Tushar, Megha, Punam and Richa can complete a piece of work in 10 days, 12 days, 15 days and 18 days, respectively. In how many days will the work be completed if each of them work on alternate days starting with Megha on first day, Punam on second day, Richa on third day, Tushar on fourth day and then again Megha on fifth day and so on.
13
This problem involves four individuals, Tushar, Megha, Punam, and Richa, working on a task on alternate days following a specific sequence. We are given the time each person takes to complete the entire work individually and need to find the total time taken when they work in a rotating pattern.
To solve problems involving work and time, it's helpful to determine the amount of work each person can complete in a single day. This is often called their work rate or efficiency. We can assume a total amount of work that is a common multiple of all the individual times. The Least Common Multiple (LCM) is a convenient choice.
Let's find the LCM of 10, 12, 15, and 18.
LCM(10, 12, 15, 18) = 2² × 3² × 5 = 4 × 9 × 5 = 180.
Let the total work be 180 units.
Now, we can calculate the daily work rate for each person:
The individuals work on alternate days in a specific sequence:
This sequence of 4 days constitutes one complete cycle. After Day 4, the sequence repeats starting with Megha on Day 5.
Let's calculate the total work done in one 4-day cycle:
Total work done in 1 cycle (4 days) = \(15 + 12 + 10 + 18 = 55\) units.
The total work to be completed is 180 units. In each 4-day cycle, 55 units of work are completed. We need to find how many cycles are required to complete 180 units.
Number of full cycles = Total work / Work per cycle
Number of full cycles = \(180 / 55\)
\(180 \div 55 \approx 3.27\). This means 3 full cycles are completed, and some work remains.
Work done in 3 full cycles = 3 cycles × 55 units/cycle = 165 units.
Days taken for 3 full cycles = 3 cycles × 4 days/cycle = 12 days.
Remaining work = Total work - Work done in 3 cycles
Remaining work = \(180 - 165 = 15\) units.
After 12 days (3 full cycles), the next day is Day 13, and the sequence restarts with Megha.
On Day 13, Megha works. Her daily work rate is 15 units/day.
The remaining work is 15 units.
Time taken by Megha to complete the remaining 15 units = Remaining work / Megha's daily rate
Time taken = \(15 \text{ units} / 15 \text{ units/day} = 1\) day.
So, Megha completes the remaining work on Day 13.
Total number of days to complete the work = Days for full cycles + Days for remaining work
Total number of days = 12 days + 1 day = 13 days.
| Day | Worker | Work Done (units) | Cumulative Work (units) |
|---|---|---|---|
| 1 | Megha | 15 | 15 |
| 2 | Punam | 12 | \(15 + 12 = 27\) |
| 3 | Richa | 10 | \(27 + 10 = 37\) |
| 4 | Tushar | 18 | \(37 + 18 = 55\) |
| 5 | Megha | 15 | \(55 + 15 = 70\) |
| ... | ... | ... | ... |
| 12 (End of Cycle 3) | Tushar | 18 | \(55 \times 3 = 165\) |
| 13 (Start of Cycle 4) | Megha | 15 | \(165 + 15 = 180\) |
The work is completed exactly on Day 13.
By calculating the individual work rates, the work done in one complete cycle, and determining the remaining work after full cycles, we found that the total time taken to complete the work when they work on alternate days in the given sequence is 13 days.
| Concept | Description | Formula |
|---|---|---|
| Work Rate | Amount of work done per unit of time (e.g., per day). | Work Rate = Total Work / Time Taken |
| Total Work | The total amount of task to be completed. Often assumed as the LCM of individual times. | - |
| Time Taken | The duration required to complete the work. | Time Taken = Total Work / Work Rate |
| Work Done in 'n' Days | If a person's daily rate is 'r', work done in 'n' days is \(n \times r\). | Work Done = Rate × Time |
| Alternate Days Work | Individuals work on different days or in a specific sequence. Calculate work done in one complete cycle of the sequence. | Sum of work rates of individuals in one cycle duration. |
The concept of efficiency (work rate) is fundamental in solving work and time problems. Efficiency is inversely proportional to the time taken; more efficient individuals take less time. Using the LCM of the given times as the total work simplifies calculations, as it results in integer values for daily work rates.
In alternate day problems, identifying the repeating cycle of workers and calculating the work done within that cycle is crucial. This allows you to determine how many cycles are needed to complete most of the work and then calculate the time required for the remaining work based on the sequence of workers after the last full cycle.
A and B together can complete a certain work in 20 days whereas B and C together can complete it in 24 days. If A is twice as good a workman as C, then in what time will B alone do 40% of the same work?
14 men can complete a work in 15 days. If 21 men are employed, then in how many days will they complete the same work?
A can do a certain work in 15 days, while B can do the same work in 21 days. If they work together, then in how many days will the same work be completed?
To do a certain work, A and B work on alternate days with B beginning the work on the first day. A alone can complete the same work in 24 days. If the work gets completed in \(11 \frac{1}{3}\) days, then B alone can complete \(\rm \frac{7}{9}^{th}\) part of the original work in:
Two men and 7 women can complete a work in 28 days whereas 6 men and 16 women can do the same work in 11 days. In how many days can 7 men complete the same work?