If the R.L. of canal bed level and high flood level of drainage are 212.0 m and 210 m respectively, then the cross-drainage work will be
aqueduct
Cross-drainage works are crucial structures built when a canal and a natural drainage channel (like a river or stream) intersect. Their purpose is to allow one path of flow (either the canal or the drainage) to pass over or under the other, preventing the mixing of waters and ensuring the continuous operation of the canal.
The type of cross-drainage structure is determined by comparing the canal's relevant levels with the drainage channel's levels, particularly the High Flood Level (HFL).
The primary types are classified based on whether the canal flows over or under the drainage:
| Condition Comparison | Structure Type | Flow Arrangement |
|---|---|---|
| CBL > HFL of Drainage | Aqueduct | Canal over Drainage |
| HFL of Drainage > CBL | Syphon | Drainage under Canal |
| HFL of Drainage < CBL | Super Passage | Drainage over Canal |
We are given the following levels:
Now, let's compare these values:
$CBL = 212.0 \, m$
$HFL_{drainage} = 210 \, m$
We can see that $CBL > HFL_{drainage}$, as $212.0 \, m$ is greater than $210 \, m$.
Since the Canal Bed Level ($212.0 \, m$) is higher than the High Flood Level of the drainage ($210 \, m$), the canal must pass over the drainage channel.
Based on the classification criteria, when the canal flows over the drainage because its bed level is above the drainage's flood level, the structure is identified as an Aqueduct.
A cross drainage work in which a canal is provided over the natural drainage is called:
Which of the following is not a cross-drainage work?
The cross drainage structure in which the canal bed level is kept much higher than the high flood level (HFL) of a stream is called
In an aqueduct, natural drainage is kept at the following of a canal
When the drain is over the canal, and FSL of canal is below the bed level of drain the structure provided is known as