 2 M = 3 W \implies M = \frac{3}{2} W \)
\( \text{Total Equivalent Women} = 20 M + 20 W = 20 \left( \frac{3}{2} W \right) + 20 W \)
\( = 30 W + 20 W = 50 W \)
\( \text{Total Work} = 15 \text{ women} \times 170 \text{ days} = 2550 \text{ woman-days} \)
\( \text{Time} = \frac{2550 \text{ woman-days}}{50 \text{ women}} = \frac{255}{5} \text{ days} = 51 \text{ days} \)
Both methods confirm that 20 men and 20 women will take 51 days to complete the same work.
A and B can complete a task together in 12 days, while B and C can finish it in 16 days. After A works on it for 5 days and B for 7 days, C takes the remaining 13 days to finish the work. How many days would it take for C to complete the work alone?
A is three times more efficient as a worker than B, which allows A to complete a job in 60 days less than B. If they work together, they can finish the job in:
A and B can finish a certain job in 28 and 35 days, respectively. They started working together, but A left after a while, and B managed to complete the remaining work in 17 days. How many days did A work before leaving?
If 6 machines complete a task in 10 days, how many days for 15 machines at the same rate?
A can do a work in 8 days and B in 12 days. They work together for 3 days. What part of the work is left?
Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?
A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?
Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?
A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?