Read the following passage carefully and answer the question. XYZ Ltd. funrnished you with the following information: Budgeted overhead rate is Rs. 1 per unit. In a particular month the actual hours worked were 31,500.Budget Actual (in a particular month) No. of working days 25 27 Production (in units) 20,000 22,000 Fixed overhead (in Rupees) 30,000 31,000
From given information in the passage, what is the volume variance of XYZ Ltd in given month?
Rs. 3,000 (Favourable)
Let's break down how to calculate the fixed overhead volume variance based on the information provided for XYZ Ltd. The volume variance specifically measures the impact on fixed overhead absorption due to the actual production volume being different from the budgeted production volume.
The fixed overhead volume variance is a part of fixed overhead variance analysis. It arises because fixed overheads are applied (absorbed) into product costs based on a budgeted rate per unit of activity (like units produced or hours worked). If the actual activity level differs from the budgeted level, the total fixed overhead absorbed will differ from the budgeted fixed overhead.
The formula for Volume Variance is:
\(\text{Volume Variance} = \text{Absorbed Fixed Overhead} - \text{Budgeted Fixed Overhead}\)
Alternatively, it can be calculated as:
\(\text{Volume Variance} = (\text{Actual Volume} - \text{Budgeted Volume}) \times \text{Budgeted Fixed Overhead Rate per Unit}\)
A positive variance is usually Favourable (F), meaning more fixed overhead was absorbed than budgeted (due to higher actual volume). A negative variance is usually Adverse (A), meaning less fixed overhead was absorbed than budgeted (due to lower actual volume).
From the provided details for XYZ Ltd, we need the following figures to calculate the fixed overhead volume variance:
The passage also mentions a "Budgeted overhead rate is Rs. 1 per unit". However, if we calculate the budgeted rate from the budgeted figures (Rs. 30,000 / 20,000 units), we get Rs. 1.5 per unit. In cost accounting questions, when an explicit rate contradicts the rate derived from total budgeted figures, it is often the case that the rate derived from the totals is the intended rate for variance calculations unless otherwise specified. Let's use the calculated rate of Rs. 1.5 per unit as it is consistent with the total budgeted fixed overhead and production, and see if it leads to one of the options.
Step 1: Calculate the Budgeted Fixed Overhead Rate per Unit
Based on budgeted figures:
\(\text{Budgeted Rate} = \frac{\text{Budgeted Fixed Overhead}}{\text{Budgeted Production Units}}\)
\(\text{Budgeted Rate} = \frac{\text{Rs. } 30,000}{20,000 \text{ units}}\)
\(\text{Budgeted Rate} = \text{Rs. } 1.50 \text{ per unit}\)
Step 2: Calculate the Volume Variance
Using the calculated budgeted rate and the difference in volume:
\(\text{Volume Variance} = (\text{Actual Production} - \text{Budgeted Production}) \times \text{Budgeted Rate per Unit}\)
\(\text{Volume Variance} = (22,000 \text{ units} - 20,000 \text{ units}) \times \text{Rs. } 1.50 \text{ per unit}\)
\(\text{Volume Variance} = 2,000 \text{ units} \times \text{Rs. } 1.50 \text{ per unit}\)
\(\text{Volume Variance} = \text{Rs. } 3,000\)
Step 3: Determine if the Variance is Favourable or Adverse
Actual production (22,000 units) is greater than budgeted production (20,000 units). This means XYZ Ltd produced more units than planned. Since each unit absorbs fixed overhead at the budgeted rate, producing more units leads to absorbing more fixed overhead than budgeted. Therefore, the variance is Favourable.
\(\text{Volume Variance} = \text{Rs. } 3,000 \text{ (Favourable)}\)
The figures for the number of working days and actual hours worked are not needed for the calculation of fixed overhead volume variance, which is based on production units and the budgeted rate per unit.
Based on the calculation using the budgeted fixed overhead and budgeted production to determine the rate, the fixed overhead volume variance for XYZ Ltd in the given month is Rs. 3,000 (Favourable).
Here is a quick overview of key fixed overhead variances:
| Variance Name | Formula | Explanation |
|---|---|---|
| Total Fixed Overhead Variance | Actual Fixed Overhead - Absorbed Fixed Overhead | Difference between actual fixed overhead cost and the amount absorbed into production. |
| Fixed Overhead Spending Variance | Actual Fixed Overhead - Budgeted Fixed Overhead | Difference between actual fixed overhead cost incurred and the budgeted fixed overhead cost. |
| Fixed Overhead Volume Variance | Budgeted Fixed Overhead - Absorbed Fixed Overhead OR (Budgeted Volume - Actual Volume) x Budgeted Rate per Unit |
Difference between budgeted fixed overhead and the amount absorbed, arising solely due to the difference between budgeted and actual production volume. (Note: Formula sign convention can vary, but the absolute value and F/A determination is key. Our calculation uses the (Actual - Budgeted) * Rate format, giving a positive result for Favourable.) |
Variance analysis is a critical tool in cost accounting for performance evaluation and control. It involves comparing actual results with budgeted or standard amounts to identify differences, known as variances. These variances help management pinpoint areas that need attention.
Understanding these variances helps businesses manage costs effectively and improve future budgeting and operational efficiency.
Which of the following may be the reasons for a material usage variance?
(A) Negligence in the use of materials
(B) Changes in basic prices of materials
(C) Poor or improper machine handling
(D) Wastage due to inefficient production methods
(E) Change in product design requiring usuage different from the standard
Choose the correct answer from the options given below:
An unfavourable overhead volume variance indicates that:
As per the information given below, what is the correct material yield variance ?
Standard input = 100 kg
Standard yield = 90 kg
Standard cost per kg of output = Rs. 20
Actual input = 200 kg
Actual yield = 182 kg
Actual cost per kg of output = Rs. 19
What is the total overhead variance in the given month experienced by the XYZ Ltd?
What is the expenditure variance of XYZ Ltd as on given month?