What is the correct sequence of steps involved in the master production schedule preparation?

(A) Obtaining the net requirement of materials

(B) Revising the preliminary master production schedule to accommodate the inadequacy of materials

(C) Obtaining the specification on required production

(D) Assessing the inventory in hand and on order

(E) Determining the gross requirements of materials using MRP

Choose the correct answer from the options given below:

The correct answer is

(C), (E), (D), (A), (B)

Understanding Master Production Schedule Preparation Steps

The Master Production Schedule (MPS) is a plan for the production of individual end items. It specifies what products are to be produced, how many, and when. Preparing an accurate MPS is crucial for effective production planning and inventory management.

Let's break down the steps provided and determine the logical sequence for preparing a master production schedule.

  • (A) Obtaining the net requirement of materials: This step involves calculating the actual amount of material needed after considering what's available in inventory and what's on order.
  • (B) Revising the preliminary master production schedule to accommodate the inadequacy of materials: After determining if there are enough materials (or capacity), the initial plan might need adjustments if there are shortages or other constraints.
  • (C) Obtaining the specification on required production: This is usually the starting point, understanding what products are needed and in what quantities and timeframes, often based on forecasts or customer orders.
  • (D) Assessing the inventory in hand and on order: This step involves checking current stock levels and incoming material shipments. This information is needed to determine net requirements.
  • (E) Determining the gross requirements of materials using MRP: Using the Bill of Materials (BOM) and the required production quantity (from the MPS), the total amount of each material needed *before* considering existing inventory is calculated. This is often done using Material Requirements Planning (MRP) logic.

Sequencing Master Production Schedule Preparation

Let's arrange these steps in a logical flow for preparing an MPS:

  1. The process typically starts with understanding what needs to be produced. This comes from forecasts or customer orders, leading to the required production specifications. So, step (C) Obtaining the specification on required production is the starting point.
  2. Once we know what finished products to produce, we need to figure out the total amount of raw materials and components required for that production plan. This involves using the Bill of Materials (BOM) and calculating the total or gross requirements for each item, often using MRP principles. So, step (E) Determining the gross requirements of materials using MRP follows.
  3. Before we can determine how much we actually need to order or produce (net requirements), we must know what we currently have available or is already scheduled to arrive. This means checking the existing inventory. Thus, step (D) Assessing the inventory in hand and on order comes next.
  4. With the gross requirements calculated and the available inventory known, we can then figure out the net requirement — the difference between what is needed in total and what is already available. This is step (A) Obtaining the net requirement of materials.
  5. Finally, after determining the net requirements and potential shortages or capacity issues based on these needs, the initial production plan (the preliminary MPS) might need to be adjusted or revised to make it feasible. This addresses any inadequacies found. This is step (B) Revising the preliminary master production schedule to accommodate the inadequacy of materials.

Therefore, the correct sequence of steps involved in the master production schedule preparation, based on the logical flow of production planning and material requirements, is (C), (E), (D), (A), (B).

Step Order Description
1 (C) Obtain specification on required production
2 (E) Determine gross requirements of materials using MRP
3 (D) Assess inventory in hand and on order
4 (A) Obtain net requirement of materials
5 (B) Revise preliminary MPS to accommodate inadequacy

Revision Table: Master Production Schedule Steps

Step ID Description Role in MPS/MRP
(A) Obtaining net requirement of materials Calculates the actual quantity of materials needed after considering existing stock and scheduled receipts.
(B) Revising the preliminary master production schedule to accommodate the inadequacy of materials Adjusts the production plan based on resource availability (materials, capacity) identified in previous steps.
(C) Obtaining the specification on required production Defines what final products are needed and when, forming the basis of the MPS.
(D) Assessing the inventory in hand and on order Identifies available stock and expected deliveries to offset gross requirements.
(E) Determining the gross requirements of materials using MRP Calculates the total material needs for the planned production quantity using BOM data.

Additional Information: MPS and MRP Concepts

The Master Production Schedule (MPS) and Material Requirements Planning (MRP) are key components of production planning systems.

  • MPS: The MPS is the primary driver for MRP. It translates the aggregate production plan into a specific plan for individual end items. It deals with independent demand (finished goods, spare parts).
  • MRP: MRP takes the MPS, Bill of Materials (BOM), and inventory data as input. It calculates the time-phased requirements for raw materials, components, and sub-assemblies (dependent demand) needed to execute the MPS. It determines when orders should be placed and when they should be received to meet the production schedule.
  • Bill of Materials (BOM): A BOM is a list of raw materials, sub-assemblies, intermediate assemblies, sub-components, parts, and the quantities of each needed to manufacture an end product. It defines the structure of the product.
  • Inventory Data: Accurate records of current stock levels (on hand) and scheduled receipts (on order) are essential for calculating net requirements in MRP.

The sequence (C), (E), (D), (A), (B) reflects the flow where the production plan (C) drives the calculation of total needs (E), which are then offset by what's available (D) to determine the actual material needs (A), potentially leading to adjustments in the original plan (B) if resources are insufficient.

Was this answer helpful?

Important Questions from Marketing Management

  1. The essential conditions for price discrimination practice to succeed in a different markets are

    A. Firms must have strong interdependence per se

    B. Firm must have some control over the price of the product

    C. Differentiated products and strong entry restrictions

    D. Price elasticity of demand must differ in different markets

    E. Markets for the products must be separable

    Choose the  correct  answer from the options given below:

  2. A salesperson who relies on creative methods for selling products and services is called:

  3. Which of the following are the examples of need for status?

    (A) Being in a position of authority over others

    (B) Having executive privileges

    (C) Participating in pleasant social activities

    (D) Working for the right company in the right job

    (E) Living in the right neighbourhood

    Choose the most appropriate answer from the options below:

  4. Marketing feasibility of any idea includes the following aspects :

    (a) Current and future demand estimates

    (b) Market segmentation and identification of target markets

    (c) Competition analysis

    (d) Market testing

    Which of the following option are correct?

  5. Which of the following could be the most appropriate title of the passage?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App