Understanding Ranging in Surveying

Ranging is a fundamental operation in surveying used to establish intermediate points on a survey line. This ensures that the line being measured is straight between the two end stations. There are two main types of ranging: direct ranging and indirect ranging.

Direct Ranging Explained

Direct ranging is performed when the two end points of the survey line are visible from each other. In this method, the surveyor (or head chainman) stands behind one end station, sights towards the other end station, and directs an assistant (or follower chainman) to hold and move ranging rods until they are in perfect alignment on the line. To perform direct ranging efficiently and accurately, a minimum of two persons is required: one to sight and direct, and one to hold and place the ranging rod.

  • Person 1 (Surveyor/Leader): Stands at one end station and sights along the line.
  • Person 2 (Assistant/Follower): Holds and positions the ranging rod at intermediate points as directed.

Indirect Ranging Explained

Indirect ranging, also known as reciprocal ranging, is necessary when the two end points of the survey line are not intervisible. This often happens due to obstacles like hills, buildings, or dense vegetation blocking the line of sight. In indirect ranging, the process involves setting up two intermediate points that are intervisible with each other and also intervisible with their respective end stations.

Consider a line AB where A and B are not visible from each other. We select two points C and D such that:

  • Point C is on the line AB (or close to it) and is visible from B.
  • Point D is on the line AB (or close to it) and is visible from A.
  • Points C and D are intervisible.

The process typically involves the surveyor and assistant positioning themselves at C and D and iteratively directing each other until both points C and D lie on the true line AB. For example, the person at C directs the person at D to move left or right until D appears to be on the line CB. Then, the person at D directs the person at C to move until C appears to be on the line DA. This reciprocal process is repeated until C and D are both correctly aligned on the line AB.

Even in this indirect process, to establish and adjust the positions of the intermediate points and direct the placement of ranging rods, a minimum of two persons is required:

  • Person 1 (Surveyor/Leader): Often positions themselves at one intermediate point (say, C) and directs the other person.
  • Person 2 (Assistant/Follower): Positions themselves at the other intermediate point (say, D) and moves as directed, holding the ranging rod.

Therefore, the minimum number of persons needed to perform indirect ranging is also two, just like direct ranging.

Comparison of Direct and Indirect Ranging
Feature Direct Ranging Indirect Ranging
End points intervisible? Yes No (due to obstacles)
Minimum Persons Required 2 2
Method Sighting directly between ends, placing intermediate rods. Reciprocal sighting between intermediate points, iteratively adjusting positions.

Based on the methods for both direct and indirect ranging, the minimum number of persons required in both cases is 2.

Revision Table: Ranging Personnel

Ranging Type Minimum Persons
Direct Ranging 2
Indirect Ranging 2

Additional Information on Surveying Ranging

Ranging is a crucial preliminary step before chaining (measuring distance) along a line. Proper ranging ensures the measured distance is the true horizontal distance between the end points, assuming the line is straight.

  • Ranging Rods: These are typically 2-3 meters long, painted in alternating bands of red and white (or black and white) for visibility, and have a pointed shoe at the bottom for fixing into the ground.
  • Obstacles: Obstacles in surveying can be broadly classified into obstacles to ranging (like a hill) and obstacles to chaining (like a pond) or obstacles to both (like a building). Indirect ranging deals specifically with obstacles preventing direct line of sight between end points.
  • Roles: In a typical surveying team for ranging and chaining, roles like Surveyor, Leader (or Head Chainman), and Follower (or Rear Chainman) are common. The Leader and Follower are directly involved in ranging and chaining, and the minimum team size for these tasks is typically two people.
Was this answer helpful?

Important Questions from Linear Measurement

  1. Which one is the CORRECT statement?

  2. The method of reciprocal ranging can be used in which of the following cases?

  3. The scale of a drawing is given as 1 : 20.

    What is the representative fraction?

  4. 1 chain is equal to

  5. __________ are used to mark the end of each chain during the chaining process.

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App