All Exams Test series for 1 year @ ₹349 only
Question

Rohit and Mohit can do a piece of work in 4 days, while Ram and Shyam can do the same work in 12 days. In how many days will Rohit, Mohit, Ram and Shyam do it together?

The correct answer is

3 days

Understanding Work and Time Problems

In work and time problems, we often calculate the amount of work done by a person or a group in a single unit of time (like a day or an hour). This is called their work rate or efficiency. The total work is usually considered as 1 unit.

The relationship is: Work = Rate × Time. Therefore, Rate = \( \frac{\text{Work}}{\text{Time}} \) and Time = \( \frac{\text{Work}}{\text{Rate}} \).

Calculating Individual and Combined Work Rates

Let's find the daily work rate for each group mentioned in the problem:

  • Rohit and Mohit together: They can do the work in 4 days.

Their combined work rate per day is \( \frac{1}{\text{Time taken}} = \frac{1}{4} \) of the total work.

  • Ram and Shyam together: They can do the same work in 12 days.

Their combined work rate per day is \( \frac{1}{\text{Time taken}} = \frac{1}{12} \) of the total work.

Finding the Combined Work Rate of All Four

When Rohit, Mohit, Ram, and Shyam work together, their combined daily work rate is the sum of the work rate of Rohit & Mohit and the work rate of Ram & Shyam.

Combined work rate of Rohit, Mohit, Ram, and Shyam = Work rate of (Rohit + Mohit) + Work rate of (Ram + Shyam)

Combined work rate = \( \frac{1}{4} + \frac{1}{12} \)

To add these fractions, we find a common denominator, which is 12.

Combined work rate = \( \frac{1 \times 3}{4 \times 3} + \frac{1}{12} = \frac{3}{12} + \frac{1}{12} \)

Combined work rate = \( \frac{3 + 1}{12} = \frac{4}{12} \)

Simplifying the fraction:

Combined work rate = \( \frac{1}{3} \) of the work per day.

Calculating Time Taken When All Four Work Together

If the combined daily work rate of Rohit, Mohit, Ram, and Shyam is \( \frac{1}{3} \) of the work per day, then the time taken to complete the whole work (which is 1 unit of work) is the reciprocal of their combined work rate.

Time taken together = \( \frac{\text{Total Work}}{\text{Combined Work Rate}} = \frac{1}{\frac{1}{3}} \)

Time taken together = \( 1 \times 3 = 3 \) days.

So, Rohit, Mohit, Ram, and Shyam will do the work together in 3 days.

Summary of Calculations

Group Time Taken (Days) Daily Work Rate (Fraction of work)
Rohit & Mohit 4 \( \frac{1}{4} \)
Ram & Shyam 12 \( \frac{1}{12} \)
Rohit, Mohit, Ram & Shyam (Together) ? \( \frac{1}{4} + \frac{1}{12} = \frac{3}{12} + \frac{1}{12} = \frac{4}{12} = \frac{1}{3} \)

Time taken together = \( \frac{1}{\text{Combined Daily Work Rate}} = \frac{1}{\frac{1}{3}} = 3 \) days.

Revision Table: Work and Time Concepts

Concept Explanation Formula/Relation
Work Rate Amount of work done per unit time (e.g., per day, per hour). Rate = \( \frac{\text{Work}}{\text{Time}} \)
Total Work The entire task to be completed, often represented as 1 unit. Work = Rate × Time
Time Taken The duration required to complete the work. Time = \( \frac{\text{Work}}{\text{Rate}} \)
Combined Rate Sum of individual rates when multiple people/groups work together. Rate\(_{\text{total}}\) = Rate\(_{1}\) + Rate\(_{2}\) + ...

Additional Information on Work and Time Problems

Work and time problems are common in quantitative aptitude tests. They often involve calculating how long it takes individuals or groups to complete a task, or how much work is done in a specific time.

  • Assuming total work as the Least Common Multiple (LCM) of the time taken by individuals/groups can simplify calculations, especially when dealing with multiple people or varying efficiencies. In this case, the LCM of 4 and 12 is 12, which could represent 12 units of work.
  • If Rohit and Mohit do 12 units in 4 days, their rate is 3 units/day.
  • If Ram and Shyam do 12 units in 12 days, their rate is 1 unit/day.
  • Together, their rate is 3 + 1 = 4 units/day.
  • Time taken together = \( \frac{\text{Total Units}}{\text{Combined Rate}} = \frac{12}{4} = 3 \) days. This confirms the fractional method result.
  • Problems can also involve varying work rates, people leaving or joining, or calculating work done partially. Understanding the concept of daily work rate is key to solving all these variations.
Was this answer helpful?

Important Questions from Work Efficiency

  1. Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?

  2. A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?

  3. 24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?

  4. A and B together can do a piece of work in 4 days, B and C can do it in 6 days, A and C can do it in 8 days. Then A, B and C together can do the same work in :-

  5. A can complete 50% of a work in 9 days and B can do 25% of the work in 9 days, if they work alone. If they work together then how much work (in percentage) can be completed in 6 days?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App