LIST-I
(Managerial
Function)LIST-II
(Description)A. Plan I. Implement the plan in practice; build trust and share norms to ensure implementation B. Do II. Make changes / improvements based on the data; action may be in process or end
processC. Check III. Strategic/action planning - decide what will be done at district/school or program
levelD. Act IV. Collect and analyse formative and summative data on key measures of
implementation
Choose the correct answer from the options given below:
This question requires matching the four core managerial functions, often referred to as the PDCA (Plan-Do-Check-Act) cycle, with their corresponding descriptions.
The PDCA cycle is a framework for continuous improvement:
| Managerial Function (LIST-I) | Description (LIST-II) |
|---|---|
| A. Plan | III. Strategic/action planning - decide what will be done at district/school or program level |
| B. Do | I. Implement the plan in practice; build trust and share norms to ensure implementation |
| C. Check | IV. Collect and analyse formative and summative data on key measures of implementation |
| D. Act | II. Make changes / improvements based on the data; action may be in process or endprocess |
Therefore, the correct matching is A-III, B-I, C-IV, D-II.