All Exams Test series for 1 year @ ₹349 only
Question

A construction project requires 18 workers working for 25 days. After 10 days, 6 workers leave and 4 new workers join who are 25% more efficient than original workers. After 5 more days, all remaining workers increase their efficiency by 20%. How many total days will the project take to complete?

The correct answer is
$24\frac{7}{102}$ days

Construction Project Time Calculation

This problem involves calculating the total duration of a construction project where the number of workers and their efficiency change over time. We need to break down the project into phases based on these changes and calculate the work done in each phase.

Understanding the Total Work Required

First, let's determine the total amount of work required for the project. We assume the initial 'work' unit is equivalent to one worker working for one day at the original efficiency level.

  • Number of original workers = 18
  • Number of days planned = 25
  • Total work = Number of workers × Number of days
  • Total work = $18 \times 25 = 450$ worker-days (at original efficiency).

Phase 1: Initial Work

The project starts with 18 workers who work for the first 10 days.

  • Workers = 18
  • Days worked = 10
  • Work done in Phase 1 = $18 \text{ workers} \times 10 \text{ days} = 180$ worker-days.
  • Remaining work = Total work - Work done in Phase 1
  • Remaining work = $450 - 180 = 270$ worker-days.

Phase 2: Changes in Workforce

After 10 days, 6 workers leave, and 4 new workers join. These new workers are 25% more efficient than the original workers.

  • Workers remaining after 6 leave = $18 - 6 = 12$ original workers.
  • New workers joining = 4.
  • Total number of workers = $12 + 4 = 16$ workers.
  • Efficiency of new workers = $100\% + 25\% = 125\%$ of original efficiency.

Let the original efficiency of a worker be $E$. The efficiency of the 12 original workers is $12 \times E$. The efficiency of the 4 new workers is $4 \times (1.25 \times E) = 5 \times E$.

The combined effective efficiency of the workforce in this phase is $(12 \times E) + (5 \times E) = 17 \times E$. This means the group works at a rate equivalent to 17 original workers.

This group works for the next 5 days.

  • Days worked in Phase 2 = 5
  • Work done in Phase 2 = (Effective efficiency) × Days worked
  • Work done in Phase 2 = $(17 \times E) \times 5 \text{ days} = 85 \times E$ worker-days.
  • Remaining work after Phase 2 = Work remaining after Phase 1 - Work done in Phase 2
  • Remaining work = $270 - 85 = 185$ worker-days.

Phase 3: Efficiency Increase

After these 5 days (i.e., at the start of Phase 3), all remaining workers increase their efficiency by 20%.

  • Total workers = 16 (12 original + 4 new).
  • Efficiency increase = 20%.

Let's calculate the new efficiencies:

  • The 12 original workers (initial efficiency $E$) now work at $E \times (1 + 0.20) = 1.20E$.
  • The 4 new workers (initial efficiency $1.25E$) now work at $(1.25E) \times (1 + 0.20) = 1.25E \times 1.20 = 1.50E$.

The new combined effective efficiency is:

  • Effective efficiency = $(12 \times 1.20E) + (4 \times 1.50E)$
  • Effective efficiency = $14.4E + 6.0E = 20.4E$.

This means the current group of 16 workers works at a rate equivalent to 20.4 original workers.

Calculating Remaining Days

We need to find out how many days are required to complete the remaining 185 worker-days of work with this new efficiency level.

  • Remaining work = 185 worker-days.
  • Effective rate of work = $20.4$ original worker-days per day.
  • Days needed for Phase 3 = $\frac{\text{Remaining work}}{\text{Effective rate of work}}$
  • Days needed for Phase 3 = $\frac{185}{20.4}$ days.

To simplify the fraction:

  • $\frac{185}{20.4} = \frac{1850}{204}$
  • Divide both numerator and denominator by 2: $\frac{925}{102}$ days.

Convert the improper fraction to a mixed number:

  • $925 \div 102 = 9$ with a remainder of $7$ ($102 \times 9 = 918$).
  • So, Days needed for Phase 3 = $9\frac{7}{102}$ days.

Total Project Duration

The total time taken for the project is the sum of the days spent in each phase.

  • Total Days = Days in Phase 1 + Days in Phase 2 + Days in Phase 3
  • Total Days = $10 + 5 + 9\frac{7}{102}$
  • Total Days = $24\frac{7}{102}$ days.

Therefore, the project will take a total of $24\frac{7}{102}$ days to complete.

Was this answer helpful?

Important Questions from Time & Work (Notes)

  1. A fresh water tap fills a fish tank in 40 minutes. The same tank is filled by a salt water tap in 120 minutes. If both the taps are open, how many minutes will it take to fill the tank?
  2. A completes $\frac{7}{10}$ of a work in 15 days and then he completes the remaining work with the help of B in 5 days. In how many days can A and B together complete the entire work?
  3. Aman can do 50% of the job in 16 days, and Bhanu can do 25% of the job in 24 days. In how many days can they do $\frac{1}{4}^{th}$  of the job working together ?

  4. X can finish a job in $141$ days. He worked for $57$ days alone and the remaining work was completed by Y, in $84$ days. How many days would both together take to complete the entire job?
  5. Ravina, Sujata, and Saroj can complete a work of painting separately in 32, 48, and 64 hours, respectively. They started working together, but Saroj left after 5 hours. From the 6th hour, Ravina and Sujata decided to work on alternate hours starting with Ravina. In how much time will the entire work of painting be completed?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App