All Exams Test series for 1 year @ ₹349 only
Question

12 machines working 8 hours a day can produce 960 units in 10 days. After 4 days, 3 machines break down, and the remaining machines work 10 hours a day with 15% reduced efficiency. How many additional days are needed to complete the production?

The correct answer is

$7\frac{9}{17}$ days

Understanding the Machine Production Problem

This problem involves calculating the time required to complete a production target given initial conditions, followed by changes in the number of machines, working hours, and efficiency.

Initial Production Rate Calculation

First, let's determine the rate at which the machines produce units.

  • Number of machines (M1): 12
  • Hours per day (H1): 8
  • Number of days (D1): 10
  • Total units produced (U1): 960

The total work done can be represented as the product of machines, hours per day, and days. We can assume the production rate (units per machine-hour) is constant initially.

Total machine-hours = M1 $\times$ H1 $\times$ D1 = 12 $\times$ 8 $\times$ 10 = 960 machine-hours.

The production rate is calculated as:

Rate = Total Units / Total Machine-hours = 960 units / 960 machine-hours = 1 unit per machine-hour.

Production in the First 4 Days

The machines work under the initial conditions for the first 4 days.

  • Number of machines: 12
  • Hours per day: 8
  • Number of days: 4

Machine-hours in the first 4 days = 12 machines $\times$ 8 hours/day $\times$ 4 days = 384 machine-hours.

Units produced in the first 4 days = Rate $\times$ Machine-hours = 1 unit/machine-hour $\times$ 384 machine-hours = 384 units.

Remaining Production Calculation

Now, we need to find out how many units are left to be produced.

Total units required = 960 units.

Units produced in the first 4 days = 384 units.

Remaining units = 960 units - 384 units = 576 units.

Calculating Production Under New Conditions

After 4 days, the conditions change:

  • Number of machines break down: 3
  • Remaining machines (M2): 12 - 3 = 9
  • New hours per day (H2): 10
  • Efficiency reduced by 15%, so new efficiency (E2) = 100% - 15% = 85% = 0.85.

The effective work done per day by the remaining machines needs to be calculated.

Effective machine-hours per day = M2 $\times$ H2 $\times$ E2

Effective machine-hours per day = 9 machines $\times$ 10 hours/day $\times$ 0.85

Effective machine-hours per day = 90 $\times$ 0.85 = 76.5 effective machine-hours per day.

Calculating Additional Days Needed

We need to produce the remaining 576 units with the new conditions.

The production rate remains 1 unit per (effective) machine-hour.

Total effective machine-hours required = Remaining units / Rate

Total effective machine-hours required = 576 units / (1 unit/machine-hour) = 576 effective machine-hours.

Additional days needed (D2) = Total effective machine-hours required / Effective machine-hours per day

D2 = 576 / 76.5

To simplify the division, we can write 76.5 as $\frac{153}{2}$:

D2 = $\frac{576}{\frac{153}{2}} = \frac{576 \times 2}{153} = \frac{1152}{153}$

Now, simplify the fraction. Both numbers are divisible by 3:

$\frac{1152 \div 3}{153 \div 3} = \frac{384}{51}$

Both numbers are again divisible by 3:

$\frac{384 \div 3}{51 \div 3} = \frac{128}{17}$

Convert the improper fraction to a mixed number:

128 $\div$ 17 = 7 with a remainder of 9 (since $17 \times 7 = 119$, and $128 - 119 = 9$).

So, D2 = $7\frac{9}{17}$ days.

Conclusion

The number of additional days needed to complete the production is $7\frac{9}{17}$ days.

Was this answer helpful?

Important Questions from Time & Work (Notes)

  1. A fresh water tap fills a fish tank in 40 minutes. The same tank is filled by a salt water tap in 120 minutes. If both the taps are open, how many minutes will it take to fill the tank?
  2. A completes $\frac{7}{10}$ of a work in 15 days and then he completes the remaining work with the help of B in 5 days. In how many days can A and B together complete the entire work?
  3. Aman can do 50% of the job in 16 days, and Bhanu can do 25% of the job in 24 days. In how many days can they do $\frac{1}{4}^{th}$  of the job working together ?

  4. X can finish a job in $141$ days. He worked for $57$ days alone and the remaining work was completed by Y, in $84$ days. How many days would both together take to complete the entire job?
  5. Ravina, Sujata, and Saroj can complete a work of painting separately in 32, 48, and 64 hours, respectively. They started working together, but Saroj left after 5 hours. From the 6th hour, Ravina and Sujata decided to work on alternate hours starting with Ravina. In how much time will the entire work of painting be completed?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App