A can complete a project in 10 days and B can complete the same project in 15 days. A and B start working on the project together and A quit 5 days before the project is completed. In how many days is the project completed?
9
This problem involves calculating the total time taken to complete a project when two people, A and B, work together for some time, and then one person, A, quits before the project finishes. We need to find the total number of days the project was completed.
First, let's figure out how much work each person can do in a single day. This is their work rate.
We are told that A quit 5 days before the project was completed. This means that during the last 5 days, only B was working on the project.
Let's calculate the amount of work B completed in these last 5 days:
Work done by B in 5 days = B's daily rate \(\times\) Number of days
Work done by B in 5 days = \( \frac{1}{15} \times 5 = \frac{5}{15} = \frac{1}{3} \) of the project.
The project has a total work of '1' (representing the whole project). If B completed \( \frac{1}{3} \) of the work alone at the end, the remaining work must have been done by both A and B working together before A quit.
Remaining work = Total work - Work done by B alone
Remaining work = \( 1 - \frac{1}{3} = \frac{3}{3} - \frac{1}{3} = \frac{2}{3} \) of the project.
When A and B work together, their work rates add up to find their combined work rate per day.
Combined daily rate of A and B = A's daily rate + B's daily rate
Combined daily rate = \( \frac{1}{10} + \frac{1}{15} \)
To add these fractions, we find a common denominator, which is 30.
Combined daily rate = \( \frac{1 \times 3}{10 \times 3} + \frac{1 \times 2}{15 \times 2} = \frac{3}{30} + \frac{2}{30} = \frac{3+2}{30} = \frac{5}{30} = \frac{1}{6} \) of the project per day.
Now we know that \( \frac{2}{3} \) of the project was completed by A and B working together at a combined rate of \( \frac{1}{6} \) per day. We can find the number of days they worked together.
Days A and B worked together = Remaining work / Combined daily rate
Days A and B worked together = \( \frac{2/3}{1/6} = \frac{2}{3} \div \frac{1}{6} = \frac{2}{3} \times \frac{6}{1} \)
Days A and B worked together = \( \frac{12}{3} = 4 \) days.
The total time for the project is the sum of the time A and B worked together and the time B worked alone.
Total time = Days A and B worked together + Days B worked alone
Total time = 4 days + 5 days = 9 days.
So, the project was completed in 9 days.
| Task | Work Rate | Time | Work Done |
|---|---|---|---|
| A's Daily Rate | \( \frac{1}{10} \) | - | - |
| B's Daily Rate | \( \frac{1}{15} \) | - | - |
| B alone (last 5 days) | \( \frac{1}{15} \) | 5 days | \( \frac{1}{15} \times 5 = \frac{1}{3} \) |
| A and B together | \( \frac{1}{10} + \frac{1}{15} = \frac{1}{6} \) | 4 days (calculated) | \( \frac{1}{6} \times 4 = \frac{4}{6} = \frac{2}{3} \) |
| Total Work | - | Total 9 days | \( \frac{1}{3} + \frac{2}{3} = 1 \) (Project Completed) |
| Concept | Formula/Explanation |
|---|---|
| Individual Daily Work Rate | \( \frac{1}{\text{Time taken to complete the work alone}} \) |
| Work done in 'n' days | Daily Work Rate \(\times\) n |
| Combined Daily Work Rate (A and B) | A's Daily Rate + B's Daily Rate |
| Time taken to complete 'W' amount of work | \( \frac{\text{Amount of Work (W)}}{\text{Daily Work Rate}} \) |
Time and work problems often involve calculating rates and combining them. Here are some key ideas:
Understanding these basic principles helps in tackling various types of time and work problems, including those where workers start or stop at different times.
Surbhi can do a piece of work in 24 days. She completed 3/8 of the work and then left it. Amit can complete the remaining work in 10 days. Working together, they will complete 125% of the same work in:
Rama and Hari can together finish a piece of work in 15 day. Rama works twice as fast as Hari, then Hari alone can finish work in :
Anil, Deepak and Dinesh together can complete a work in 35 days. Anil and Dinesh together can complete the same work in 60 days. In how many days Deepak alone can complete the same work?
Anu is four times as good as Binni in completing a task. Together they finish the same task in 7 hours. In how many hours will Anu alone complete the task?
P, Q and R can complete a work in 10 days, 20 days and 30 days, respectively, working alone. How soon can the work be completed if P is assisted by Q and R on alternate days?