All Exams Test series for 1 year @ ₹349 only
Question

A, B and C can complete their project work individually in 10 days, 15 days and 20 days, respectively. A and B start working but A quits after working for 3 days. After this, C joins B till the completion of project work. In how much time will the project work be completed?

The correct answer is
$7\frac{2}{7}$ days

Understanding the Project Work Problem

This problem involves calculating the total time needed to finish a project based on the individual work rates of three people: A, B, and C. The scenario describes a sequence where A and B start together, A leaves, and then C joins B to complete the remaining work.

Calculating Individual Work Rates

To solve this, we first find out how much of the project each person can complete in a single day. This is their 'work rate'.

  • A completes the project in 10 days, so A's rate is $ \frac{1}{10} $ of the project per day.
  • B completes the project in 15 days, so B's rate is $ \frac{1}{15} $ of the project per day.
  • C completes the project in 20 days, so C's rate is $ \frac{1}{20} $ of the project per day.

Step-by-Step Solution: Project Phases

Phase 1: A and B Working Together

A and B begin the project and work side-by-side for the first 3 days.

  • First, we find their combined work rate when they work together:
  • $ \text{Combined Rate}_{A+B} = \text{Rate of A} + \text{Rate of B} = \frac{1}{10} + \frac{1}{15} $
  • To add these, we find a common denominator, which is 30:
  • $ \text{Combined Rate}_{A+B} = \frac{3}{30} + \frac{2}{30} = \frac{5}{30} = \frac{1}{6} $ project per day.
  • Next, we calculate the amount of work they complete in these 3 days:
  • Work Done = $ \text{Combined Rate}_{A+B} \times \text{Time} $
  • Work Done = $ \frac{1}{6} \times 3 = \frac{3}{6} = \frac{1}{2} $ of the project.

Phase 2: B and C Working Together

After 3 days, A leaves. The rest of the project work is completed by B and C working together.

  • We first determine the amount of work remaining:
  • Remaining Work = Total Work - Work Done in Phase 1
  • Remaining Work = $ 1 - \frac{1}{2} = \frac{1}{2} $ of the project.
  • Now, we find the combined work rate of B and C:
  • $ \text{Combined Rate}_{B+C} = \text{Rate of B} + \text{Rate of C} = \frac{1}{15} + \frac{1}{20} $
  • The common denominator for 15 and 20 is 60:
  • $ \text{Combined Rate}_{B+C} = \frac{4}{60} + \frac{3}{60} = \frac{7}{60} $ project per day.
  • Finally, we calculate the time B and C need to finish the remaining work:
  • Time = $ \frac{\text{Remaining Work}}{\text{Combined Rate}_{B+C}} $
  • Time = $ \frac{1/2}{7/60} = \frac{1}{2} \times \frac{60}{7} = \frac{60}{14} = \frac{30}{7} $ days.

Calculating Total Project Completion Time

The total time to complete the project is the sum of the durations of Phase 1 and Phase 2.

  • Total Time = Time in Phase 1 + Time in Phase 2
  • Total Time = 3 days + $ \frac{30}{7} $ days
  • To add these, we express 3 days as a fraction with a denominator of 7: $ 3 = \frac{21}{7} $.
  • Total Time = $ \frac{21}{7} + \frac{30}{7} = \frac{51}{7} $ days.
  • Converting the improper fraction $ \frac{51}{7} $ into a mixed number gives us $ 7 \frac{2}{7} $ days.

Thus, the entire project work will be completed in $ 7 \frac{2}{7} $ days.

Was this answer helpful?

Important Questions from Time & Work (Notes)

  1. Aman can do 50% of the job in 16 days, and Bhanu can do 25% of the job in 24 days. In how many days can they do $\frac{1}{4}^{th}$  of the job working together ?

  2. X can finish a job in $141$ days. He worked for $57$ days alone and the remaining work was completed by Y, in $84$ days. How many days would both together take to complete the entire job?
  3. Ravina, Sujata, and Saroj can complete a work of painting separately in 32, 48, and 64 hours, respectively. They started working together, but Saroj left after 5 hours. From the 6th hour, Ravina and Sujata decided to work on alternate hours starting with Ravina. In how much time will the entire work of painting be completed?

  4. A and B complete a work in 6 days. If A alone can do it in 9 days, then B alone can do $\frac{1}{3}$ of the same work in ________ (days).

  5. A construction project requires 18 workers working for 25 days. After 10 days, 6 workers leave and 4 new workers join who are 25% more efficient than original workers. After 5 more days, all remaining workers increase their efficiency by 20%. How many total days will the project take to complete?
Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App