Question

It is proposed to construct bench terraces on a 10% hill slope. If the batter slope is $\frac{1}{2} \text{ H} : 1 \text{ V}$, the percentage area that will be lost for cultivation due to bench terracing is

The correct answer is
5.47

This question asks to calculate the percentage of area lost for cultivation when constructing bench terraces on a hill slope with a given batter slope.

Understanding Bench Terracing Parameters

We are given:

  • Hill Slope, $S = 10\% = 0.1$
  • Batter Slope notation: $ \frac{1}{2} \text{ H} : 1 \text{ V} $. This is interpreted as the ratio of Vertical (V) to Horizontal (H) components, meaning $V/H = 0.5 / 1 = 0.5$. So, the batter slope $m = 0.5$.

Calculating Area Lost

The percentage area lost for cultivation due to the construction of batters (cut and fill slopes) can be estimated using a formula that considers the hill slope and the batter slope.

A common formula used in this context is:

$ \text{Area Lost (\%)} = \frac{100 \times m \times S}{1 - S} $

Where:

  • $S$ is the hill slope (as a decimal)
  • $m$ is the batter slope (V/H, as a decimal)

Substitute the given values:

$ \text{Area Lost (\%)} = \frac{100 \times 0.5 \times 0.1}{1 - 0.1} $ $ \text{Area Lost (\%)} = \frac{100 \times 0.05}{0.9} $ $ \text{Area Lost (\%)} = \frac{5}{0.9} $ $ \text{Area Lost (\%)} \approx 5.555... \% $

Conclusion

The calculated area lost is approximately $5.56\%$. Comparing this to the options provided, the closest value is $5.47\%$.

Was this answer helpful?

Important Questions from Terraces

  1. Bench terraces are planned on $15\%$ hill slope. The vertical interval is $2.5\text{ m}$, and the riser has a slope of $1:1$. The earthwork in cutting is equal to the earthwork in filling. The volume of earthwork per hectare (in $\text{m}^3\text{.ha}^{-1}$) is ________ (Rounded off to the nearest integer)
  2. Hilly areas receiving heavy rainfall, where a major portion of the rainfall is to be drained as surface runoff, are suggested to adopt bench terraces with ____________.

  3. If the width of bench terrace is W, drop D and existing land slope S; then for 150% batter slope, the drop D will be
  4. Bench terraces are to be constructed on a 15% hill slope. The batter slope is 1:1 and vertical interval is 2.5 m. The earth work in cutting is equal to filling. The quantum of earthwork in $m^3 ha^{-1}$ will be
  5. For the eastern Himalayan region having hill slope of 16%, a bench terrace system is to be designed. It is found that the depth of cut for constructing the bench terrace cannot be more than 0.40 m due to the limitation of the soil depth. If a batter slope of $1\frac{1}{2}:1$ is proposed, the maximum possible width of the terrace and the required earthwork per hectare (assuming cut equal to fill) will be
Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App