All Exams Test series for 1 year @ ₹349 only
Question

Rajan does 7/11 of a work in 21 days. How many more days will he take to complete the work?

The correct answer is

(b) 12

Calculating Additional Days to Complete Work

This problem is about understanding the relationship between the amount of work done and the time taken, assuming a constant work rate. We are given that Rajan completes a fraction of the total work in a certain number of days and need to find out how many more days he requires to finish the remaining part.

Understanding the Work Done and Remaining Work

Rajan has completed $\frac{7}{11}$ of the total work. The total work can be considered as 1 whole or $\frac{11}{11}$.

The fraction of work remaining is calculated by subtracting the completed work from the total work:

Remaining Work = Total Work - Work Done

Remaining Work = $1 - \frac{7}{11}$

To subtract these fractions, we find a common denominator, which is 11.

Remaining Work = $\frac{11}{11} - \frac{7}{11}$

Remaining Work = $\frac{11 - 7}{11}$

Remaining Work = $\frac{4}{11}$

So, $\frac{4}{11}$ of the work is still left to be done by Rajan.

Relating Work Done and Time Taken

We are told that Rajan does $\frac{7}{11}$ of the work in 21 days. Assuming Rajan works at a constant pace, the time taken is directly proportional to the amount of work done. This means if he does more work, he takes more time, and vice versa, in direct proportion.

We can set up a proportion to find the total time required to complete the entire work, or directly find the time needed for the remaining work.

Method 1: Find total time first

Let $T$ be the total number of days required to complete the entire work ($\frac{11}{11}$ or 1).

The proportion is: $\frac{\text{Fraction of Work Done}}{\text{Time Taken}} = \text{Constant}$

Using the given information:

$$ \frac{7/11}{21 \text{ days}} = \frac{1}{T \text{ days}} $$

Simplifying the left side:

$$ \frac{7}{11 \times 21} = \frac{1}{T} $$ $$ \frac{7}{231} = \frac{1}{T} $$

Cross-multiplying to solve for $T$:

$$ T = \frac{231}{7} $$ $$ T = 33 \text{ days} $$

The total time required to complete the entire work is 33 days.

Rajan has already worked for 21 days. The number of more days he will take to complete the remaining work is:

More Days = Total Time - Time Already Spent

More Days = $33 \text{ days} - 21 \text{ days}$

More Days = $12 \text{ days}$

Method 2: Find time for remaining work directly

We know Rajan does $\frac{7}{11}$ of the work in 21 days.

Let $D$ be the number of days required to complete the remaining $\frac{4}{11}$ of the work.

Using the proportion: $\frac{\text{Fraction of Work 1}}{\text{Time 1}} = \frac{\text{Fraction of Work 2}}{\text{Time 2}}$

$$ \frac{7/11}{21 \text{ days}} = \frac{4/11}{D \text{ days}} $$

We can cancel the common denominator 11 from both numerators:

$$ \frac{7}{21} = \frac{4}{D} $$

Now, solve for $D$ by cross-multiplying:

$$ 7 \times D = 4 \times 21 $$ $$ 7D = 84 $$

Divide by 7:

$$ D = \frac{84}{7} $$ $$ D = 12 \text{ days} $$

Both methods show that Rajan will take 12 more days to complete the remaining work.

Conclusion on Additional Days Needed

Based on the calculations, Rajan needs 12 more days to complete the $\frac{4}{11}$ fraction of the work that is remaining.

Detail Value
Fraction of work done $\frac{7}{11}$
Time taken for work done 21 days
Fraction of work remaining $\frac{4}{11}$
Total time for work (calculated) 33 days
Additional days needed (calculated) 12 days

Revision Table: Work and Time Concepts

Concept Explanation
Work Rate The amount of work done per unit of time (e.g., fraction of work per day). Assumed constant unless specified otherwise.
Work and Time Relationship Work Done $\propto$ Time Taken (if rate is constant). Formula: Work Done = Rate $\times$ Time.
Total Work = 1 Often, the total work is represented as 1 whole unit.
Fraction of Work Represents a part of the total work. If $\frac{a}{b}$ work is done, then $1 - \frac{a}{b}$ is remaining.

Additional Information: Solving Work and Time Problems

Work and time problems often involve calculating the time taken by individuals or groups to complete a task, or the rate at which they work. A key assumption is usually that the work rate is constant.

  • If a person completes a work in $N$ days, their daily work rate is $\frac{1}{N}$ of the total work per day.
  • If a person completes a fraction of work, say $\frac{a}{b}$, in $D$ days, the time taken for the entire work can be found using proportionality or by finding the rate. Rate = $\frac{a/b}{D} = \frac{a}{bD}$ per day. Total time = $\frac{1}{\text{Rate}} = \frac{bD}{a}$ days.
  • When multiple people work together, their individual work rates are often added to find the combined work rate.
  • Efficiency can sometimes be a factor, which affects the work rate.

In problems like Rajan's, where a fraction of work is done, it's helpful to determine the rate of work. Rajan's rate is $\frac{7/11 \text{ work}}{21 \text{ days}} = \frac{7}{11 \times 21} = \frac{7}{231} = \frac{1}{33}$ work per day. This means he takes 33 days for the entire work. Since he finished 7/11 in 21 days, the remaining time for 4/11 work would be $\frac{4/11}{1/33} = \frac{4}{11} \times 33 = 4 \times 3 = 12$ days. This confirms the result.

Was this answer helpful?

Important Questions from Time and Work

  1. A man, a woman, and a boy can do a work in 6, 9, and 18 days respectively. How many boys must assist one man and one woman to do the work in 1 day?

  2. A, B, and C worked together for 5 days to build a wall and then B left the work. A and C together finished the remaining work in 5 days. In how many days can A and C working together finish building the whole wall if B alone can do it in 25 days?

  3. Three men can complete a work in 6 days and five women can complete the same work in 18 days. In how many days can 4 men and 10 women together complete the same work?

  4. Mother, daughter, and son can do a work in 3, 4, and 5 days respectively. How many days will they take to complete the work, if they work together?

  5. By looking in a mirror, it appears that it is 6:30 in the clock. What is the real time?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App