All Exams Test series for 1 year @ ₹349 only
Question

A can finish a work in 5 days and B can do the same work in 50 days. B worked alone for 10 days and left the job. In how many days can A alone finish the remaining work?

The correct answer is
4

This problem involves calculating the time A needs to complete the remaining work after B has worked for a certain period.

Calculating Work Rates

First, determine the fraction of the work each person completes per day:

  • A's daily work rate = $\frac{1}{\text{A's total days}} = \frac{1}{5}$ of the work per day.
  • B's daily work rate = $\frac{1}{\text{B's total days}} = \frac{1}{50}$ of the work per day.

Work Done by B

B worked alone for 10 days. Calculate the portion of the work B completed:

  • Work done by B = B's rate $\times$ Time worked
  • Work done by B = $\frac{1}{50} \times 10 = \frac{10}{50} = \frac{1}{5}$ of the total work.

Calculating Remaining Work

Determine the amount of work left to be done:

  • Remaining Work = Total Work - Work done by B
  • Remaining Work = $1 - \frac{1}{5} = \frac{4}{5}$ of the total work.

Time for A to Finish Work

Calculate how many days A needs to complete the remaining work using A's daily rate:

  • Time = $\frac{\text{Remaining Work}}{\text{A's daily rate}}$
  • Time = $\frac{4/5}{1/5}$
  • Time = $\frac{4}{5} \times \frac{5}{1} = 4$ days.

Therefore, A can finish the remaining work alone in 4 days.

Was this answer helpful?

Important Questions from Time & Work (Notes)

  1. A fresh water tap fills a fish tank in 40 minutes. The same tank is filled by a salt water tap in 120 minutes. If both the taps are open, how many minutes will it take to fill the tank?
  2. A completes $\frac{7}{10}$ of a work in 15 days and then he completes the remaining work with the help of B in 5 days. In how many days can A and B together complete the entire work?
  3. Aman can do 50% of the job in 16 days, and Bhanu can do 25% of the job in 24 days. In how many days can they do $\frac{1}{4}^{th}$  of the job working together ?

  4. X can finish a job in $141$ days. He worked for $57$ days alone and the remaining work was completed by Y, in $84$ days. How many days would both together take to complete the entire job?
  5. Ravina, Sujata, and Saroj can complete a work of painting separately in 32, 48, and 64 hours, respectively. They started working together, but Saroj left after 5 hours. From the 6th hour, Ravina and Sujata decided to work on alternate hours starting with Ravina. In how much time will the entire work of painting be completed?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App