All Exams Test series for 1 year @ ₹349 only
Question

"Section 55 of the Indian Contract Act says that when a party to a contract promises to do a certain thing within a specified time but fails to do so, the contract or so much of it as has not been performed, becomes voidable at the option of the promisee if the intention of the parties was, that time should be of the essence of the contract. If time is not the essence of the contract, the contract does not become voidable by the failure to do such thing on or before the specified time but the promisee is entitled to compensation from the promisor for any loss occasioned to him by such failure. Further, if in case of a contract voidable on account of the promisor's failure to perform his promise within the time agreed and the promisee accepts performance of such promise at any time other than that agreed, the promisee cannot claim compensation for any loss occasioned by the non-performance of the promise at the time agreed, unless, at the time of such acceptance he gives notice to the promisor of his intention to do so.
... Sections 73 and 74 deal with consequences of breach of contract. Heading of Section 73 is compensation for loss or damage caused by breach of contract. When a contract is broken, the party who suffers by such breach is entitled to receive from the party who has broken the contract compensation for any loss or damage caused to him thereby which naturally arose in the usual course of things from such breach or which the parties knew when they made the contract to be likely to result from the breach of it. On the other hand, Section 74 deals with compensation for breach of contract where penalty is stipulated for. When a contract is broken, if a sum is mentioned in the contract as the amount to be paid in case of such breach or if the contract contains any other stipulation by way of penalty, the party complaining of the breach is entitled whether or not actually damage or loss is proved to have been caused thereby, to receive from the party who has broken the contract reasonable compensation not exceeding the amount so named or the penalty stipulated for."
[Extracted from: Consolidated Construction Consortium Limited v Software Technology Parks of India 2025 INSC 574]

Which of the following is NOT a leading judgement on section 74 of the Indian Contract Act:

The correct answer is
Satyabrata Ghose v Mugneeram Bangur& Co 1954 SCR 310.

Indian Contract Act: Sections 73 and 74 Overview

The Indian Contract Act, 1872, lays down principles for valid contracts and provides remedies when these agreements are not fulfilled. Sections 73 and 74 are particularly important as they deal with the consequences of a breach of contract, specifically concerning compensation. While Section 73 addresses general compensation for losses that naturally arise from a breach, Section 74 focuses on situations where a contract includes a pre-agreed sum payable upon breach, often termed a 'penalty' or 'liquidated damages'.

Section 74: Penalty and Compensation

Section 74 of the Act governs the compensation payable when a contract contains a stipulation by way of penalty. Based on the provided context:

  • When a contract is broken, and it contains a clause specifying a sum as the amount payable in case of breach, or any other stipulation by way of penalty, the affected party is entitled to compensation.
  • This compensation is for reasonable damages, not exceeding the amount stipulated or the penalty provided in the contract.
  • A key aspect is that the party complaining of the breach can claim this reasonable compensation whether or not actual damage or loss is proven.

The interpretation of this section has been shaped by numerous judicial pronouncements, distinguishing between genuine pre-estimates of loss and penalties intended to deter breach.

Section 74: Key Judgments

Leading Section 74 Cases

The following cases are widely recognized as landmark judgments that have significantly interpreted and applied Section 74:

Fateh Chand v Balkishan Dass [1964]

This Supreme Court ruling is pivotal in understanding Section 74. The court established that the stipulation for a penalty is not enforceable in itself, but the court can award reasonable compensation, not exceeding the stipulated amount. This judgment emphasized that the purpose is compensation, not punishment, and the court's discretion to award reasonable compensation up to the stated limit is key.

ONGC Ltd v Saw Pipes Ltd (2003)

In this significant case, the Supreme Court further clarified the application of Section 74, especially concerning large commercial contracts. It affirmed that while parties can agree on the amount of compensation (liquidated damages), courts retain the power to award only reasonable compensation not exceeding the stipulated sum if the clause amounts to a penalty. The court underlined that the burden is on the party claiming the full stipulated amount to justify it.

