All Exams Test series for 1 year @ ₹349 only
Question

A, B and C can complete their project work individually in 10 days, 15 days and 20 days, respectively. A and B start working but A quits after working for 3 days. After this, C joins B till the completion of project work. In how much time will the project work be completed?

The correct answer is
$7\frac{2}{7}$ days

Understanding the Project Work Problem

This problem involves calculating the total time needed to finish a project based on the individual work rates of three people: A, B, and C. The scenario describes a sequence where A and B start together, A leaves, and then C joins B to complete the remaining work.

Calculating Individual Work Rates

To solve this, we first find out how much of the project each person can complete in a single day. This is their 'work rate'.

  • A completes the project in 10 days, so A's rate is $ \frac{1}{10} $ of the project per day.
  • B completes the project in 15 days, so B's rate is $ \frac{1}{15} $ of the project per day.
  • C completes the project in 20 days, so C's rate is $ \frac{1}{20} $ of the project per day.

Step-by-Step Solution: Project Phases

Phase 1: A and B Working Together

A and B begin the project and work side-by-side for the first 3 days.

  • First, we find their combined work rate when they work together:
  • $ \text{Combined Rate}_{A+B} = \text{Rate of A} + \text{Rate of B} = \frac{1}{10} + \frac{1}{15} $
  • To add these, we find a common denominator, which is 30:
  • $ \text{Combined Rate}_{A+B} = \frac{3}{30} + \frac{2}{30} = \frac{5}{30} = \frac{1}{6} $ project per day.
  • Next, we calculate the amount of work they complete in these 3 days:
  • Work Done = $ \text{Combined Rate}_{A+B} \times \text{Time} $
  • Work Done = $ \frac{1}{6} \times 3 = \frac{3}{6} = \frac{1}{2} $ of the project.

Phase 2: B and C Working Together

After 3 days, A leaves. The rest of the project work is completed by B and C working together.

  • We first determine the amount of work remaining:
  • Remaining Work = Total Work - Work Done in Phase 1
  • Remaining Work = $ 1 - \frac{1}{2} = \frac{1}{2} $ of the project.
  • Now, we find the combined work rate of B and C:
  • $ \text{Combined Rate}_{B+C} = \text{Rate of B} + \text{Rate of C} = \frac{1}{15} + \frac{1}{20} $
  • The common denominator for 15 and 20 is 60:
  • $ \text{Combined Rate}_{B+C} = \frac{4}{60} + \frac{3}{60} = \frac{7}{60} $ project per day.
  • Finally, we calculate the time B and C need to finish the remaining work:
  • Time = $ \frac{\text{Remaining Work}}{\text{Combined Rate}_{B+C}} $
  • Time = $ \frac{1/2}{7/60} = \frac{1}{2} \times \frac{60}{7} = \frac{60}{14} = \frac{30}{7} $ days.

Calculating Total Project Completion Time

The total time to complete the project is the sum of the durations of Phase 1 and Phase 2.

  • Total Time = Time in Phase 1 + Time in Phase 2
  • Total Time = 3 days + $ \frac{30}{7} $ days
  • To add these, we express 3 days as a fraction with a denominator of 7: $ 3 = \frac{21}{7} $.
  • Total Time = $ \frac{21}{7} + \frac{30}{7} = \frac{51}{7} $ days.
  • Converting the improper fraction $ \frac{51}{7} $ into a mixed number gives us $ 7 \frac{2}{7} $ days.

Thus, the entire project work will be completed in $ 7 \frac{2}{7} $ days.

Was this answer helpful?

Important Questions from Time & Work (Notes)

  1. If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same work in 2 days, then the time taken by 15 men and 20 boys to do the same work will be
  2. A fresh water tap fills a fish tank in 40 minutes. The same tank is filled by a salt water tap in 120 minutes. If both the taps are open, how many minutes will it take to fill the tank?
  3. Three pipes A, B and C can fill a tank in $10$, $15$ and $20$ hours respectively. Pipe A was opened at $6$ AM, pipe B at $7$ AM and pipe C at $8$ AM. At what time was the tank completely filled, if pipe C needs a break of $1$ hour after remaining open for $3$ hours?

  4. A tank has four pipes $P_1$, $P_2$, $P_3$ and $P_4$. The tank can be filled in $15$ minutes by pipes $P_1$, $P_2$, $P_3$ together. It can be filled in $20$ minutes by pipes $P_2$, $P_3$, $P_4$ together and it can be filled by pipes $P_1$, $P_4$ together in $30$ minutes. If all the pipes are opened together, then in how much time will the tank be filled?

  5. $5$ men and $4$ women can earn ₹ $20000$ in $8$ days. $10$ men and $7$ women can earn ₹ $23,750$ in $5$ days. In how many days will $5$ men and $6$ women earn ₹ $12,000$?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App