All Exams Test series for 1 year @ ₹349 only
Question

An unfavourable overhead volume variance indicates that:  

The correct answer is

Actual production was less than the normal level of output .

Understanding Unfavourable Overhead Volume Variance

The question asks what an unfavourable overhead volume variance indicates. Let's break down what overhead volume variance is and what causes it to be favourable or unfavourable.

Overhead volume variance specifically relates to fixed overhead. It arises because fixed overhead is absorbed into product cost based on a budgeted level of activity (like machine hours, labour hours, or production units), but actual activity may differ from this budgeted level.

The formula for overhead volume variance is typically calculated as:

\(\text{Overhead Volume Variance} = \text{Budgeted Fixed Overhead} - \text{Absorbed Fixed Overhead}\)

Alternatively, it can be calculated based on the difference in activity levels:

\(\text{Overhead Volume Variance} = (\text{Budgeted Activity Units} - \text{Actual Activity Units}) \times \text{Fixed Overhead Absorption Rate per Unit}\)

Where Fixed Overhead Absorption Rate per Unit = \(\frac{\text{Budgeted Fixed Overhead}}{\text{Budgeted Activity Units}}\)

Analysing Unfavourable Volume Variance

An unfavourable overhead volume variance means that the absorbed fixed overhead is less than the budgeted fixed overhead. Using the second formula, this happens when the Actual Activity Units are less than the Budgeted Activity Units (often referred to as the normal level of output or capacity).

When actual production (activity) is less than the budgeted or normal level, less fixed overhead is absorbed into the cost of goods produced. Since the total fixed costs generally remain constant within a relevant range regardless of the actual production level, under-absorbing fixed overhead means that some fixed costs are not covered by the absorption process, resulting in an unfavourable variance. This unfavourable variance reflects the cost of unused capacity.

Evaluating the Options

Let's evaluate each given option in the context of an unfavourable overhead volume variance:

  1. Total fixed overhead has exceeded the standard budgeted amount: This describes a fixed overhead spending variance, not a volume variance. Volume variance is caused by differences in activity levels, not differences between actual and budgeted total fixed costs. Therefore, this option is incorrect.
  2. Variable overhead per unit has exceeded the standard budgeted amount: This refers to a variance related to variable overhead, specifically a spending variance or rate variance for variable overhead. Overhead volume variance deals exclusively with fixed overhead. Therefore, this option is incorrect.
  3. Actual production was less than the normal level of output: As explained above, when actual activity (production) is lower than the budgeted or normal level of output, less fixed overhead is absorbed. This under-absorption leads to an unfavourable fixed overhead volume variance. This statement correctly describes the condition that results in an unfavourable volume variance.
  4. Actual production was more than the normal level of output: When actual activity (production) is higher than the budgeted or normal level of output, more fixed overhead is absorbed than budgeted. This over-absorption leads to a favourable fixed overhead volume variance. This is the opposite of an unfavourable variance. Therefore, this option is incorrect.

Based on the analysis, an unfavourable overhead volume variance indicates that the actual production level was less than the normal or budgeted level of output.

Summary of Variance Type and Cause

Variance Type Relates To Cause (Unfavourable) Cause (Favourable)
Fixed Overhead Volume Variance Fixed Overhead Actual production < Budgeted/Normal production Actual production > Budgeted/Normal production
Fixed Overhead Spending Variance Fixed Overhead Actual total fixed overhead > Budgeted total fixed overhead Actual total fixed overhead < Budgeted total fixed overhead
Variable Overhead Spending Variance Variable Overhead Actual variable overhead cost per unit of activity > Standard variable overhead cost per unit of activity Actual variable overhead cost per unit of activity < Standard variable overhead cost per unit of activity
Variable Overhead Efficiency Variance Variable Overhead Actual activity units for output > Standard activity units for output Actual activity units for output < Standard activity units for output

Conclusion on Unfavourable Overhead Volume Variance

An unfavourable overhead volume variance specifically signals that the company did not utilize its capacity to the planned extent. The actual level of production or activity was lower than the level that was used to set the fixed overhead absorption rate. This results in under-absorption of fixed overhead costs, which is reported as an unfavourable variance.

Revision Table: Key Variance Concepts

Concept Explanation Variance Type
Difference in total actual vs. budgeted fixed costs Compares what was actually spent on fixed overhead to the budgeted amount. Fixed Overhead Spending Variance
Difference in actual production volume vs. budgeted volume affecting fixed cost absorption Compares the volume of activity achieved to the volume planned, impacting how fixed overhead is absorbed. Fixed Overhead Volume Variance
Difference in actual vs. standard cost per unit of variable overhead Compares the actual cost rate for variable overhead to the standard rate. Variable Overhead Spending Variance
Difference in actual activity vs. standard activity allowed for actual output for variable overhead Compares the actual usage of the activity base (like hours) to the standard usage allowed for the actual output produced, for variable overhead. Variable Overhead Efficiency Variance

Additional Information: Fixed Overhead Absorption and Capacity

Fixed overhead absorption is a process used under absorption costing where fixed manufacturing overhead costs are assigned to products. A predetermined overhead rate is calculated at the beginning of the period based on budgeted fixed overhead and a budgeted activity level (often representing normal capacity).

When actual production volume equals the budgeted volume, the total fixed overhead absorbed (\(\text{Actual Volume} \times \text{Absorption Rate}\)) will equal the budgeted fixed overhead (\(\text{Budgeted Volume} \times \text{Absorption Rate}\)). In this case, the volume variance is zero.

When actual production volume is less than budgeted volume, absorbed fixed overhead is less than budgeted fixed overhead, resulting in an unfavourable volume variance.

When actual production volume is more than budgeted volume, absorbed fixed overhead is more than budgeted fixed overhead, resulting in a favourable volume variance.

The fixed overhead volume variance essentially measures the cost impact of operating at a level different from the capacity level used for setting the absorption rate. An unfavourable variance often points to underutilization of production capacity relative to the plan.

Was this answer helpful?

Important Questions from Standard costing

  1. Which of the following may be the reasons for a material usage variance?

    (A) Negligence in the use of materials

    (B) Changes in basic prices of materials

    (C) Poor or improper machine handling

    (D) Wastage due to inefficient production methods

    (E) Change in product design requiring usuage different from the standard

    Choose the correct answer from the options given below:

  2. As per the information given below, what is the correct material yield variance ?

    Standard input = 100 kg

    Standard yield = 90 kg

    Standard cost per kg of output = Rs. 20

    Actual input = 200 kg

    Actual yield = 182 kg

    Actual cost per kg of output = Rs. 19

  3. What is the total overhead variance in the given month experienced by the XYZ Ltd?

  4. What is the expenditure variance of XYZ Ltd as on given month?

  5. From given information in the passage, what is the volume variance of XYZ Ltd in given month?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App