Kailash Nath Associates v Delhi Development Authority [2015]

This judgment provided further clarity on Section 74, particularly on the distinction between genuine liquidated damages and penalties. The Supreme Court held that if a sum is named as penalty, compensation can only be awarded if actual loss is proved, and even then, it cannot exceed the stipulated amount. This case highlighted that compensation must be based on established loss and cannot be claimed arbitrarily merely because a penalty is mentioned in the contract.

Non-Leading Section 74 Case

Satyabrata Ghose v Mugneeram Bangur& Co (1954)

The case of Satyabrata Ghose v Mugneeram Bangur& Co is indeed a landmark decision in contract law. However, its fame and primary legal contribution are related to the interpretation of Section 55 of the Indian Contract Act, which deals with the effect of 'time being the essence of the contract'. This case extensively discussed issues like the consequences of failing to perform within the stipulated time and the concept of frustration of contract. While any breach of contract case might tangentially involve aspects of compensation, Satyabrata Ghose is not predominantly cited or relied upon as a leading authority specifically for the principles governing penalty clauses and compensation under Section 74.

Section 74: Conclusion on Judgments

Evaluating the given options against their established legal significance:

  • Kailash Nath Associates v Delhi Development Authority is a key judgment for Section 74.
  • ONGC Ltd v Saw Pipes Ltd is a key judgment for Section 74.
  • Fateh Chand v Balkishan Dass is a key judgment for Section 74.
  • Satyabrata Ghose v Mugneeram Bangur& Co is primarily associated with Section 55 and other general contract principles, rather than being a leading case specifically on Section 74.

Therefore, among the given choices, Satyabrata Ghose v Mugneeram Bangur& Co is the judgment that is NOT considered a leading judgement on Section 74 of the Indian Contract Act.

Was this answer helpful?

Similar Questions

  1. As per section 96 of the Transfer of Property Act, the provisions which apply to _________ shall, so far as may be, apply to a mortgage by deposit of title-deeds.
  2. In a mortgage by deposit of title-deeds, after the deposit of the title-deeds, if the creditor and the borrower choose to record their transaction in a memorandum reducing other terms and conditions (in addition to what flow from the mortgage by deposit of title-deeds) with regard to the deposit in the form of a memorandum/document, then the memorandum/document requires registration under section 17(1)(c) of the Registration Act. In this context which among the following propositions is not correct?
  3. The Supreme Court's final decision on the appeal filed by M/s. Balaji Traders was to:
  4. In which of the following cases, the Supreme Court read down the word "adult male" in Section 2(q) of the Protection of Women from Domestic Violence Act, 2005?
  5. The Supreme Court emphasized that the expression "extinguishment of any right therein" is of wide import. What does this expression cover?
  6. Section 28 of the Indian Contract Act is subject to __________ appended to it:
  7. Under the Industrial Dispute Act, 1947, what is the role of the "Works Committee" and which of the following correctly describes its function?
  8. The court in this case justified application of Article 30(1) to educational institutions established by religious and linguistic minorities before commencement of Constitution through a co-joint reading of Article 30, with Articles 13 and 372. In doing so it observed that 'Article 13(1) has a retroactive effect and not a retrospective effect.' Which of the following statement best captures the difference between the two effects?
  9. Which of the following is NOT an essential of a valid gift:
  10. The element of _________ is common to all the three transactions, i.e. Gift, Settlement and Will:

Important Questions from Legal Aptitude

  1. As per section 96 of the Transfer of Property Act, the provisions which apply to _________ shall, so far as may be, apply to a mortgage by deposit of title-deeds.
  2. In a mortgage by deposit of title-deeds, after the deposit of the title-deeds, if the creditor and the borrower choose to record their transaction in a memorandum reducing other terms and conditions (in addition to what flow from the mortgage by deposit of title-deeds) with regard to the deposit in the form of a memorandum/document, then the memorandum/document requires registration under section 17(1)(c) of the Registration Act. In this context which among the following propositions is not correct?
  3. The Supreme Court's final decision on the appeal filed by M/s. Balaji Traders was to:
  4. In which of the following cases, the Supreme Court read down the word "adult male" in Section 2(q) of the Protection of Women from Domestic Violence Act, 2005?
  5. The Supreme Court emphasized that the expression "extinguishment of any right therein" is of wide import. What does this expression cover?
Need Expert Advice?
More Questions from CLAT

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App