All Exams Test series for 1 year @ ₹349 only
Question

A and B together can complete a certain work in 20 days whereas B and C together can complete it in 24 days. If A is twice as good a workman as C, then in what time will B alone do 40% of the same work?

The correct answer is

12 days

Understanding the Time and Work Problem

This problem involves understanding the concept of time and work, specifically how individuals working together complete a task and how their efficiencies relate to each other.

We are given information about the time taken by pairs of workers (A and B, B and C) to complete a certain work. We are also given a relationship between the efficiencies of A and C. We need to find the time taken by B alone to complete 40% of the same work.

Setting up the Problem: Efficiency and Total Work

Let's assume the total work to be a certain number of units. A common method is to take the Least Common Multiple (LCM) of the days given. The days given are 20 days (for A and B) and 24 days (for B and C).

LCM(20, 24) = 120 units.

Let the efficiency of A, B, and C (i.e., the amount of work they do per day) be \(a\), \(b\), and \(c\) units/day, respectively.

Formulating Equations based on Given Information

1. A and B together complete the work in 20 days:

Total work = (Combined efficiency) \(\times\) Time taken

\(120 = (a + b) \times 20\)

Dividing both sides by 20, we get the combined efficiency of A and B:

\(a + b = \frac{120}{20} = 6\) units/day. (Equation 1)

2. B and C together complete the work in 24 days:

Total work = (Combined efficiency) \(\times\) Time taken

\(120 = (b + c) \times 24\)

Dividing both sides by 24, we get the combined efficiency of B and C:

\(b + c = \frac{120}{24} = 5\) units/day. (Equation 2)

3. A is twice as good a workman as C:

This means the efficiency of A is twice the efficiency of C.

\(a = 2c\) units/day. (Equation 3)

Solving the System of Equations

We have a system of three linear equations with three variables (\(a\), \(b\), \(c\)):

1. \(a + b = 6\)

2. \(b + c = 5\)

3. \(a = 2c\)

Substitute Equation 3 into Equation 1:

\(2c + b = 6\) (Equation 4)

Now we have two equations (Equation 2 and Equation 4) involving only \(b\) and \(c\):

Equation 4: \(b + 2c = 6\)

Equation 2: \(b + c = 5\)

Subtract Equation 2 from Equation 4:

\((b + 2c) - (b + c) = 6 - 5\)

\(b + 2c - b - c = 1\)

\(c = 1\) unit/day.

Now that we have the value of \(c\), we can find \(a\) using Equation 3:

\(a = 2c = 2 \times 1 = 2\) units/day.

Finally, we can find \(b\) using Equation 2 (or Equation 1):

Using Equation 2: \(b + c = 5\)

\(b + 1 = 5\)

\(b = 5 - 1 = 4\) units/day.

So, the efficiencies are: A does 2 units/day, B does 4 units/day, and C does 1 unit/day.

Calculating Time for B Alone to do 40% Work

The total work is 120 units.

We need to find the time B alone takes to complete 40% of the work.

Amount of work B needs to complete = 40% of 120 units

Work = \(0.40 \times 120 = \frac{40}{100} \times 120 = \frac{2}{5} \times 120 = 2 \times 24 = 48\) units.

The efficiency of B is 4 units/day.

Time taken by B alone to complete 48 units of work = \(\frac{\text{Amount of Work}}{\text{Efficiency of B}}\)

Time = \(\frac{48}{4} = 12\) days.

Conclusion

B alone will take 12 days to complete 40% of the same work.

Workers Combined Time (days) Combined Efficiency (units/day)
A + B 20 \(\frac{120}{20} = 6\)
B + C 24 \(\frac{120}{24} = 5\)

Worker Efficiency (units/day)
A 2
B 4
C 1

40% of total work = \(0.40 \times 120 = 48\) units.

Time for B to do 40% work = \(\frac{48 \text{ units}}{4 \text{ units/day}} = 12 \text{ days}\).

Revision Table: Key Concepts

Concept Description
Time and Work Relationship Work = Efficiency \(\times\) Time
Efficiency The amount of work done per unit of time. Higher efficiency means less time taken to complete work.
Combined Efficiency When multiple people work together, their efficiencies add up.
Assuming Total Work Taking LCM of the given time periods simplifies calculations by making the total work an integer.

Additional Information: Variations in Time and Work Problems

Time and work problems can have several variations, including:

  • Problems involving different efficiencies of workers (like A is twice as good as C).
  • Problems where workers join or leave the work at different times.
  • Problems involving wages earned for the work done, which are usually proportional to the work done or efficiency.
  • Problems involving pipes and cisterns, which are similar to time and work problems where pipes fill or empty a tank (work) over time.

Solving these problems often involves calculating individual or combined efficiencies and then using the relationship Work = Efficiency \(\times\) Time to find the unknown quantity.

Was this answer helpful?

Important Questions from Work Efficiency

  1. 14 men can complete a work in 15 days. If 21 men are employed, then in how many days will they complete the same work?

  2. A can do a certain work in 15 days, while B can do the same work in 21 days. If they work together, then in how many days will the same work be completed?

  3. To do a certain work, A and B work on alternate days with B beginning the work on the first day. A alone can complete the same work in 24 days. If the work gets completed in  \(11 \frac{1}{3}\)  days, then B alone can complete  \(\rm \frac{7}{9}^{th}\)  part of the original work in:

  4. Two men and 7 women can complete a work in 28 days whereas 6 men and 16 women can do the same work in 11 days. In how many days can 7 men complete the same work?

  5. Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App