Work Rate Analysis for A and B
First, determine the daily work rate for both individuals.
- A completes the work in 12 days, so A's daily rate is $ \frac{1}{12} $.
- B completes the work in 6 days, so B's daily rate is $ \frac{1}{6} $.
Combined Work and Remaining Work
Calculate the work done when they work together and the remaining portion.
- Their combined daily rate is $ \frac{1}{12} + \frac{1}{6} = \frac{1}{12} + \frac{2}{12} = \frac{3}{12} = \frac{1}{4} $ of the work.
- In the 2 days they worked together, they completed $ \frac{1}{4} \times 2 = \frac{1}{2} $ of the work.
- The remaining work is $ 1 - \frac{1}{2} = \frac{1}{2} $.
A Completes Remaining Work
Determine the time A needs to finish the rest of the work alone.
- A's daily rate is $ \frac{1}{12} $.
- Time for A to complete the remaining $ \frac{1}{2} $ work = $ \frac{1/2}{1/12} $.
- Calculation: $ \frac{1}{2} \times 12 = 6 $ days.
A completed the remaining work in 6 days.