All Exams Test series for 1 year @ ₹349 only
Question

Tushar, Megha, Punam and Richa can complete a piece of work in 10 days, 12 days, 15 days and 18 days, respectively. In how many days will the work be completed if each of them work on alternate days starting with Megha on first day, Punam on second day, Richa on third day, Tushar on fourth day and then again Megha on fifth day and so on.

The correct answer is

13

Understanding the Work and Time Problem

This problem involves four individuals, Tushar, Megha, Punam, and Richa, working on a task on alternate days following a specific sequence. We are given the time each person takes to complete the entire work individually and need to find the total time taken when they work in a rotating pattern.

Calculating Individual Work Rates (Efficiency)

To solve problems involving work and time, it's helpful to determine the amount of work each person can complete in a single day. This is often called their work rate or efficiency. We can assume a total amount of work that is a common multiple of all the individual times. The Least Common Multiple (LCM) is a convenient choice.

  • Time taken by Tushar = 10 days
  • Time taken by Megha = 12 days
  • Time taken by Punam = 15 days
  • Time taken by Richa = 18 days

Let's find the LCM of 10, 12, 15, and 18.

  • Prime factorization of 10 = 2 × 5
  • Prime factorization of 12 = 2² × 3
  • Prime factorization of 15 = 3 × 5
  • Prime factorization of 18 = 2 × 3²

LCM(10, 12, 15, 18) = 2² × 3² × 5 = 4 × 9 × 5 = 180.

Let the total work be 180 units.

Now, we can calculate the daily work rate for each person:

  • Tushar's daily work rate = Total work / Time taken = \(180 / 10\) = 18 units/day
  • Megha's daily work rate = Total work / Time taken = \(180 / 12\) = 15 units/day
  • Punam's daily work rate = Total work / Time taken = \(180 / 15\) = 12 units/day
  • Richa's daily work rate = Total work / Time taken = \(180 / 18\) = 10 units/day

Work Done in One Cycle of Alternate Days

The individuals work on alternate days in a specific sequence:

  1. Day 1: Megha
  2. Day 2: Punam
  3. Day 3: Richa
  4. Day 4: Tushar

This sequence of 4 days constitutes one complete cycle. After Day 4, the sequence repeats starting with Megha on Day 5.

Let's calculate the total work done in one 4-day cycle:

  • Work done on Day 1 (Megha) = 15 units
  • Work done on Day 2 (Punam) = 12 units
  • Work done on Day 3 (Richa) = 10 units
  • Work done on Day 4 (Tushar) = 18 units

Total work done in 1 cycle (4 days) = \(15 + 12 + 10 + 18 = 55\) units.

Calculating the Total Number of Days

The total work to be completed is 180 units. In each 4-day cycle, 55 units of work are completed. We need to find how many cycles are required to complete 180 units.

Number of full cycles = Total work / Work per cycle

Number of full cycles = \(180 / 55\)

\(180 \div 55 \approx 3.27\). This means 3 full cycles are completed, and some work remains.

Work done in 3 full cycles = 3 cycles × 55 units/cycle = 165 units.

Days taken for 3 full cycles = 3 cycles × 4 days/cycle = 12 days.

Remaining work = Total work - Work done in 3 cycles

Remaining work = \(180 - 165 = 15\) units.

After 12 days (3 full cycles), the next day is Day 13, and the sequence restarts with Megha.

On Day 13, Megha works. Her daily work rate is 15 units/day.

The remaining work is 15 units.

Time taken by Megha to complete the remaining 15 units = Remaining work / Megha's daily rate

Time taken = \(15 \text{ units} / 15 \text{ units/day} = 1\) day.

So, Megha completes the remaining work on Day 13.

Total number of days to complete the work = Days for full cycles + Days for remaining work

Total number of days = 12 days + 1 day = 13 days.

Day Worker Work Done (units) Cumulative Work (units)
1 Megha 15 15
2 Punam 12 \(15 + 12 = 27\)
3 Richa 10 \(27 + 10 = 37\)
4 Tushar 18 \(37 + 18 = 55\)
5 Megha 15 \(55 + 15 = 70\)
... ... ... ...
12 (End of Cycle 3) Tushar 18 \(55 \times 3 = 165\)
13 (Start of Cycle 4) Megha 15 \(165 + 15 = 180\)

The work is completed exactly on Day 13.

Conclusion

By calculating the individual work rates, the work done in one complete cycle, and determining the remaining work after full cycles, we found that the total time taken to complete the work when they work on alternate days in the given sequence is 13 days.

Revision Table: Work and Time Concepts

Concept Description Formula
Work Rate Amount of work done per unit of time (e.g., per day). Work Rate = Total Work / Time Taken
Total Work The total amount of task to be completed. Often assumed as the LCM of individual times. -
Time Taken The duration required to complete the work. Time Taken = Total Work / Work Rate
Work Done in 'n' Days If a person's daily rate is 'r', work done in 'n' days is \(n \times r\). Work Done = Rate × Time
Alternate Days Work Individuals work on different days or in a specific sequence. Calculate work done in one complete cycle of the sequence. Sum of work rates of individuals in one cycle duration.

Additional Information: Efficiency and LCM in Work Problems

The concept of efficiency (work rate) is fundamental in solving work and time problems. Efficiency is inversely proportional to the time taken; more efficient individuals take less time. Using the LCM of the given times as the total work simplifies calculations, as it results in integer values for daily work rates.

In alternate day problems, identifying the repeating cycle of workers and calculating the work done within that cycle is crucial. This allows you to determine how many cycles are needed to complete most of the work and then calculate the time required for the remaining work based on the sequence of workers after the last full cycle.

Was this answer helpful?

Important Questions from Work Efficiency

  1. A and B together can complete a certain work in 20 days whereas B and C together can complete it in 24 days. If A is twice as good a workman as C, then in what time will B alone do 40% of the same work?

  2. 14 men can complete a work in 15 days. If 21 men are employed, then in how many days will they complete the same work?

  3. A can do a certain work in 15 days, while B can do the same work in 21 days. If they work together, then in how many days will the same work be completed?

  4. To do a certain work, A and B work on alternate days with B beginning the work on the first day. A alone can complete the same work in 24 days. If the work gets completed in  \(11 \frac{1}{3}\)  days, then B alone can complete  \(\rm \frac{7}{9}^{th}\)  part of the original work in:

  5. Two men and 7 women can complete a work in 28 days whereas 6 men and 16 women can do the same work in 11 days. In how many days can 7 men complete the same work?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App