All Exams Test series for 1 year @ ₹349 only
Question

Hari and Mohan can do a work in 20 and 25 days respectively. After doing collectively 10 days of work, they leave the work due to illness and Shyam completes rest of the work in 3 days. How many days Shyam alone can take to complete the whole work?

The correct answer is

30 days

Work and Time Problem Solution

This solution will explain step-by-step how to determine the total number of days Shyam would take to complete the entire work alone, based on the contributions of Hari and Mohan. We will calculate individual work rates, combined work rates, and then use the remaining work to find Shyam's efficiency.

Hari's Work Rate

First, let's understand how much work Hari can do in one day. Hari can complete the entire work in 20 days. This means his daily work rate is the reciprocal of the total days he takes.

  • Hari's 1-day work = $\frac{1}{\text{Total days Hari takes}}$
  • Hari's 1-day work = $\frac{1}{20}$ of the total work

Mohan's Work Rate

Similarly, we calculate Mohan's daily work rate. Mohan can complete the entire work in 25 days.

  • Mohan's 1-day work = $\frac{1}{\text{Total days Mohan takes}}$
  • Mohan's 1-day work = $\frac{1}{25}$ of the total work

Combined Work Rate of Hari and Mohan

Next, we find their combined efficiency when they work together. To do this, we add their individual daily work rates.

  • Combined 1-day work of Hari and Mohan = Hari's 1-day work + Mohan's 1-day work
  • Combined 1-day work = $\frac{1}{20} + \frac{1}{25}$
  • To add these fractions, we find a common denominator, which is 100.
  • Combined 1-day work = $\frac{1 \times 5}{20 \times 5} + \frac{1 \times 4}{25 \times 4} = \frac{5}{100} + \frac{4}{100} = \frac{5+4}{100} = \frac{9}{100}$ of the total work

Work Completed by Hari and Mohan Together

Hari and Mohan work collectively for 10 days. We multiply their combined daily work rate by the number of days they worked.

  • Work done by Hari and Mohan in 10 days = Combined 1-day work $\times$ Number of days worked
  • Work done in 10 days = $\frac{9}{100} \times 10 = \frac{90}{100} = \frac{9}{10}$ of the total work

Remaining Work Calculation

After Hari and Mohan leave, Shyam completes the rest of the work. To find out how much work is remaining, we subtract the work already done from the total work (which is considered as 1 unit).

  • Remaining work = Total work - Work done by Hari and Mohan
  • Remaining work = $1 - \frac{9}{10} = \frac{10-9}{10} = \frac{1}{10}$ of the total work

Shyam's Daily Work Rate

Shyam completes this remaining work in 3 days. We can use this information to find Shyam's daily work rate.

  • Shyam's 1-day work = $\frac{\text{Remaining work}}{\text{Days Shyam took}}$
  • Shyam's 1-day work = $\frac{1/10}{3} = \frac{1}{10} \times \frac{1}{3} = \frac{1}{30}$ of the total work

Total Days for Shyam to Complete Work Alone

Finally, to find out how many days Shyam alone would take to complete the whole work, we take the reciprocal of Shyam's 1-day work rate.

  • Days Shyam alone takes = $\frac{1}{\text{Shyam's 1-day work}}$
  • Days Shyam alone takes = $\frac{1}{1/30} = 30$ days

Therefore, Shyam alone can complete the entire work in 30 days.


Person Days to complete work 1-day work rate
Hari 20 days $\frac{1}{20}$
Mohan 25 days $\frac{1}{25}$
Hari & Mohan (combined) N/A $\frac{1}{20} + \frac{1}{25} = \frac{9}{100}$


Step Description Calculation
1 Work done by Hari & Mohan in 10 days $10 \times \frac{9}{100} = \frac{9}{10}$
2 Remaining work $1 - \frac{9}{10} = \frac{1}{10}$
3 Shyam's 1-day work (for remaining work) $\frac{1/10}{3} = \frac{1}{30}$
4 Days Shyam alone takes to complete whole work $\frac{1}{1/30} = 30$ days
Was this answer helpful?

Important Questions from Work Efficiency

  1. Sumi can complete a job working 5 hours per day in 2 days. If she doubles her working hours per day, then in how many days will she complete the work?

  2. Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?

  3. A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?

  4. 24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?

  5. 3 men working 7 hours a day can complete a piece of work in 45 days. In how many days will 9 men working 6 hours a day complete the same work?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App