Rohit and Mohit can do a piece of work in 4 days, while Ram and Shyam can do the same work in 12 days. In how many days will Rohit, Mohit, Ram and Shyam do it together?
3 days
In work and time problems, we often calculate the amount of work done by a person or a group in a single unit of time (like a day or an hour). This is called their work rate or efficiency. The total work is usually considered as 1 unit.
The relationship is: Work = Rate × Time. Therefore, Rate = \( \frac{\text{Work}}{\text{Time}} \) and Time = \( \frac{\text{Work}}{\text{Rate}} \).
Let's find the daily work rate for each group mentioned in the problem:
Their combined work rate per day is \( \frac{1}{\text{Time taken}} = \frac{1}{4} \) of the total work.
Their combined work rate per day is \( \frac{1}{\text{Time taken}} = \frac{1}{12} \) of the total work.
When Rohit, Mohit, Ram, and Shyam work together, their combined daily work rate is the sum of the work rate of Rohit & Mohit and the work rate of Ram & Shyam.
Combined work rate of Rohit, Mohit, Ram, and Shyam = Work rate of (Rohit + Mohit) + Work rate of (Ram + Shyam)
Combined work rate = \( \frac{1}{4} + \frac{1}{12} \)
To add these fractions, we find a common denominator, which is 12.
Combined work rate = \( \frac{1 \times 3}{4 \times 3} + \frac{1}{12} = \frac{3}{12} + \frac{1}{12} \)
Combined work rate = \( \frac{3 + 1}{12} = \frac{4}{12} \)
Simplifying the fraction:
Combined work rate = \( \frac{1}{3} \) of the work per day.
If the combined daily work rate of Rohit, Mohit, Ram, and Shyam is \( \frac{1}{3} \) of the work per day, then the time taken to complete the whole work (which is 1 unit of work) is the reciprocal of their combined work rate.
Time taken together = \( \frac{\text{Total Work}}{\text{Combined Work Rate}} = \frac{1}{\frac{1}{3}} \)
Time taken together = \( 1 \times 3 = 3 \) days.
So, Rohit, Mohit, Ram, and Shyam will do the work together in 3 days.
| Group | Time Taken (Days) | Daily Work Rate (Fraction of work) |
|---|---|---|
| Rohit & Mohit | 4 | \( \frac{1}{4} \) |
| Ram & Shyam | 12 | \( \frac{1}{12} \) |
| Rohit, Mohit, Ram & Shyam (Together) | ? | \( \frac{1}{4} + \frac{1}{12} = \frac{3}{12} + \frac{1}{12} = \frac{4}{12} = \frac{1}{3} \) |
Time taken together = \( \frac{1}{\text{Combined Daily Work Rate}} = \frac{1}{\frac{1}{3}} = 3 \) days.
| Concept | Explanation | Formula/Relation |
|---|---|---|
| Work Rate | Amount of work done per unit time (e.g., per day, per hour). | Rate = \( \frac{\text{Work}}{\text{Time}} \) |
| Total Work | The entire task to be completed, often represented as 1 unit. | Work = Rate × Time |
| Time Taken | The duration required to complete the work. | Time = \( \frac{\text{Work}}{\text{Rate}} \) |
| Combined Rate | Sum of individual rates when multiple people/groups work together. | Rate\(_{\text{total}}\) = Rate\(_{1}\) + Rate\(_{2}\) + ... |
Work and time problems are common in quantitative aptitude tests. They often involve calculating how long it takes individuals or groups to complete a task, or how much work is done in a specific time.
Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?
A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?
24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?
A and B together can do a piece of work in 4 days, B and C can do it in 6 days, A and C can do it in 8 days. Then A, B and C together can do the same work in :-
A can complete 50% of a work in 9 days and B can do 25% of the work in 9 days, if they work alone. If they work together then how much work (in percentage) can be completed in 6 days?