All Exams Test series for 1 year @ ₹349 only
Question

Diptesh and Tushar working separately can do a piece of work in 9 and 12 days respectively. If they work for a day alternately, Diptesh beginning, in how many days, the work will be completed?

The correct answer is

41/4

Solving Work and Time Problems with Alternate Working

This problem involves two individuals, Diptesh and Tushar, working alternately on a task. To solve such problems, we first need to determine their individual work rates and then calculate the work done in each cycle (a cycle includes one day for each person).

Understanding Individual Work Rates

The work rate is the amount of work a person can do in one day. If a person can complete a job in 'n' days, their one day work rate is \( \frac{1}{n} \) of the total work.

  • Diptesh can do the work in 9 days.
  • Diptesh's one day work rate = \( \frac{1}{9} \) of the total work.
  • Tushar can do the work in 12 days.
  • Tushar's one day work rate = \( \frac{1}{12} \) of the total work.

Calculating Work Done in One Cycle

They work alternately, with Diptesh beginning. A complete cycle consists of Diptesh working for one day and then Tushar working for one day. So, one cycle takes 2 days.

Work done in 1st day (by Diptesh) = \( \frac{1}{9} \)

Work done in 2nd day (by Tushar) = \( \frac{1}{12} \)

Work done in one cycle (2 days) = Work done by Diptesh + Work done by Tushar

Work done in one cycle = \( \frac{1}{9} + \frac{1}{12} \)

To add these fractions, we find a common denominator, which is the LCM of 9 and 12. LCM(9, 12) = 36.

\( \frac{1}{9} = \frac{1 \times 4}{9 \times 4} = \frac{4}{36} \)

\( \frac{1}{12} = \frac{1 \times 3}{12 \times 3} = \frac{3}{36} \)

Work done in one cycle (2 days) = \( \frac{4}{36} + \frac{3}{36} = \frac{4+3}{36} = \frac{7}{36} \)

So, in every 2-day cycle, \( \frac{7}{36} \) of the total work is completed.

Determining the Number of Full Cycles

We need to find out how many full cycles of 2 days can occur before the work is almost finished. The total work is considered as 1 unit. We want to find the number of cycles such that the work done is close to, but not exceeding, 1.

Let 'n' be the number of cycles. Work done in 'n' cycles = \( n \times \frac{7}{36} \).

We look for the largest 'n' such that \( n \times \frac{7}{36} \le 1 \).

If \( n=5 \), work done = \( 5 \times \frac{7}{36} = \frac{35}{36} \). This is less than 1.

If \( n=6 \), work done = \( 6 \times \frac{7}{36} = \frac{42}{36} \). This is greater than 1, meaning the work is completed within the 6th cycle.

Therefore, 5 full cycles are completed.

Calculating Work Done After Full Cycles and Remaining Work

After 5 full cycles (which take \( 5 \times 2 = 10 \) days), the work completed is \( \frac{35}{36} \).

Remaining work = Total work - Work done in 5 cycles

Remaining work = \( 1 - \frac{35}{36} = \frac{36}{36} - \frac{35}{36} = \frac{1}{36} \).

So, \( \frac{1}{36} \) of the work still needs to be done.

Completing the Remaining Work

After 5 cycles (10 days), the 11th day begins. The turn is for the person who started the work, which is Diptesh.

Diptesh's one day work rate is \( \frac{1}{9} \).

He needs to complete the remaining work of \( \frac{1}{36} \).

Time taken by Diptesh to complete \( \frac{1}{36} \) of the work = \( \frac{\text{Remaining Work}}{\text{Diptesh's One Day Work Rate}} \)

Time taken = \( \frac{\frac{1}{36}}{\frac{1}{9}} = \frac{1}{36} \times \frac{9}{1} = \frac{9}{36} = \frac{1}{4} \) day.

Total Time Taken

Total time = Time for 5 cycles + Time for remaining work

Total time = 10 days + \( \frac{1}{4} \) day

Total time = \( 10 \frac{1}{4} \) days.

In improper fraction form, \( 10 \frac{1}{4} = \frac{(10 \times 4) + 1}{4} = \frac{40 + 1}{4} = \frac{41}{4} \) days.

Thus, the work will be completed in \( \frac{41}{4} \) days.

Revision Table: Work and Time Concepts

Concept Explanation Formula/Calculation
Work Rate Amount of work done per unit of time (e.g., per day). If work takes N days, rate = \( \frac{1}{N} \) work/day.
Total Work Usually represented as 1 unit. Work Rate \( \times \) Time Taken = Total Work (1)
Combined Work Rate Sum of individual work rates when working together. Rate1 + Rate2 + ...
Alternate Working Individuals take turns doing the work. Calculate work done in a cycle (usually includes one turn for each). Work in cycle = Sum of work rates for one turn each.

Additional Information: Efficiency and Time

Efficiency is inversely proportional to the time taken to complete a task. If a person is more efficient, they take less time, and their work rate is higher.

  • Diptesh takes 9 days, Tushar takes 12 days.
  • Diptesh is more efficient than Tushar because he takes less time.
  • Diptesh's rate (\( \frac{1}{9} \)) is greater than Tushar's rate (\( \frac{1}{12} \)).

When solving alternate working problems, it's crucial to track whose turn it is after each full cycle of turns is completed, as this person will start the next sequence of turns or complete the remaining work.

Was this answer helpful?

Important Questions from Work Efficiency

  1. A and B together can complete a certain work in 20 days whereas B and C together can complete it in 24 days. If A is twice as good a workman as C, then in what time will B alone do 40% of the same work?

  2. 14 men can complete a work in 15 days. If 21 men are employed, then in how many days will they complete the same work?

  3. A can do a certain work in 15 days, while B can do the same work in 21 days. If they work together, then in how many days will the same work be completed?

  4. To do a certain work, A and B work on alternate days with B beginning the work on the first day. A alone can complete the same work in 24 days. If the work gets completed in  \(11 \frac{1}{3}\)  days, then B alone can complete  \(\rm \frac{7}{9}^{th}\)  part of the original work in:

  5. Two men and 7 women can complete a work in 28 days whereas 6 men and 16 women can do the same work in 11 days. In how many days can 7 men complete the same work?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App