All Exams Test series for 1 year @ ₹349 only
Question

S, M, E and F are working in shifts in a team to finish a project. M works with twice the efficiency of others but for half as many days as E worked. S and M have 6 hour shifts in a day, whereas E and F have 12 hours shifts. What is the ratio of contribution of M to contribution of E in the project?

The correct answer is

1:2

In this problem, we are asked to determine the ratio of the contribution of team member M to the contribution of team member E in a project. The overall contribution of an individual to a project depends on three main factors: their efficiency, the number of hours they work per day, and the total number of days they work. We need to analyze the given information for M and E and then calculate their individual contributions to find the required ratio.

Project Team Parameters: Efficiency and Shifts

Let's first define the efficiency levels and daily shift durations for the team members involved:

  • Efficiency:
    • The problem states that M works with twice the efficiency of others. Let's assume a base efficiency unit, say \(\text{Eff}\), for team members S, E, and F.
    • Therefore, the efficiency of E (\(\text{Eff}_{\text{E}}\)) = \(\text{Eff}\).
    • And the efficiency of M (\(\text{Eff}_{\text{M}}\)) = \(2 \times \text{Eff}\).
  • Shift Duration (Hours per Day):
    • S and M have 6-hour shifts in a day. So, the hours worked per day by M (\(\text{H}_{\text{M}}\)) = 6 hours.
    • E and F have 12-hour shifts. So, the hours worked per day by E (\(\text{H}_{\text{E}}\)) = 12 hours.

Determining Workdays for M and E

The problem provides a direct relationship regarding the number of days M and E worked on the project:

  • Let the number of days E worked on the project be \(\text{D}_{\text{E}}\).
  • The problem states that M worked for half as many days as E. Therefore, the number of days M worked (\(\text{D}_{\text{M}}\)) = \(\frac{1}{2} \times \text{D}_{\text{E}}\).

Calculating Individual Contributions to the Project

The total contribution of any team member to a project can be calculated using the following formula:

Contribution = Efficiency \(\times\) Hours per Day \(\times\) Number of Days Worked

Contribution of M

Let's apply the formula for team member M:

  • Efficiency of M (\(\text{Eff}_{\text{M}}\)) = \(2 \times \text{Eff}\)
  • Hours per day for M (\(\text{H}_{\text{M}}\)) = 6 hours
  • Number of days M worked (\(\text{D}_{\text{M}}\)) = \(\frac{1}{2} \times \text{D}_{\text{E}}\)

Substituting these values into the contribution formula:

\(\text{Contribution}_{\text{M}} = \text{Eff}_{\text{M}} \times \text{H}_{\text{M}} \times \text{D}_{\text{M}}\)

\(\text{Contribution}_{\text{M}} = (2 \times \text{Eff}) \times 6 \text{ hours/day} \times \left(\frac{1}{2} \times \text{D}_{\text{E}}\right) \text{ days}\)

\(\text{Contribution}_{\text{M}} = 2 \times 6 \times \frac{1}{2} \times \text{Eff} \times \text{D}_{\text{E}}\)

\(\text{Contribution}_{\text{M}} = 6 \times \text{Eff} \times \text{D}_{\text{E}}\)

Contribution of E

Now, let's apply the formula for team member E:

  • Efficiency of E (\(\text{Eff}_{\text{E}}\)) = \(\text{Eff}\)
  • Hours per day for E (\(\text{H}_{\text{E}}\)) = 12 hours
  • Number of days E worked (\(\text{D}_{\text{E}}\)) = \(\text{D}_{\text{E}}\)

Substituting these values into the contribution formula:

\(\text{Contribution}_{\text{E}} = \text{Eff}_{\text{E}} \times \text{H}_{\text{E}} \times \text{D}_{\text{E}}\)

\(\text{Contribution}_{\text{E}} = \text{Eff} \times 12 \text{ hours/day} \times \text{D}_{\text{E}} \text{ days}\)

\(\text{Contribution}_{\text{E}} = 12 \times \text{Eff} \times \text{D}_{\text{E}}\)

Finding the Contribution Ratio of M to E

To find the ratio of M's contribution to E's contribution, we divide the contribution of M by the contribution of E:

\(\text{Ratio} = \frac{\text{Contribution}_{\text{M}}}{\text{Contribution}_{\text{E}}}\)

\(\text{Ratio} = \frac{6 \times \text{Eff} \times \text{D}_{\text{E}}}{12 \times \text{Eff} \times \text{D}_{\text{E}}}\)

Notice that \(\text{Eff}\) and \(\text{D}_{\text{E}}\) are common terms in both the numerator and the denominator, so they cancel each other out:

\(\text{Ratio} = \frac{6}{12}\)

Simplifying the fraction:

\(\text{Ratio} = \frac{1}{2}\)

Thus, the ratio of the contribution of M to the contribution of E in the project is 1:2.

Summary of Team Member Contributions
Team Member Efficiency Hours Worked per Day Days Worked Calculated Contribution
M \(2 \times \text{Eff}\) 6 hours \(\frac{1}{2} \times \text{D}_{\text{E}}\) \((2 \times \text{Eff}) \times 6 \times (\frac{1}{2} \times \text{D}_{\text{E}}) = 6 \times \text{Eff} \times \text{D}_{\text{E}}\)
E \(\text{Eff}\) 12 hours \(\text{D}_{\text{E}}\) \(\text{Eff} \times 12 \times \text{D}_{\text{E}} = 12 \times \text{Eff} \times \text{D}_{\text{E}}\)

The final ratio of contributions is M : E = 1 : 2.

Was this answer helpful?

Important Questions from Numerical Estimation

  1. The number of digits you have to type to write all the page numbers of a book starting from I (first page) is 2019. What is the number of pages in that book?

  2. Two fair dice are thrown. The number of cases where the number appearing on the upper face of the first die is not less than that on the lower face of the second die is

  3. The number of Hens, Ducks, and Goats in farm P are 65, 91 and 169, respectively. The total number of Hens, Ducks and Goats in a nearby farm Q is 416. The ratio of hens : ducks : goats in farm Q is 5 : 14 : 13. All the hens, ducks and goats are sent from farm Q to farm P.

    The new ratio of hens : ducks : goats in farm P is ____________.

  4. A person divided an amount of Rs. 100,000 into two parts and invested in two different schemes. In one he got 10% profit and in the other he got 12%. If the profit percentages are interchanged with these investments he would have got Rs.120 less. Find the ratio between his investments in the two schemes.

  5. M and N start from the same location. M travels 10 km East and then 10 km North – East. N travels 5 km South and then 4 km South – East. What is the shortest distance (in km) between M and N at the end of their travel?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App