All Exams Test series for 1 year @ ₹349 only
Question

A process needs to be standardized for method and time. Which one of the following represents the sequence of work study experiments?

The correct answer is
Method study followed by time study

Sequence of Work Study Experiments

Work study involves two main techniques: method study and time study. The goal is to standardize a process for both the best method and the appropriate time required.

Purpose of Work Study

The primary objective is process improvement and standardization. This involves finding the most efficient way to perform a task and then determining the standard time needed for its completion.

Role of Method Study

Method study focuses on improving the way a job is performed. It involves:

  • Observing the current method.
  • Analyzing the steps involved.
  • Eliminating unnecessary elements.
  • Developing a new, improved method.
  • Standardizing the improved method.

This step ensures the task is done efficiently before its duration is measured.

Role of Time Study

Time study measures the time required to complete a specific task using a standardized method. It involves:

  • Timing the elements of the job performed using the standardized method.
  • Calculating the standard time based on these observations.
  • Setting performance standards.

Time study is only meaningful once the method itself has been optimized and standardized.

Determining the Correct Sequence

To effectively standardize a process for both method and time, the sequence must be logical:

  1. Method Study First: Identify and standardize the most efficient and effective method for performing the task. This eliminates inefficiencies and variations in how the task is done.
  2. Time Study Second: Once the method is fixed and optimized, measure the time required to perform the task using that specific, standardized method. This allows for accurate time standardization.

Therefore, method study must precede time study for effective process standardization.

Was this answer helpful?

Important Questions from Line Balancing and Work Study

  1. The time study of machinery operation recorded a cycle time of 7.0, 6.0, 7.0, 8.0 minutes. The performance rating of worker is 95%. The allowance fraction is 0.1. Standard time will be given by:

  2. A manufacturing cell has 5 machines A, B, C, D and E. The average cycle time (in minutes) for a job on each of the machines is given in the following table:

    MachineABCDE
    Average cycle time565.544.5

    There are three operators in the cell. First operator operates machines A and B. The second operator operates machine C and the third operator operates machines D and E. All the jobs have to move in the following sequence: 

    $A \to B \to C \to D \to E$ 

    Assuming the job transfer time between two machines to be negligible, the average cycle time (in minutes) for the manufacturing cell is

  3. Work costs defined as ___________.
  4. Employee participation in the planning, organisation, and control of their work is what is referred to as the process of changing the nature of the work to increase job satisfaction and meaning.

  5. Fifty observations of production operation revealed a mean cycle time of 10 min. The worker was evaluated to be performing at 90% efficiency. Assuming the allowances to be 10% of the normal time, the standard time (in minutes) for the job is