Select the correct option for the given statements. Statement 1: In level crossing, the canal water and drain water are allowed to intermingle with each other. Statement 2: A level crossing is generally provided when a large canal and huge drainage approaches each other practically at the same level.
Both statement 1 and statement 2 are true, and statement 2 is the correct explanation of statement 1
Let's analyze the given statements about level crossings in the context of irrigation and drainage works. Level crossings are important cross drainage works used in civil engineering projects.
Statement 1 says: "In level crossing, the canal water and drain water are allowed to intermingle with each other."
A level crossing is a type of cross drainage work where a canal and a drain (or natural stream) meet at approximately the same level. The design of a level crossing involves constructing regulators on both the canal and the drain. When the drain is in flood, its water is allowed to pass across the canal alignment, and the canal water is held back by closing the canal regulator. When the canal is running, the drain water is held back by closing the drain regulator, and the canal water is allowed to flow. However, during normal flow conditions or specific operational requirements, the waters are indeed allowed to mix or flow across each other's path at grade.
Therefore, the statement that canal water and drain water are allowed to intermingle in a level crossing is correct. Statement 1 is true.
Statement 2 says: "A level crossing is generally provided when a large canal and huge drainage approaches each other practically at the same level."
Cross drainage works are constructed where a canal intersects with a natural drain or stream. Different types of structures (like aqueducts, super passages, or level crossings) are chosen based on the relative levels of the canal bed and the drain bed, the size of the canal and drain, and the topography.
A level crossing is a suitable and often economical option when:
In such scenarios, allowing the waters to cross at the same level via a level crossing becomes the preferred solution. Therefore, Statement 2 accurately describes the conditions under which a level crossing is typically provided. Statement 2 is true.
Statement 2 describes the condition (large canal/drain, same level) that favors the selection of a level crossing structure. Given these conditions, the design of a level crossing involves allowing the canal water and drain water to meet and cross each other at grade, which inherently involves the potential for their intermingling (as described in Statement 1). The situation described in Statement 2 is the reason why a structure where water intermingles (Statement 1) is chosen over structures that keep the flows separate (like aqueducts or super passages).
Hence, Statement 2 provides the justification or the conditions leading to the implementation of the structure described in Statement 1. Statement 2 is the correct explanation for Statement 1.
Both Statement 1 and Statement 2 are true, and Statement 2 is the correct explanation for Statement 1.
| Statement | Truth Value | Reason |
|---|---|---|
| Statement 1: In level crossing, the canal water and drain water are allowed to intermingle with each other. | True | This is the operational characteristic of a level crossing where flows meet at grade. |
| Statement 2: A level crossing is generally provided when a large canal and huge drainage approaches each other practically at the same level. | True | These are the suitable conditions for selecting a level crossing over grade separation structures. |
| Feature | Description |
|---|---|
| Type of Structure | Cross Drainage Work |
| Relative Level of Canal & Drain | Approximately the same level |
| Water Interaction | Allowed to intermingle/cross at grade |
| Suitability | Economical for large flows at similar levels |
| Components | Regulators on canal and drain |
Cross drainage works are essential components of an irrigation system. They are structures built to safely cross the natural drainage lines (like streams, rivers, or nullahs) that intersect with the path of a canal. There are several types based on the relative levels:
Choosing the right type of cross drainage work like a level crossing depends on detailed site surveys, hydrological data, and economic considerations.
When the HFL of the drain is sufficiently below the bottom of the canal, so that the drainage water flows freely under gravity, the structure is known as _______
The velocity of drainage water in the barrels of syphon aqueduct is normally limited to
______ is a passage for water over a natural ground having a deck slab over it as path way for vehicles.
The distance between bottom of the bridge super structure and H.F.L is known as____.