$7\frac{9}{17}$ days
This problem involves calculating the time required to complete a production target given initial conditions, followed by changes in the number of machines, working hours, and efficiency.
First, let's determine the rate at which the machines produce units.
The total work done can be represented as the product of machines, hours per day, and days. We can assume the production rate (units per machine-hour) is constant initially.
Total machine-hours = M1 $\times$ H1 $\times$ D1 = 12 $\times$ 8 $\times$ 10 = 960 machine-hours.
The production rate is calculated as:
Rate = Total Units / Total Machine-hours = 960 units / 960 machine-hours = 1 unit per machine-hour.
The machines work under the initial conditions for the first 4 days.
Machine-hours in the first 4 days = 12 machines $\times$ 8 hours/day $\times$ 4 days = 384 machine-hours.
Units produced in the first 4 days = Rate $\times$ Machine-hours = 1 unit/machine-hour $\times$ 384 machine-hours = 384 units.
Now, we need to find out how many units are left to be produced.
Total units required = 960 units.
Units produced in the first 4 days = 384 units.
Remaining units = 960 units - 384 units = 576 units.
After 4 days, the conditions change:
The effective work done per day by the remaining machines needs to be calculated.
Effective machine-hours per day = M2 $\times$ H2 $\times$ E2
Effective machine-hours per day = 9 machines $\times$ 10 hours/day $\times$ 0.85
Effective machine-hours per day = 90 $\times$ 0.85 = 76.5 effective machine-hours per day.
We need to produce the remaining 576 units with the new conditions.
The production rate remains 1 unit per (effective) machine-hour.
Total effective machine-hours required = Remaining units / Rate
Total effective machine-hours required = 576 units / (1 unit/machine-hour) = 576 effective machine-hours.
Additional days needed (D2) = Total effective machine-hours required / Effective machine-hours per day
D2 = 576 / 76.5
To simplify the division, we can write 76.5 as $\frac{153}{2}$:
D2 = $\frac{576}{\frac{153}{2}} = \frac{576 \times 2}{153} = \frac{1152}{153}$
Now, simplify the fraction. Both numbers are divisible by 3:
$\frac{1152 \div 3}{153 \div 3} = \frac{384}{51}$
Both numbers are again divisible by 3:
$\frac{384 \div 3}{51 \div 3} = \frac{128}{17}$
Convert the improper fraction to a mixed number:
128 $\div$ 17 = 7 with a remainder of 9 (since $17 \times 7 = 119$, and $128 - 119 = 9$).
So, D2 = $7\frac{9}{17}$ days.
The number of additional days needed to complete the production is $7\frac{9}{17}$ days.
Aman can do 50% of the job in 16 days, and Bhanu can do 25% of the job in 24 days. In how many days can they do $\frac{1}{4}^{th}$ of the job working together ?
Ravina, Sujata, and Saroj can complete a work of painting separately in 32, 48, and 64 hours, respectively. They started working together, but Saroj left after 5 hours. From the 6th hour, Ravina and Sujata decided to work on alternate hours starting with Ravina. In how much time will the entire work of painting be completed?