Which of the following infrastructure components are included in the Zojila Tunnel Project? (1) Snow galleries (2) Avalanche protection structures (3) Bi-directional horse shoe passage (4) Inland waterways
(1), (2) and (3) only
The Zojila Tunnel is being built under the Zojila Pass on the Srinagar-Leh highway to give all-weather road connectivity between the Kashmir valley and Ladakh. At about 13 km it will be the longest road tunnel in India.
The main tunnel is a single-tube, bi-directional road tunnel with a horseshoe-shaped cross-section. The approach road includes snow galleries, cut-and-cover sections and avalanche protection structures to keep traffic moving in heavy snowfall.
Inland waterways have nothing to do with this high-altitude road project, so component (4) is not included.
Hence, (1), (2) and (3) only.
Which of the following statements are true about Economic Infrastructure Investment?
(i) It is generally aimed to realize relatively more direct benefits than in social infrastructure.
(ii) It is generally smaller in size.
(iii) It is generally invites from public sector as well as private sector.
Which of the following statement causes the continuation of bridge rebuilding, road repairs, and waterline repairs in India?
(i) Inadequate maintenance leading to ongoing repairs
(ii) Utility cuts and rework
(iii) Poor initial construction quality
(iv) Fair prices given to workers
Buckingham canal connects the following two states.