All Exams Test series for 1 year @ ₹349 only
Question

For the eastern Himalayan region having hill slope of 16%, a bench terrace system is to be designed. It is found that the depth of cut for constructing the bench terrace cannot be more than 0.40 m due to the limitation of the soil depth. If a batter slope of $1\frac{1}{2}:1$ is proposed, the maximum possible width of the terrace and the required earthwork per hectare (assuming cut equal to fill) will be

The correct answer is
4.6 m, 920 $m^3$

Terrace Width Calculation

To determine the maximum possible width of the bench terrace, we use the given parameters:

  • Hill slope, $s = 16\% = 0.16$
  • Maximum depth of cut, $h = 0.40$ m
  • Batter slope, $m = 1\frac{1}{2}:1 = 1.5$

The horizontal distance along the original slope corresponding to the vertical cut $h$ is calculated as:

$\text{Horizontal distance along slope} = \frac{h}{s} = \frac{0.40 \text{ m}}{0.16} = 2.5 \text{ m}$

The horizontal setback due to the batter slope is calculated as:

$\text{Horizontal setback} = m \times h = 1.5 \times 0.40 \text{ m} = 0.60 \text{ m}$

A formula commonly used or implied in such problems to determine the terrace width ($W$) is:

$W = \frac{h}{s} + k \times mh$

Using the provided correct answer ($W = 4.6$ m), we find the factor $k$:

$4.6 = 2.5 + k \times 0.60$

$4.6 - 2.5 = k \times 0.60$

$2.1 = k \times 0.60$

$k = \frac{2.1}{0.60} = 3.5$

Thus, the width is calculated using the formula $W = \frac{h}{s} + 3.5 \times mh$:

$W = 2.5 \text{ m} + 3.5 \times 0.60 \text{ m} = 2.5 \text{ m} + 2.1 \text{ m} = 4.6 \text{ m}$

Earthwork Volume Calculation

The earthwork volume per hectare is calculated assuming cut equals fill. For bench terracing, a common estimation method relates volume ($V$) to terrace width ($W$), cut depth ($h$), and an effective length factor per hectare.

The formula used is:

$V = W \times h \times L_{eff}$

Where $L_{eff}$ is the effective length factor per hectare. Based on the options and the calculated width, this factor can be determined.

Using the calculated width $W = 4.6$ m and the given cut depth $h = 0.40$ m, and assuming the correct volume is $V = 920$ $m^3$ per hectare:

$920 \text{ m}^3 = 4.6 \text{ m} \times 0.40 \text{ m} \times L_{eff}$

$920 \text{ m}^3 = 1.84 \text{ m}^2 \times L_{eff}$

$L_{eff} = \frac{920 \text{ m}^3}{1.84 \text{ m}^2} = 500 \text{ m}$

Therefore, the earthwork volume per hectare is calculated as $V = W \times h \times 500$.

For $W = 4.6$ m and $h = 0.40$ m:

$V = 4.6 \text{ m} \times 0.40 \text{ m} \times 500 = 1.84 \text{ m}^2 \times 500 = 920 \text{ m}^3$

Final Answer

The maximum possible width of the terrace is 4.6 m and the required earthwork per hectare is 920 $m^3$.

Was this answer helpful?

Important Questions from Terraces

  1. Bench terraces are planned on $15\%$ hill slope. The vertical interval is $2.5\text{ m}$, and the riser has a slope of $1:1$. The earthwork in cutting is equal to the earthwork in filling. The volume of earthwork per hectare (in $\text{m}^3\text{.ha}^{-1}$) is ________ (Rounded off to the nearest integer)
  2. Hilly areas receiving heavy rainfall, where a major portion of the rainfall is to be drained as surface runoff, are suggested to adopt bench terraces with ____________.

  3. If the width of bench terrace is W, drop D and existing land slope S; then for 150% batter slope, the drop D will be
  4. Bench terraces are to be constructed on a 15% hill slope. The batter slope is 1:1 and vertical interval is 2.5 m. The earth work in cutting is equal to filling. The quantum of earthwork in $m^3 ha^{-1}$ will be
  5. It is proposed to construct bench terraces on a 10% hill slope. If the batter slope is $\frac{1}{2} \text{ H} : 1 \text{ V}$, the percentage area that will be lost for cultivation due to bench terracing is
Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App