Anu is four times as good as Binni in completing a task. Together they finish the same task in 7 hours. In how many hours will Anu alone complete the task?
35/4
This problem involves the concept of work and time, where the efficiency of individuals affects the time taken to complete a task. The key relationship is between work rate, time, and the total work done. We can assume the total task is one unit of work.
Let's define the terms:
The formula connecting these is: $\text{Work Rate} \times \text{Time} = \text{Total Work}$. Since Total Work is 1, we have $\text{Work Rate} = 1 / \text{Time}$. Conversely, $\text{Time} = 1 / \text{Work Rate}$.
We are told that Anu is four times as good as Binni in completing a task. This means Anu's work rate is four times Binni's work rate.
Let $R_A$ be Anu's work rate and $R_B$ be Binni's work rate.
According to the question: $\text{Anu's Work Rate} = 4 \times \text{Binni's Work Rate}$, which is written as $R_A = 4 R_B$.
Let $T_A$ be the time Anu takes alone to complete the task and $T_B$ be the time Binni takes alone. Using the relationship $\text{Work Rate} = 1 / \text{Time}$, we have $R_A = 1/T_A$ and $R_B = 1/T_B$.
Substituting these into the rate relationship: $1/T_A = 4 (1/T_B)$. This simplifies to $T_B = 4 T_A$. This means Binni takes four times as long as Anu to complete the task alone, which makes sense because Anu is four times more efficient.
When Anu and Binni work together, their individual work rates add up to form a combined work rate. Let $R_{Together}$ be their combined work rate.
$R_{Together} = R_A + R_B$
We are given that together they finish the same task in 7 hours. Using the formula $\text{Work Rate} = 1 / \text{Time}$, their combined work rate is $1/7$ (task per hour).
So, $R_{Together} = 1/7$.
We have the combined work rate equation: $R_A + R_B = 1/7$.
We also know $R_A = 1/T_A$ and $R_B = 1/T_B$. Substituting these into the equation:
$\frac{1}{T_A} + \frac{1}{T_B} = \frac{1}{7}$
From the efficiency relationship, we established that $T_B = 4 T_A$. Substitute this into the equation:
$\frac{1}{T_A} + \frac{1}{4T_A} = \frac{1}{7}$
Now, we solve the equation for $T_A$:
Combine the terms on the left side by finding a common denominator, which is $4T_A$:
$\frac{4}{4T_A} + \frac{1}{4T_A} = \frac{1}{7}$
$\frac{4 + 1}{4T_A} = \frac{1}{7}$
$\frac{5}{4T_A} = \frac{1}{7}$
Now, cross-multiply:
$5 \times 7 = 1 \times 4T_A$
$35 = 4T_A$
To find $T_A$, divide both sides by 4:
$T_A = \frac{35}{4}$
So, Anu alone will complete the task in $\frac{35}{4}$ hours.
| Person | Work Rate (Task/Hour) | Time (Hours) |
|---|---|---|
| Anu | $R_A = \frac{1}{T_A}$ | $T_A$ |
| Binni | $R_B = \frac{1}{T_B}$ | $T_B$ |
| Together | $R_{Together} = R_A + R_B = \frac{1}{7}$ | 7 |
We found $T_A = \frac{35}{4}$. Let's verify this. If $T_A = 35/4$, then $R_A = 4/35$. $T_B = 4T_A = 4 \times (35/4) = 35$. So $R_B = 1/35$. Combined rate $R_A + R_B = 4/35 + 1/35 = 5/35 = 1/7$. Time taken together is $1 / (1/7) = 7$ hours. This matches the information given in the question.
| Concept | Explanation | Formula (Work = 1) |
|---|---|---|
| Work Rate | Amount of work done per unit time. Higher rate means more efficient. | Rate = 1 / Time |
| Time | Duration to complete the work. | Time = 1 / Rate |
| Combined Rate (Multiple workers) | Sum of individual work rates when working together. | $R_{combined} = R_1 + R_2 + ...$ |
| Time Together | Time taken when multiple workers work together. | $T_{together} = 1 / R_{combined}$ |
| Efficiency Relation | If A is 'n' times as good as B, then Rate of A = n × Rate of B, and Time taken by A = (1/n) × Time taken by B. | $R_A = n R_B$, $T_A = T_B / n$ |
Here are some general formulas useful for solving work and time problems:
Surbhi can do a piece of work in 24 days. She completed 3/8 of the work and then left it. Amit can complete the remaining work in 10 days. Working together, they will complete 125% of the same work in:
Rama and Hari can together finish a piece of work in 15 day. Rama works twice as fast as Hari, then Hari alone can finish work in :
Anil, Deepak and Dinesh together can complete a work in 35 days. Anil and Dinesh together can complete the same work in 60 days. In how many days Deepak alone can complete the same work?
P, Q and R can complete a work in 10 days, 20 days and 30 days, respectively, working alone. How soon can the work be completed if P is assisted by Q and R on alternate days?
A can complete a project in 10 days and B can complete the same project in 15 days. A and B start working on the project together and A quit 5 days before the project is completed. In how many days is the project completed?