All Exams Test series for 1 year @ ₹349 only
Question

If 9 men and 12 boys can do a piece of work in 4 days and 4 men and 16 boys can do the same piece of work in 6 days, how long will 6 men and 24 boys take to complete the same work?

The correct answer is

4 days

From the problem statement, we have two scenarios: 9 men and 12 boys can do the work in 4 days. Using the first scenario (9 men and 12 boys in 4 days):

Was this answer helpful?

Important Questions from Work Efficiency

  1. M is thrice as efficient as workman as N and therefore is able to finish a job in 264 days less than N. Then in how many days can N finish the entire work?
  2. A can do a piece of work in $1455$ days. B is $25\%$ more efficient than A. Find the number of days taken by B to do the same piece of work.
  3. 45 people take 18 days to dig a pond. If the pond would have to be dug in 15 days, then the number of people to be employed will be
  4. A stock of food is enough for 240 men for 48 days. How long will the same stock last for 160 men?
  5. One contractor had undertaken a construction work. To complete the given job, he sought labour comprising 24 men for 12 days for working 10 hours a day. But due to festival season, as the labour had gone to their respective hometowns, he could get only 15 men and they too were willing to work 8 hours a day. With this much labour, in how many days would he be able to complete the same job?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App