This problem involves calculating the total time needed to finish a project based on the individual work rates of three people: A, B, and C. The scenario describes a sequence where A and B start together, A leaves, and then C joins B to complete the remaining work.
To solve this, we first find out how much of the project each person can complete in a single day. This is their 'work rate'.
A and B begin the project and work side-by-side for the first 3 days.
After 3 days, A leaves. The rest of the project work is completed by B and C working together.
The total time to complete the project is the sum of the durations of Phase 1 and Phase 2.
Thus, the entire project work will be completed in $ 7 \frac{2}{7} $ days.
Three pipes A, B and C can fill a tank in $10$, $15$ and $20$ hours respectively. Pipe A was opened at $6$ AM, pipe B at $7$ AM and pipe C at $8$ AM. At what time was the tank completely filled, if pipe C needs a break of $1$ hour after remaining open for $3$ hours?
A tank has four pipes $P_1$, $P_2$, $P_3$ and $P_4$. The tank can be filled in $15$ minutes by pipes $P_1$, $P_2$, $P_3$ together. It can be filled in $20$ minutes by pipes $P_2$, $P_3$, $P_4$ together and it can be filled by pipes $P_1$, $P_4$ together in $30$ minutes. If all the pipes are opened together, then in how much time will the tank be filled?
$5$ men and $4$ women can earn ₹ $20000$ in $8$ days. $10$ men and $7$ women can earn ₹ $23,750$ in $5$ days. In how many days will $5$ men and $6$ women earn ₹ $12,000$?