All Exams Test series for 1 year @ ₹349 only
Question

A, B and C can complete their project work individually in 10 days, 15 days and 20 days, respectively. A and B start working but A quits after working for 3 days. After this, C joins B till the completion of project work. In how much time will the project work be completed?

The correct answer is
$7\frac{2}{7}$ days

Understanding the Project Work Problem

This problem involves calculating the total time needed to finish a project based on the individual work rates of three people: A, B, and C. The scenario describes a sequence where A and B start together, A leaves, and then C joins B to complete the remaining work.

Calculating Individual Work Rates

To solve this, we first find out how much of the project each person can complete in a single day. This is their 'work rate'.

  • A completes the project in 10 days, so A's rate is $ \frac{1}{10} $ of the project per day.
  • B completes the project in 15 days, so B's rate is $ \frac{1}{15} $ of the project per day.
  • C completes the project in 20 days, so C's rate is $ \frac{1}{20} $ of the project per day.

Step-by-Step Solution: Project Phases

Phase 1: A and B Working Together

A and B begin the project and work side-by-side for the first 3 days.

  • First, we find their combined work rate when they work together:
  • $ \text{Combined Rate}_{A+B} = \text{Rate of A} + \text{Rate of B} = \frac{1}{10} + \frac{1}{15} $
  • To add these, we find a common denominator, which is 30:
  • $ \text{Combined Rate}_{A+B} = \frac{3}{30} + \frac{2}{30} = \frac{5}{30} = \frac{1}{6} $ project per day.
  • Next, we calculate the amount of work they complete in these 3 days:
  • Work Done = $ \text{Combined Rate}_{A+B} \times \text{Time} $
  • Work Done = $ \frac{1}{6} \times 3 = \frac{3}{6} = \frac{1}{2} $ of the project.

Phase 2: B and C Working Together

After 3 days, A leaves. The rest of the project work is completed by B and C working together.

  • We first determine the amount of work remaining:
  • Remaining Work = Total Work - Work Done in Phase 1
  • Remaining Work = $ 1 - \frac{1}{2} = \frac{1}{2} $ of the project.
  • Now, we find the combined work rate of B and C:
  • $ \text{Combined Rate}_{B+C} = \text{Rate of B} + \text{Rate of C} = \frac{1}{15} + \frac{1}{20} $
  • The common denominator for 15 and 20 is 60:
  • $ \text{Combined Rate}_{B+C} = \frac{4}{60} + \frac{3}{60} = \frac{7}{60} $ project per day.
  • Finally, we calculate the time B and C need to finish the remaining work:
  • Time = $ \frac{\text{Remaining Work}}{\text{Combined Rate}_{B+C}} $
  • Time = $ \frac{1/2}{7/60} = \frac{1}{2} \times \frac{60}{7} = \frac{60}{14} = \frac{30}{7} $ days.

Calculating Total Project Completion Time

The total time to complete the project is the sum of the durations of Phase 1 and Phase 2.

  • Total Time = Time in Phase 1 + Time in Phase 2
  • Total Time = 3 days + $ \frac{30}{7} $ days
  • To add these, we express 3 days as a fraction with a denominator of 7: $ 3 = \frac{21}{7} $.
  • Total Time = $ \frac{21}{7} + \frac{30}{7} = \frac{51}{7} $ days.
  • Converting the improper fraction $ \frac{51}{7} $ into a mixed number gives us $ 7 \frac{2}{7} $ days.

Thus, the entire project work will be completed in $ 7 \frac{2}{7} $ days.

Was this answer helpful?

Important Questions from Time & Work (Notes)

  1. A fresh water tap fills a fish tank in 40 minutes. The same tank is filled by a salt water tap in 120 minutes. If both the taps are open, how many minutes will it take to fill the tank?
  2. A completes $\frac{7}{10}$ of a work in 15 days and then he completes the remaining work with the help of B in 5 days. In how many days can A and B together complete the entire work?
  3. Aman can do 50% of the job in 16 days, and Bhanu can do 25% of the job in 24 days. In how many days can they do $\frac{1}{4}^{th}$  of the job working together ?

  4. X can finish a job in $141$ days. He worked for $57$ days alone and the remaining work was completed by Y, in $84$ days. How many days would both together take to complete the entire job?
  5. Ravina, Sujata, and Saroj can complete a work of painting separately in 32, 48, and 64 hours, respectively. They started working together, but Saroj left after 5 hours. From the 6th hour, Ravina and Sujata decided to work on alternate hours starting with Ravina. In how much time will the entire work of painting be completed?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App