All Exams Test series for 1 year @ ₹349 only
Question

X, Y and Z can complete a piece of work individually in 6 hours, 8 hours and 8 hours respectively. However, only one person at a time can work in each hour and nobody can work for two consecutive hours. All are engaged to finish the work. What is the minimum amount of time that they will take to finish the work.

The correct answer is

6 hours 45 minutes

Understanding the Work and Time Problem

The question asks for the minimum time required for three individuals, X, Y, and Z, to complete a piece of work. We are given their individual times to complete the work, and specific constraints on how they can work together:

  • Only one person works in any given hour.
  • No single person can work for two hours in a row (no consecutive hours).
  • All three individuals (X, Y, and Z) must be involved in completing the work.

Our goal is to find the most efficient working pattern that satisfies these rules and determines the shortest possible time to finish the entire work.

Calculating Individual Work Rates

First, let's determine how much work each person can complete in one hour. This is their work rate.

  • X can complete the work in 6 hours. So, X's work rate is \(\frac{1}{6}\) of the work per hour.
  • Y can complete the work in 8 hours. So, Y's work rate is \(\frac{1}{8}\) of the work per hour.
  • Z can complete the work in 8 hours. So, Z's work rate is \(\frac{1}{8}\) of the work per hour.

The rates are: X (\(\frac{1}{6}\)), Y (\(\frac{1}{8}\)), Z (\(\frac{1}{8}\)). X is the fastest worker.

Finding the Optimal Working Pattern

To minimize the total time, we need to maximize the amount of work done in each hour, given the constraints. The constraint that no one can work for two consecutive hours means we must alternate workers every hour.

Since X is the fastest worker, we should try to use X as frequently as possible. Under the alternating rule, X can work every other hour. In the hours X is not working, Y and Z must take turns (since all are engaged and must alternate with X and each other). A pattern like X, Y, X, Z, X, Y, X, Z... seems efficient because it uses X every second hour and alternates between Y and Z in the hours X is resting. This pattern satisfies all conditions:

  • Only one person works per hour.
  • No one works consecutively (X is followed by Y or Z, Y is followed by X, Z is followed by X).
  • All three workers (X, Y, Z) are engaged in this repeating pattern.

Step-by-Step Calculation of Work Done

Let's calculate the work done hour by hour following the pattern X, Y, X, Z, X, Y, X, Z...:

Hour Worker Work Done in Hour Total Work Done Remaining Work
1 X \(\frac{1}{6}\) \(\frac{1}{6}\) \(1 - \frac{1}{6} = \frac{5}{6}\)
2 Y \(\frac{1}{8}\) \(\frac{1}{6} + \frac{1}{8} = \frac{4+3}{24} = \frac{7}{24}\) \(1 - \frac{7}{24} = \frac{17}{24}\)
3 X \(\frac{1}{6}\) \(\frac{7}{24} + \frac{1}{6} = \frac{7+4}{24} = \frac{11}{24}\) \(1 - \frac{11}{24} = \frac{13}{24}\)
4 Z \(\frac{1}{8}\) \(\frac{11}{24} + \frac{1}{8} = \frac{11+3}{24} = \frac{14}{24} = \frac{7}{12}\) \(1 - \frac{7}{12} = \frac{5}{12}\)
5 X \(\frac{1}{6}\) \(\frac{7}{12} + \frac{1}{6} = \frac{7+2}{12} = \frac{9}{12} = \frac{3}{4}\) \(1 - \frac{3}{4} = \frac{1}{4}\)
6 Y \(\frac{1}{8}\) \(\frac{3}{4} + \frac{1}{8} = \frac{6+1}{8} = \frac{7}{8}\) \(1 - \frac{7}{8} = \frac{1}{8}\)

After 6 hours, \(\frac{7}{8}\) of the work is completed, and \(\frac{1}{8}\) work remains. The pattern dictates that X works in the 7th hour.

Remaining work = \(\frac{1}{8}\).

X's work rate = \(\frac{1}{6}\) work per hour.

Time needed by X to complete the remaining \(\frac{1}{8}\) work = \(\frac{\text{Remaining Work}}{\text{X's Rate}} = \frac{\frac{1}{8}}{\frac{1}{6}}\) hours.

Calculating the time: \(\frac{1}{8} \times \frac{6}{1} = \frac{6}{8} = \frac{3}{4}\) hours.

Convert the fraction of an hour to minutes: \(\frac{3}{4} \times 60\) minutes = 45 minutes.

So, the work finishes after 6 full hours and an additional 45 minutes into the 7th hour.

Conclusion: Minimum Time to Finish the Work

The total minimum time taken to finish the work following the optimal pattern is 6 hours and 45 minutes.

Revision Table: Work and Time Concepts

Concept Description Formula
Work Rate The amount of work done by a person per unit of time. Rate = \(\frac{1}{\text{Time Taken}}\)
Total Work Usually considered as 1 unit. Work = Rate \(\times\) Time
Time Taken Total time to complete the work. Time = \(\frac{\text{Total Work}}{\text{Combined Rate}}\) (for simultaneous work) or calculated based on individual contributions over time.
Alternating Work Workers take turns, often calculated based on cycles of work done by a group. Calculate work done in one cycle, then find number of cycles and remaining work.

Additional Information: Work and Time Efficiency

In work and time problems with constraints like alternating work or non-consecutive hours, the most efficient strategy typically involves having the most efficient worker (the one with the highest rate) work for the largest possible share of the total time, while still adhering to the rules. By having X work every other hour and alternating the less efficient workers Y and Z in the gaps, we ensure X's higher rate contributes significantly to completing the work quickly. The 'all engaged' rule confirms that no worker can be left out entirely from the process.

Was this answer helpful?

Important Questions from Miscellaneous Topics

  1. Which one of the following statements best reflects the critical message conveyed by the author of the passage?

  2. With reference to the above passage, the following assumptions have been made:
    I. No country needs to depend on ecosystems to boost national income.
    II. Resource-rich countries need to share their resources with those of scant resources so as to prevent the degradation of ecosystems.
    Which of the above assumptions is/are valid?

  3. Which one of the following statements best reflects the central idea of the passage?

  4. With reference to the above passage, the following assumptions have been made:
    I. Path-dependent green investments will eventually most likely benefit growth as well as public finances in a country like India.
    II. If other green technologies follow the same pattern as that of solar energy, there will most likely be an easy green transition.
    Which of the above assumptions is/are valid?

  5. Three prime numbers p, q and r, each less than 20, are such that p − q = q − r. How many distinct possible values can we get for (p + q + r)?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App