All Exams Test series for 1 year @ ₹349 only
Question

A can complete a task in the same time in which B and C together can complete it. If A and B together can complete it in 10 days and C alone can complete it in 60 days, then B alone can complete it in:

The correct answer is

24 days

Understanding the Time and Work Problem

This question is a classic example of a time and work problem. These problems often involve calculating the time taken by individuals or groups to complete a task, based on their work rates.

The core concept here is that the amount of work done per unit of time is called the work rate. If a person can complete a task in $T$ days, their work rate per day is $\frac{1}{T}$. The total work is usually considered '1 unit' (completing the task).

Setting Up the Equations for Time and Work

We are given the following information about completing a task:

  • A can complete the task in the same time as B and C together. Let $T_A$, $T_B$, and $T_C$ be the time taken by A, B, and C alone, respectively. This means $T_A = T_{B+C}$. In terms of work rates, this translates to the work done by A in a day being equal to the combined work done by B and C in a day. If $W_A, W_B, W_C$ are the daily work rates of A, B, C respectively, then $W_A = W_B + W_C$.
  • A and B together can complete the task in 10 days. Their combined work rate per day is $\frac{1}{10}$. So, $W_A + W_B = \frac{1}{10}$.
  • C alone can complete the task in 60 days. C's work rate per day is $\frac{1}{60}$. So, $W_C = \frac{1}{60}$.

We need to find the time taken by B alone to complete the task, which is $T_B$. This means we need to find B's work rate, $W_B$, because $T_B = \frac{1}{W_B}$.

Solving for B's Work Rate using Equations

We have the following relationships based on the given information:

  1. $W_A = W_B + W_C$
  2. $W_A + W_B = \frac{1}{10}$
  3. $W_C = \frac{1}{60}$

We can use these equations to find $W_B$. Let's substitute the value of $W_C$ from equation (3) into equation (1):

Substituting $W_C = \frac{1}{60}$ into the equation $W_A = W_B + W_C$, we get:

$\qquad W_A = W_B + \frac{1}{60}$

Now we have an expression for $W_A$ in terms of $W_B$. We can substitute this expression for $W_A$ into equation (2), which is $W_A + W_B = \frac{1}{10}$:

Substituting $W_A = W_B + \frac{1}{60}$ into $W_A + W_B = \frac{1}{10}$ gives:

$\qquad (W_B + \frac{1}{60}) + W_B = \frac{1}{10}$

Now, let's solve this equation for $W_B$. Combine the $W_B$ terms:

$\qquad 2W_B + \frac{1}{60} = \frac{1}{10}$

To isolate the term with $W_B$, subtract $\frac{1}{60}$ from both sides of the equation:

$\qquad 2W_B = \frac{1}{10} - \frac{1}{60}$

To perform the subtraction on the right side, we need a common denominator for 10 and 60. The least common multiple is 60. So, rewrite $\frac{1}{10}$ as $\frac{6}{60}$:

$\qquad 2W_B = \frac{6}{60} - \frac{1}{60}$

Now subtract the numerators:

$\qquad 2W_B = \frac{6-1}{60}$

$\qquad 2W_B = \frac{5}{60}$

Simplify the fraction $\frac{5}{60}$ by dividing both numerator and denominator by 5:

$\qquad 2W_B = \frac{1}{12}$

Finally, divide both sides by 2 to find $W_B$:

$\qquad W_B = \frac{1}{12} \div 2$

$\qquad W_B = \frac{1}{12} \times \frac{1}{2}$

$\qquad W_B = \frac{1}{24}$

Calculating the Time Taken by B Alone

We have found that B's work rate is $W_B = \frac{1}{24}$ task per day. The time taken by B alone to complete the entire task is the reciprocal of B's daily work rate.

$\qquad T_B = \frac{1}{W_B} = \frac{1}{\frac{1}{24}} = 24$ days.

Thus, B alone can complete the task in 24 days.

Worker(s) Information Given Work Rate (Task/Day)
A $T_A = T_{B+C}$ $W_A = W_B + W_C$
A + B Complete in 10 days $W_A + W_B = \frac{1}{10}$
C Complete in 60 days $W_C = \frac{1}{60}$
B To Find $T_B$ $W_B = \frac{1}{T_B}$

Revision Table: Key Time and Work Concepts

Concept Explanation Formula
Work Rate The fraction of the total work done in one unit of time (e.g., per day). Work Rate = $\frac{1}{\text{Time Taken}}$
Total Work Completing the entire task is usually represented as 1 unit of work. Time Taken = $\frac{\text{Total Work}}{\text{Work Rate}}$
Combined Work Rate When multiple individuals work together, their work rates add up. $W_{\text{Total}} = W_1 + W_2 + ...$

Additional Information: Time and Work Problem-Solving Tips

Solving time and work problems often involves setting up equations based on the work rates of individuals or groups. Here are some useful tips:

  • Represent the total work as 1 unit.
  • If someone takes $T$ days, their daily work rate is $\frac{1}{T}$.
  • If multiple people work together, add their individual work rates to get the combined work rate.
  • If someone stops working or joins later, calculate the work done in phases.
  • Problems involving pipes filling or emptying tanks are similar; filling is positive work rate, emptying is negative.

Always check if the question asks for the time taken by an individual, a group, or the time to complete a specific fraction of the work.

Was this answer helpful?

Important Questions from Work Efficiency

  1. M is thrice as efficient as workman as N and therefore is able to finish a job in 264 days less than N. Then in how many days can N finish the entire work?
  2. A can do a piece of work in $1455$ days. B is $25\%$ more efficient than A. Find the number of days taken by B to do the same piece of work.
  3. 45 people take 18 days to dig a pond. If the pond would have to be dug in 15 days, then the number of people to be employed will be
  4. A stock of food is enough for 240 men for 48 days. How long will the same stock last for 160 men?
  5. One contractor had undertaken a construction work. To complete the given job, he sought labour comprising 24 men for 12 days for working 10 hours a day. But due to festival season, as the labour had gone to their respective hometowns, he could get only 15 men and they too were willing to work 8 hours a day. With this much labour, in how many days would he be able to complete the same job?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App