Read the following passage carefully and answer the question. XYZ Ltd. funrnished you with the following information: Budgeted overhead rate is Rs. 1 per unit. In a particular month the actual hours worked were 31,500.Budget Actual (in a particular month) No. of working days 25 27 Production (in units) 20,000 22,000 Fixed overhead (in Rupees) 30,000 31,000
What is the expenditure variance of XYZ Ltd as on given month?
Rs. 1,000 (Adverse)
Let's analyze the information provided by XYZ Ltd. to understand the expenditure variance for fixed overheads. The question asks specifically for the expenditure variance.
Expenditure variance for fixed overhead measures the difference between the actual fixed overhead costs incurred and the budgeted fixed overhead costs for a period. It essentially tells us if we spent more or less than planned on fixed overheads.
Here is the relevant data from the passage:
The formula for calculating the Fixed Overhead Expenditure Variance is:
Fixed Overhead Expenditure Variance = Actual Fixed Overhead - Budgeted Fixed Overhead
Let's plug in the numbers from the passage:
Fixed Overhead Expenditure Variance = Rs. 31,000 - Rs. 30,000
Fixed Overhead Expenditure Variance = Rs. 1,000
Now, we need to determine if this variance is favourable or adverse. An adverse variance occurs when the actual cost is higher than the budgeted cost. A favourable variance occurs when the actual cost is lower than the budgeted cost.
In this case, the actual fixed overhead (Rs. 31,000) is higher than the budgeted fixed overhead (Rs. 30,000). Therefore, the variance is adverse.
So, the expenditure variance is Rs. 1,000 (Adverse).
| Item | Budget | Actual |
|---|---|---|
| Fixed Overhead (Rs.) | 30,000 | 31,000 |
Calculation Summary:
The other data provided, such as working days, production units, and actual hours worked, are relevant for calculating other variances like volume variance or efficiency variance, but they are not needed to calculate the fixed overhead expenditure variance, which only compares actual fixed costs to budgeted fixed costs.
| Variance Type | Formula | Explanation |
|---|---|---|
| Expenditure Variance | Actual Fixed Overhead - Budgeted Fixed Overhead | Difference between actual and budgeted fixed costs. Measures cost control. |
| Volume Variance | Budgeted Fixed Overhead Rate $\times$ (Actual Production Volume - Budgeted Production Volume) | Difference due to producing more or less than budgeted volume. Measures utilisation of capacity based on production output. |
| Total Fixed Overhead Variance | Actual Fixed Overhead - Absorbed Fixed Overhead | Overall difference between actual fixed costs and fixed costs absorbed into production. Can also be calculated as Expenditure Variance + Volume Variance. |
Overhead variances help management understand the reasons for differences between planned (budgeted) and actual overhead costs. Variances can be categorised into fixed overhead variances and variable overhead variances.
Fixed Overhead Variances:
Variable Overhead Variances:
Understanding these variances helps managers identify areas for improvement in cost control and efficiency.
An unfavourable overhead volume variance indicates that:
What is the total overhead variance in the given month experienced by the XYZ Ltd?
From given information in the passage, what is the volume variance of XYZ Ltd in given month?
Find the capacity variance for the month from the information given in the passage.
Given the information in the passage, what is the calendar variance for the month?