All Exams Test series for 1 year @ ₹349 only
Question

40 students working 9 h per day complete the task in 5 days. If 45 students are instructed to work 10 h per days, what is the time required to complete the work?

The correct answer is
4 days

Understanding the Work and Time Problem

This problem involves calculating the time required to complete a task based on the number of students, the hours they work per day, and the number of days taken. The core concept here is that the total amount of work done is proportional to the product of these three factors: the number of workers, the rate at which they work (hours per day), and the duration they work (days).

We can express this relationship. Let:

  • $S$ be the number of students (workers).
  • $H$ be the number of hours worked per day.
  • $D$ be the number of days required to complete the work.

The total work ($W$) can be considered proportional to the product $S \times H \times D$. Since the task remains the same in both scenarios, the total work required is constant.

Breaking Down the Information

Let's list the information provided for the two scenarios:

Scenario 1:

  • Number of students ($S_1$): 40
  • Hours worked per day ($H_1$): 9 h
  • Days to complete the work ($D_1$): 5 days

Scenario 2:

  • Number of students ($S_2$): 45
  • Hours worked per day ($H_2$): 10 h
  • Days to complete the work ($D_2$): ? (This is what we need to find)

Calculating the Required Time

The principle of work problems states that the total work done is constant if the task is the same. Therefore, we can set the work done in Scenario 1 equal to the work done in Scenario 2:

$ S_1 \times H_1 \times D_1 = S_2 \times H_2 \times D_2 $

Now, let's substitute the known values into the equation:

$ 40 \text{ students} \times 9 \text{ h/day} \times 5 \text{ days} = 45 \text{ students} \times 10 \text{ h/day} \times D_2 \text{ days} $

First, calculate the total 'student-hours' required in the first scenario:

Total Work (Scenario 1) = $40 \times 9 \times 5$

Total Work (Scenario 1) = $40 \times 45$

Total Work (Scenario 1) = $1800$ student-hours

Now, set this equal to the work done in the second scenario:

$ 1800 = 45 \times 10 \times D_2 $

Simplify the right side:

$ 1800 = 450 \times D_2 $

To find $D_2$, we rearrange the equation:

$ D_2 = \frac{1800}{450} $

Now, perform the division:

$ D_2 = \frac{180}{45} $

$ D_2 = 4 $

So, the time required for 45 students working 10 hours a day to complete the same task is 4 days.

Was this answer helpful?

Important Questions from Time & Work (Notes)

  1. A fresh water tap fills a fish tank in 40 minutes. The same tank is filled by a salt water tap in 120 minutes. If both the taps are open, how many minutes will it take to fill the tank?
  2. A completes $\frac{7}{10}$ of a work in 15 days and then he completes the remaining work with the help of B in 5 days. In how many days can A and B together complete the entire work?
  3. Aman can do 50% of the job in 16 days, and Bhanu can do 25% of the job in 24 days. In how many days can they do $\frac{1}{4}^{th}$  of the job working together ?

  4. X can finish a job in $141$ days. He worked for $57$ days alone and the remaining work was completed by Y, in $84$ days. How many days would both together take to complete the entire job?
  5. Ravina, Sujata, and Saroj can complete a work of painting separately in 32, 48, and 64 hours, respectively. They started working together, but Saroj left after 5 hours. From the 6th hour, Ravina and Sujata decided to work on alternate hours starting with Ravina. In how much time will the entire work of painting be completed?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App