$7\frac{9}{17}$ days
This problem involves calculating the time required to complete a production target given initial conditions, followed by changes in the number of machines, working hours, and efficiency.
First, let's determine the rate at which the machines produce units.
The total work done can be represented as the product of machines, hours per day, and days. We can assume the production rate (units per machine-hour) is constant initially.
Total machine-hours = M1 $\times$ H1 $\times$ D1 = 12 $\times$ 8 $\times$ 10 = 960 machine-hours.
The production rate is calculated as:
Rate = Total Units / Total Machine-hours = 960 units / 960 machine-hours = 1 unit per machine-hour.
The machines work under the initial conditions for the first 4 days.
Machine-hours in the first 4 days = 12 machines $\times$ 8 hours/day $\times$ 4 days = 384 machine-hours.
Units produced in the first 4 days = Rate $\times$ Machine-hours = 1 unit/machine-hour $\times$ 384 machine-hours = 384 units.
Now, we need to find out how many units are left to be produced.
Total units required = 960 units.
Units produced in the first 4 days = 384 units.
Remaining units = 960 units - 384 units = 576 units.
After 4 days, the conditions change:
The effective work done per day by the remaining machines needs to be calculated.
Effective machine-hours per day = M2 $\times$ H2 $\times$ E2
Effective machine-hours per day = 9 machines $\times$ 10 hours/day $\times$ 0.85
Effective machine-hours per day = 90 $\times$ 0.85 = 76.5 effective machine-hours per day.
We need to produce the remaining 576 units with the new conditions.
The production rate remains 1 unit per (effective) machine-hour.
Total effective machine-hours required = Remaining units / Rate
Total effective machine-hours required = 576 units / (1 unit/machine-hour) = 576 effective machine-hours.
Additional days needed (D2) = Total effective machine-hours required / Effective machine-hours per day
D2 = 576 / 76.5
To simplify the division, we can write 76.5 as $\frac{153}{2}$:
D2 = $\frac{576}{\frac{153}{2}} = \frac{576 \times 2}{153} = \frac{1152}{153}$
Now, simplify the fraction. Both numbers are divisible by 3:
$\frac{1152 \div 3}{153 \div 3} = \frac{384}{51}$
Both numbers are again divisible by 3:
$\frac{384 \div 3}{51 \div 3} = \frac{128}{17}$
Convert the improper fraction to a mixed number:
128 $\div$ 17 = 7 with a remainder of 9 (since $17 \times 7 = 119$, and $128 - 119 = 9$).
So, D2 = $7\frac{9}{17}$ days.
The number of additional days needed to complete the production is $7\frac{9}{17}$ days.
Three pipes A, B and C can fill a tank in $10$, $15$ and $20$ hours respectively. Pipe A was opened at $6$ AM, pipe B at $7$ AM and pipe C at $8$ AM. At what time was the tank completely filled, if pipe C needs a break of $1$ hour after remaining open for $3$ hours?
A tank has four pipes $P_1$, $P_2$, $P_3$ and $P_4$. The tank can be filled in $15$ minutes by pipes $P_1$, $P_2$, $P_3$ together. It can be filled in $20$ minutes by pipes $P_2$, $P_3$, $P_4$ together and it can be filled by pipes $P_1$, $P_4$ together in $30$ minutes. If all the pipes are opened together, then in how much time will the tank be filled?
$5$ men and $4$ women can earn ₹ $20000$ in $8$ days. $10$ men and $7$ women can earn ₹ $23,750$ in $5$ days. In how many days will $5$ men and $6$ women earn ₹ $12,000$?