C1, C2 and C3 can do a work alone in 10, 12 and 15 days respectively. All three of them began the work together but C2 left 2 days before the completion of the work. In how many days was the work completed?
(14/3) days
This problem involves calculating the total time taken to complete a piece of work when multiple individuals work together, but one of them leaves before the work is finished. We need to use the concept of individual work rates and set up an equation based on the total work done.
The work rate of a person is the amount of work they can complete in one day. If a person takes \(d\) days to complete a work alone, their daily work rate is \(1/d\) of the work.
Let the total number of days taken to complete the work be \(T\) days. We are given that C2 left 2 days before the completion of the work. This means:
The total work done is the sum of the work done by C1, C2, and C3. The total work completed is represented as 1 (or 100%).
The total work done is the sum of these individual contributions:
\( \text{Total Work} = \frac{T}{10} + \frac{T - 2}{12} + \frac{T}{15} \)
Since the work is completed, the total work done equals 1:
\( \frac{T}{10} + \frac{T - 2}{12} + \frac{T}{15} = 1 \)
To solve this equation for \(T\), we need to find a common denominator for 10, 12, and 15. The least common multiple (LCM) of 10, 12, and 15 is 60.
Multiply the entire equation by 60 to eliminate the denominators:
\( 60 \times \left( \frac{T}{10} + \frac{T - 2}{12} + \frac{T}{15} \right) = 60 \times 1 \)
\( 60 \times \frac{T}{10} + 60 \times \frac{T - 2}{12} + 60 \times \frac{T}{15} = 60 \)
\( 6T + 5(T - 2) + 4T = 60 \)
Now, simplify and solve for \(T\):
\( 6T + 5T - 10 + 4T = 60 \)
\( (6T + 5T + 4T) - 10 = 60 \)
\( 15T - 10 = 60 \)
Add 10 to both sides:
\( 15T = 60 + 10 \)
\( 15T = 70 \)
Divide by 15:
\( T = \frac{70}{15} \)
Simplify the fraction by dividing both numerator and denominator by their greatest common divisor, which is 5:
\( T = \frac{70 \div 5}{15 \div 5} = \frac{14}{3} \)
So, the total number of days the work was completed is \( \frac{14}{3} \) days.
Let's check if the sum of the work done by each person in the calculated time equals 1.
Total work = \( \frac{7}{15} + \frac{2}{9} + \frac{14}{45} \)
Find the LCM of 15, 9, and 45, which is 45.
Total work = \( \frac{7 \times 3}{15 \times 3} + \frac{2 \times 5}{9 \times 5} + \frac{14}{45} = \frac{21}{45} + \frac{10}{45} + \frac{14}{45} \)
Total work = \( \frac{21 + 10 + 14}{45} = \frac{45}{45} = 1 \)
The total work is 1, which means the calculation is correct.
| Person | Time Alone (days) | Daily Work Rate | Time Worked (days) | Work Done |
|---|---|---|---|---|
| C1 | 10 | \(1/10\) | \(T\) | \(T/10\) |
| C2 | 12 | \(1/12\) | \(T-2\) | \((T-2)/12\) |
| C3 | 15 | \(1/15\) | \(T\) | \(T/15\) |
The total time taken for the work to be completed is \( \frac{14}{3} \) days.
| Concept | Explanation | Formula/Example |
|---|---|---|
| Work Rate | The amount of work done per unit of time (e.g., per day). | If A does work in \(D\) days, rate = \(1/D\) per day. |
| Total Work | Usually represented as 1 unit. | Work = Rate \(\times\) Time |
| Combined Rate | Sum of individual rates when working together. | If A's rate is \(R_A\) and B's rate is \(R_B\), combined rate = \(R_A + R_B\). |
| Work Done | Fraction or amount of work completed. | Work Done by A in \(t\) days = \(R_A \times t\). |
Another way to approach this problem is to consider the work done in the last 2 days. In the last 2 days, only C1 and C3 were working (since C2 left 2 days before completion).
This means the remaining \( 1 - \frac{1}{3} = \frac{2}{3} \) of the work was done by all three (C1, C2, and C3) working together at the beginning.
Let the number of days all three worked together be \(t_1\). They completed \( \frac{2}{3} \) of the work in \(t_1\) days.
\( \text{Combined Rate} \times t_1 = \text{Work Done} \)
\( \frac{1}{4} \times t_1 = \frac{2}{3} \)
\( t_1 = \frac{2}{3} \times 4 = \frac{8}{3} \) days.
The total time for the work is the time all three worked together plus the time only C1 and C3 worked:
\( \text{Total Time} = t_1 + 2 \text{ days} \)
\( \text{Total Time} = \frac{8}{3} + 2 = \frac{8}{3} + \frac{6}{3} = \frac{14}{3} \) days.
Both methods give the same result, \( \frac{14}{3} \) days, confirming the answer.
A and B working together can complete a job in 30 days. The ratio of their efficiencies is 3 : 2. In how many days can the faster person complete the job?
A takes 15 days to complete \(\frac{5}{7} \) of a work. With the help of B, they finish the whole work in 12 days. In how many days, B alone will complete the same work
A alone can complete a work in 14 days and B alone can complete the same work in 21 days. A and B start the work together but A leaves the work after 4 days of the starting of work. In how many days B will complete the remaining work?
For completing a certain work, A is 50% less efficient than B and B is 50% more efficient than C. Working together A, B and C can complete the work in 48 days. A alone can complete the same work in:
30 persons can do a piece of work in 24 days. How many more persons are required to complete the work in 20 days?