All Exams Test series for 1 year @ ₹349 only
Question

X boys can do a work in 80 days. In how much time, 2X boys will do half of the same work?

The correct answer is

20 days

Solving Work and Time Problems: X Boys and 2X Boys

This question involves a classic scenario in work and time problems where the number of workers and the amount of work change, and we need to find the new time taken. The core principle is that the total work done is proportional to the number of workers and the time they spend working, assuming their efficiency is constant.

Understanding the Relationship between Men, Work, and Time

In problems like this, we often use the formula based on the idea that Men $\times$ Days $\times$ Efficiency = Work. If efficiency is constant (or the same for all workers), we can simplify this. For two different scenarios doing the same work, we have $M_1 \times D_1 = M_2 \times D_2$. If the work done is different, the relationship becomes $M_1 \times D_1 \times W_2 = M_2 \times D_2 \times W_1$, where $W_1$ and $W_2$ represent the amounts of work in scenario 1 and scenario 2, respectively.

Setting Up the Problem

Let's break down the given information into two scenarios:

Scenario 1: The Initial Condition

  • Number of boys ($M_1$): X
  • Time taken ($D_1$): 80 days
  • Amount of work done ($W_1$): Let's consider this as 1 unit of work (the full work).

Scenario 2: The New Condition

  • Number of boys ($M_2$): 2X
  • Time taken ($D_2$): This is what we need to find. Let's call it T days.
  • Amount of work done ($W_2$): Half of the same work, which is 0.5 units (or $\frac{1}{2}$).

Applying the Work-Time Formula

We will use the formula that relates men, days, and work done for two scenarios:

\( M_1 \times D_1 \times W_2 = M_2 \times D_2 \times W_1 \)

Step-by-Step Calculation

Now, let's substitute the values from our scenarios into the formula:

\( X \times 80 \times 0.5 = 2X \times T \times 1 \)

Simplify both sides of the equation:

Left side: \( X \times 80 \times 0.5 = 80X \times 0.5 = 40X \)

Right side: \( 2X \times T \times 1 = 2XT \)

So the equation becomes:

\( 40X = 2XT \)

We need to solve for T. We can divide both sides by 2X (assuming X is not zero, which it must be for there to be boys working):

\( \frac{40X}{2X} = T \)

\( \frac{40}{2} = T \)

\( 20 = T \)

So, the time taken by 2X boys to do half of the work is 20 days.

Conclusion

Using the relationship between the number of workers, time, and the amount of work, we found that 2X boys will take 20 days to complete half of the work that X boys completed in 80 days.

Scenario Number of Boys (M) Time (D) Work (W)
1 X 80 days 1 (full work)
2 2X T days 0.5 (half work)

Revision Table: Work and Time Concepts

Concept Explanation Formula (Constant Work) Formula (Different Work)
Inverse Proportionality More workers means less time for the same work (and vice versa), assuming constant efficiency. \(M_1 D_1 = M_2 D_2\) \(M_1 D_1 W_2 = M_2 D_2 W_1\)
Direct Proportionality More work means more time for the same number of workers (and vice versa), assuming constant efficiency. N/A \( \frac{W_1}{D_1} = \frac{W_2}{D_2} \) (for constant M)
Combined Proportionality Work is proportional to the product of Men and Time. N/A \( \frac{M_1 D_1}{W_1} = \frac{M_2 D_2}{W_2} \)

Additional Information: Efficiency in Work Problems

Sometimes, work and time problems introduce the concept of efficiency. If the efficiency of workers is different, the formula expands to include efficiency (E). The total work done would be proportional to Men $\times$ Days $\times$ Efficiency. For two scenarios with potentially different efficiencies:

\( M_1 \times D_1 \times E_1 \times W_2 = M_2 \times D_2 \times E_2 \times W_1 \)

In this particular problem, since all workers are referred to simply as 'boys' without any mention of different capabilities, we assume their efficiency is the same ($E_1 = E_2$), which is why the efficiency term cancels out and we can use the simplified formula \( M_1 \times D_1 \times W_2 = M_2 \times D_2 \times W_1 \).

Always carefully read the question to identify if efficiency is a factor to consider. If not mentioned, assume identical efficiency for all workers of the same type.

Was this answer helpful?

Important Questions from Work Efficiency

  1. A and B working together can complete a job in 30 days. The ratio of their efficiencies is 3 : 2. In how many days can the faster person complete the job?

  2. A takes 15 days to complete \(\frac{5}{7} \)  of a work. With the help of B, they finish the whole work in 12 days. In how many days, B alone will complete the same work

  3. A alone can complete a work in 14 days and B alone can complete the same work in 21 days. A and B start the work together but A leaves the work after 4 days of the starting of work. In how many days B will complete the remaining work?

  4. For completing a certain work, A is 50% less efficient than B and B is 50% more efficient than C. Working together A, B and C can complete the work in 48 days. A alone can complete the same work in:

  5. 30 persons can do a piece of work in 24 days. How many more persons are required to complete the work in 20 days?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App