A man, a woman, and a boy can do a work in 6, 9, and 18 days respectively. How many boys must assist one man and one woman to do the work in 1 day?
13
This question involves the concept of work and time, specifically how individuals or groups with different efficiencies can complete a task. The key idea is to calculate the work done per unit of time (usually per day) by each person.
The work rate of a person is the fraction of the total work they can complete in one day. If a person takes 'd' days to complete the entire work, their 1-day work rate is \( \frac{1}{d} \).
We need to find the amount of work done by one man and one woman together in one day. This is the sum of their individual 1-day work rates.
Combined work rate of 1 man and 1 woman in 1 day \( = \) Man's rate \( + \) Woman's rate
\( = \frac{1}{6} + \frac{1}{9} \)
To add these fractions, we find a common denominator, which is the least common multiple (LCM) of 6 and 9. The LCM of 6 and 9 is 18.
\( = \frac{1 \times 3}{6 \times 3} + \frac{1 \times 2}{9 \times 2} = \frac{3}{18} + \frac{2}{18} \)
\( = \frac{3 + 2}{18} = \frac{5}{18} \)
So, one man and one woman together complete \( \frac{5}{18} \) of the total work in 1 day.
The goal is to complete the entire work (which is represented as 1 unit of work) in 1 day. One man and one woman complete \( \frac{5}{18} \) of the work in that day. The remaining work must be done by the boys in the same day.
Remaining work \( = \) Total work \( - \) Work done by 1 man and 1 woman
\( = 1 - \frac{5}{18} \)
\( = \frac{18}{18} - \frac{5}{18} = \frac{18 - 5}{18} = \frac{13}{18} \)
So, the boys must complete \( \frac{13}{18} \) of the total work in 1 day.
Each boy completes \( \frac{1}{18} \) of the work in 1 day. To find out how many boys are needed to complete the remaining \( \frac{13}{18} \) of the work in 1 day, we divide the remaining work by the work rate of a single boy.
Number of boys \( = \frac{\text{Remaining work}}{\text{Work rate of one boy}} \)
\( = \frac{13/18}{1/18} \)
\( = \frac{13}{18} \times \frac{18}{1} \)
\( = 13 \)
Therefore, 13 boys must assist one man and one woman to do the work in 1 day.
The final answer is 13.
| Concept | Explanation | Formula |
|---|---|---|
| Work Rate | Amount of work done per unit of time (e.g., per day). | If a person finishes work in \(d\) days, rate \( = \frac{1}{d}\) per day. |
| Total Work | Usually considered as 1 unit or the LCM of the days taken by individuals. | Total Work \( = \) Rate \( \times \) Time |
| Combined Rate | Sum of individual rates when people work together. | Rate\(_{\text{Total}}\) \( = \) Rate\(_{1}\) \( + \) Rate\(_{2}\) \( + \) ... |
| Time Taken Together | Time to complete the total work (1 unit) at the combined rate. | Time \( = \frac{1}{\text{Combined Rate}}\) |
Work and time problems often involve calculating efficiency and combining the efforts of multiple individuals or machines. Here are some points to remember:
A, B, and C worked together for 5 days to build a wall and then B left the work. A and C together finished the remaining work in 5 days. In how many days can A and C working together finish building the whole wall if B alone can do it in 25 days?
Three men can complete a work in 6 days and five women can complete the same work in 18 days. In how many days can 4 men and 10 women together complete the same work?
Mother, daughter, and son can do a work in 3, 4, and 5 days respectively. How many days will they take to complete the work, if they work together?
Rajan does 7/11 of a work in 21 days. How many more days will he take to complete the work?
By looking in a mirror, it appears that it is 6:30 in the clock. What is the real time?