All Exams Test series for 1 year @ ₹349 only
Question

Rashmi and Tina can do a piece of work in 20 and 30 days, respectively. If they work at it on alternate days with Rashmi beginning, then, in how many days will the work be over?

The correct answer is

24

Solving the Work and Time Problem with Alternate Days

This problem involves two individuals, Rashmi and Tina, working on a task on alternate days. Rashmi starts the work. We need to find the total number of days required to complete the entire work.

Understanding Individual Work Rates

First, let's determine how much work each person can do in a single day. This is their work rate.

  • Rashmi can do the work in 20 days. So, Rashmi's daily work rate is \( \frac{1}{20} \) of the total work per day.
  • Tina can do the work in 30 days. So, Tina's daily work rate is \( \frac{1}{30} \) of the total work per day.

Work Done in One Cycle (Two Days)

Since they work on alternate days with Rashmi starting, the work happens in cycles of two days:

  • Day 1: Rashmi works.
  • Day 2: Tina works.

Let's calculate the total amount of work done in one such two-day cycle.

Work done in 1 cycle = Work done by Rashmi on Day 1 + Work done by Tina on Day 2

Work done in 1 cycle = \( \frac{1}{20} + \frac{1}{30} \)

To add these fractions, we find a common denominator, which is 60.

\( \frac{1}{20} = \frac{1 \times 3}{20 \times 3} = \frac{3}{60} \)

\( \frac{1}{30} = \frac{1 \times 2}{30 \times 2} = \frac{2}{60} \)

Work done in 1 cycle = \( \frac{3}{60} + \frac{2}{60} = \frac{5}{60} = \frac{1}{12} \)

So, in every two-day cycle, \( \frac{1}{12} \) of the total work is completed.

Calculating the Number of Cycles

To complete the entire work (which is 1 unit of work), we need to figure out how many such two-day cycles are required.

If 1 cycle completes \( \frac{1}{12} \) of the work, then to complete 1 whole work, the number of cycles needed is:

Number of cycles = Total work ÷ Work done in 1 cycle

Number of cycles = \( 1 \div \frac{1}{12} = 1 \times \frac{12}{1} = 12 \)

So, exactly 12 cycles are needed to complete the work.

Total Days to Complete the Work

Each cycle consists of 2 days. Since 12 cycles are needed, the total number of days will be:

Total days = Number of cycles × Days per cycle

Total days = \( 12 \times 2 = 24 \) days

Let's quickly verify this:

  • After 11 cycles (22 days), \( 11 \times \frac{1}{12} = \frac{11}{12} \) of the work is done.
  • Remaining work = \( 1 - \frac{11}{12} = \frac{1}{12} \).
  • Day 23 is the start of the 12th cycle, which is Rashmi's turn. Rashmi does \( \frac{1}{20} \) work.
  • Work remaining after Day 23 = \( \frac{1}{12} - \frac{1}{20} \). Common denominator 60: \( \frac{5}{60} - \frac{3}{60} = \frac{2}{60} = \frac{1}{30} \).
  • Day 24 is Tina's turn. Tina's daily work rate is \( \frac{1}{30} \).
  • Tina completes the remaining \( \frac{1}{30} \) work on Day 24.
  • The work is finished exactly at the end of Day 24.

Therefore, the total number of days required to complete the work is 24 days.

Person Time to complete work Daily Work Rate
Rashmi 20 days \( \frac{1}{20} \)
Tina 30 days \( \frac{1}{30} \)

Period Days Work Done
1 cycle (R then T) 2 days \( \frac{1}{20} + \frac{1}{30} = \frac{1}{12} \)
12 cycles \( 12 \times 2 = 24 \) days \( 12 \times \frac{1}{12} = 1 \) (Total work)

Conclusion

By calculating the work done in a two-day cycle and determining the number of cycles needed, we find that the work is completed in 24 days when Rashmi and Tina work on alternate days starting with Rashmi.

Revision Table: Alternate Day Work Problems

Here's a quick review of the steps for alternate day work problems:

Step Action Purpose
1 Calculate individual daily work rates. Find how much each person does in 1 day.
2 Calculate work done in one cycle. Sum daily rates for the people in one sequence (e.g., Person A then Person B).
3 Determine the duration of one cycle. Usually the number of people in the sequence.
4 Find the number of full cycles to get close to the total work. Divide total work (usually 1) by work done in one cycle. Use the whole number part for full cycles.
5 Calculate work done after full cycles and remaining work. Multiply work per cycle by number of full cycles. Subtract from total work.
6 Determine who works on the next day(s). Follow the sequence based on who started.
7 Calculate time for remaining work. Divide remaining work by the daily rate of the person working next.
8 Calculate total days. Add days for full cycles and days for remaining work.

Additional Information: Work and Time Concepts

Work and time problems often involve calculating efficiency and combining work rates.

  • Efficiency: A person's efficiency is inversely proportional to the time taken to complete a task. More efficient people take less time.
  • Combined Work Rate: If two people A and B can do a work in \( t_A \) and \( t_B \) days respectively, their combined daily work rate when working together is \( \frac{1}{t_A} + \frac{1}{t_B} \). The total time taken together is \( \frac{1}{\frac{1}{t_A} + \frac{1}{t_B}} = \frac{t_A \times t_B}{t_A + t_B} \).
  • Alternate Days: As seen in this problem, the work is not continuous but happens in a sequence, requiring calculation based on cycles.

Understanding these basic concepts helps in solving various types of work and time problems.

Was this answer helpful?

Important Questions from Work Efficiency

  1. Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?

  2. A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?

  3. 24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?

  4. A and B together can do a piece of work in 4 days, B and C can do it in 6 days, A and C can do it in 8 days. Then A, B and C together can do the same work in :-

  5. A can complete 50% of a work in 9 days and B can do 25% of the work in 9 days, if they work alone. If they work together then how much work (in percentage) can be completed in 6 days?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App