What is the correct sequence of steps involved in the master production schedule preparation? (A) Obtaining the net requirement of materials (B) Revising the preliminary master production schedule to accommodate the inadequacy of materials (C) Obtaining the specification on required production (D) Assessing the inventory in hand and on order (E) Determining the gross requirements of materials using MRP Choose the correct answer from the options given below:
(C), (E), (D), (A), (B)
The Master Production Schedule (MPS) is a plan for the production of individual end items. It specifies what products are to be produced, how many, and when. Preparing an accurate MPS is crucial for effective production planning and inventory management.
Let's break down the steps provided and determine the logical sequence for preparing a master production schedule.
Let's arrange these steps in a logical flow for preparing an MPS:
Therefore, the correct sequence of steps involved in the master production schedule preparation, based on the logical flow of production planning and material requirements, is (C), (E), (D), (A), (B).
| Step Order | Description |
|---|---|
| 1 | (C) Obtain specification on required production |
| 2 | (E) Determine gross requirements of materials using MRP |
| 3 | (D) Assess inventory in hand and on order |
| 4 | (A) Obtain net requirement of materials |
| 5 | (B) Revise preliminary MPS to accommodate inadequacy |
| Step ID | Description | Role in MPS/MRP |
|---|---|---|
| (A) | Obtaining net requirement of materials | Calculates the actual quantity of materials needed after considering existing stock and scheduled receipts. |
| (B) | Revising the preliminary master production schedule to accommodate the inadequacy of materials | Adjusts the production plan based on resource availability (materials, capacity) identified in previous steps. |
| (C) | Obtaining the specification on required production | Defines what final products are needed and when, forming the basis of the MPS. |
| (D) | Assessing the inventory in hand and on order | Identifies available stock and expected deliveries to offset gross requirements. |
| (E) | Determining the gross requirements of materials using MRP | Calculates the total material needs for the planned production quantity using BOM data. |
The Master Production Schedule (MPS) and Material Requirements Planning (MRP) are key components of production planning systems.
The sequence (C), (E), (D), (A), (B) reflects the flow where the production plan (C) drives the calculation of total needs (E), which are then offset by what's available (D) to determine the actual material needs (A), potentially leading to adjustments in the original plan (B) if resources are insufficient.
The essential conditions for price discrimination practice to succeed in a different markets are
A. Firms must have strong interdependence per se
B. Firm must have some control over the price of the product
C. Differentiated products and strong entry restrictions
D. Price elasticity of demand must differ in different markets
E. Markets for the products must be separable
Choose the correct answer from the options given below:
A salesperson who relies on creative methods for selling products and services is called:
Which of the following are the examples of need for status?
(A) Being in a position of authority over others
(B) Having executive privileges
(C) Participating in pleasant social activities
(D) Working for the right company in the right job
(E) Living in the right neighbourhood
Choose the most appropriate answer from the options below:
Marketing feasibility of any idea includes the following aspects :
(a) Current and future demand estimates
(b) Market segmentation and identification of target markets
(c) Competition analysis
(d) Market testing
Which of the following option are correct?
Which of the following could be the most appropriate title of the passage?