All Exams Test series for 1 year @ ₹349 only
Question

A, B and C can separately do a work in 12, 15 and 20 days respectively. They started to work together but C left after 2 days. Then A and B will finish the remaining work in ______ days.

The correct answer is
4

Understanding Individual Work Rates

To solve this problem, we first need to understand how much work each person completes per day. This is known as their individual work rate.

  • Person A completes the entire work in 12 days. Therefore, A's work rate is $\frac{1}{12}$ of the work per day.
  • Person B completes the entire work in 15 days. So, B's work rate is $\frac{1}{15}$ of the work per day.
  • Person C completes the entire work in 20 days. Thus, C's work rate is $\frac{1}{20}$ of the work per day.

Calculating Combined Work Rate

Initially, A, B, and C started working together. We can find their combined work rate by adding their individual rates.

Combined rate of A, B, and C = Rate of A + Rate of B + Rate of C

Combined rate = $\frac{1}{12} + \frac{1}{15} + \frac{1}{20}$

To add these fractions, we find the least common multiple (LCM) of the denominators (12, 15, and 20). The LCM is 60.

Combined rate = $\frac{5}{60} + \frac{4}{60} + \frac{3}{60} = \frac{5+4+3}{60} = \frac{12}{60}$

Simplifying the fraction $\frac{12}{60}$, we get $\frac{1}{5}$. So, A, B, and C together complete $\frac{1}{5}$ of the work per day.

Work Done in the First Two Days

A, B, and C worked together for the first 2 days before C left.

Work done in 2 days = Combined rate $\times$ Number of days worked

Work done = $\frac{1}{5} \times 2 = \frac{2}{5}$

This means $\frac{2}{5}$ of the total work was completed in the first 2 days.

Calculating Remaining Work

After C left, there was a portion of the work that still needed to be completed.

Remaining work = Total work - Work done in the first 2 days

Remaining work = $1 - \frac{2}{5} = \frac{5}{5} - \frac{2}{5} = \frac{3}{5}$

So, $\frac{3}{5}$ of the work is remaining.

Determining the Combined Rate of A and B

Now, A and B are responsible for finishing the remaining $\frac{3}{5}$ of the work. Let's calculate their combined work rate.

Combined rate of A and B = Rate of A + Rate of B

Combined rate (A+B) = $\frac{1}{12} + \frac{1}{15}$

The LCM of 12 and 15 is 60.

Combined rate (A+B) = $\frac{5}{60} + \frac{4}{60} = \frac{5+4}{60} = \frac{9}{60}$

Simplifying this fraction, the combined rate of A and B is $\frac{3}{20}$ of the work per day.

Calculating Time to Finish Remaining Work

To find out how many days A and B will take to complete the remaining work, we divide the remaining work by their combined rate.

Time = $\frac{\text{Remaining Work}}{\text{Combined Rate of A and B}}$

Time = $\frac{\frac{3}{5}}{\frac{3}{20}}$

Dividing fractions involves multiplying the first fraction by the reciprocal of the second fraction:

Time = $\frac{3}{5} \times \frac{20}{3}$

Time = $\frac{3 \times 20}{5 \times 3} = \frac{60}{15}$

Time = 4 days.

Thus, A and B will finish the remaining work in 4 days.

Was this answer helpful?

Important Questions from Time and Work

  1. A works thrice as fast as B. If B can complete a work in 256 days independently, then find the number of days in which A and B can together
    finish the work.
  2. A can finish a job in 146 days, B can finish the same job in 219 days and C can finish the same job in 292 days. If all three are working together, how many days will they require to complete the same job?
  3. X can finish a work in 153 days, Y can finish a work in 255 and Z can finish the same piece of work 340 days. How many days will they require to complete the work, if X, Y and Z are working together?
  4. A finish a work in 1170 days and B can do the same work in 2340 days. Working together, they will complete the same work in how many days?
  5. A can finish a job in 102 days, B can finish the same job in 153 days and C can finish the same job in 204 days. If all three are working together, how many days will they require to complete the same job?
Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App