Identify the correct sequence of the Controlling process:

(A) Analysing deviations

(B) Measurement of actual performance

(C) Setting up standards

(D) Comparison of actual performance with standards

Choose the correct answer from the options given below:

The correct answer is

(4) (C), (B), (D), (A)

Understanding the Controlling Process in Management

The controlling process is a fundamental function of management. It involves ensuring that activities are performed according to plan and taking corrective action when necessary. This process helps organizations achieve their goals effectively and efficiently. Understanding the correct sequence of steps in the controlling process is crucial for effective management.

Steps of the Controlling Process

The question asks for the correct sequence of the Controlling process based on the given steps:

  • (A) Analysing deviations
  • (B) Measurement of actual performance
  • (C) Setting up standards
  • (D) Comparison of actual performance with standards

Let's break down the typical sequence of the controlling process:

  1. Setting up Standards: This is the first step. Standards are the criteria against which actual performance will be measured. They can be in terms of cost, time, output units, etc. Think of this as setting the target or benchmark. This corresponds to step (C).
  2. Measurement of Actual Performance: After standards are set and work begins, the next step is to measure the actual performance of the employees or the process. This measurement should be done as objectively as possible. This corresponds to step (B).
  3. Comparison of Actual Performance with Standards: Once the actual performance is measured, it is compared against the standards that were set in the first step. This comparison helps identify if the performance is on track, better than expected, or lagging behind. This corresponds to step (D).
  4. Analysing Deviations: If there is a difference (deviation) between the actual performance and the standard, this difference needs to be analyzed. The analysis aims to find out the reasons for the deviation and determine if it is significant enough to require corrective action. This corresponds to step (A).
  5. Taking Corrective Action: (While not explicitly listed as a separate step in the options, this is the logical next step after analyzing deviations). If significant deviations are found, corrective actions are taken to bring the performance back in line with the standards or to adjust the standards if they were unrealistic.

Determining the Correct Sequence

Based on the typical steps outlined above, the logical and correct sequence of the given options is:

  1. (C) Setting up standards
  2. (B) Measurement of actual performance
  3. (D) Comparison of actual performance with standards
  4. (A) Analysing deviations

Therefore, the correct sequence is (C), (B), (D), (A).

Step Description Corresponding Option
1 Establishing benchmarks or targets (C) Setting up standards
2 Measuring what has actually been achieved (B) Measurement of actual performance
3 Finding the difference between plan and actual (D) Comparison of actual performance with standards
4 Investigating why there is a difference (A) Analysing deviations

Conclusion

The correct sequence of the controlling process steps provided is setting standards, measuring performance, comparing performance to standards, and analyzing deviations. This ensures that managers can monitor progress, identify problems, and take necessary actions to achieve organizational objectives.

Revision Table: Key Controlling Process Steps

Sequence Step
1 Setting Standards
2 Measuring Performance
3 Comparing Performance to Standards
4 Analyzing Deviations
5 Taking Corrective Action (often included after deviation analysis)

Additional Information: Importance of the Controlling Process

The controlling function is vital for several reasons:

  • Achieving Goals: It helps organizations move towards their objectives by keeping activities on track.
  • Efficient Resource Utilization: Control helps identify wastage or inefficient use of resources, allowing for corrections.
  • Ensuring Order and Discipline: By setting clear expectations and monitoring performance, it promotes discipline within the organization.
  • Facilitating Coordination: Control systems help integrate the efforts of different departments and individuals.
  • Basis for Future Planning: The information gained from the controlling process helps in better planning for the future. By analyzing deviations and their causes, managers can set more realistic standards and develop improved plans.

Effective controlling requires a well-designed system that is flexible, timely, and provides accurate information. It is a continuous process that works in tandem with planning, organizing, and staffing to ensure overall organizational success.

Was this answer helpful?
The correct answer is

(4) (C), (B), (D), (A)

Correct Answer: (4) (C), (B), (D), (A)

Correct Sequence of the Controlling Process:

(C) Setting up standards – Establish benchmarks or expected outcomes.

(B) Measurement of actual performance – Measure what's actually being done.

(D) Comparison of actual performance with standards – Identify gaps.

(A) Analysing deviations – Understand the causes and take corrective actions.

Was this answer helpful?
The correct answer is

(4) (C), (B), (D), (A)

The correct sequence of the Controlling process is:

✅ (4) (C), (B), (D), (A)

Step-by-Step Explanation:

Setting up standards (C) – Establishing benchmarks/goals for performance. (First step)

Measurement of actual performance (B) – Collecting data on current performance.

Comparison of actual performance with standards (D) – Identifying gaps between actual and desired results.

Analyzing deviations (A) – Investigating causes of discrepancies to take corrective action. (Final step)

Why Other Options Are Incorrect:

(1) (A), (B), (C), (D) → Starts with analysis (illogical without prior steps).

(2) (A), (C), (B), (D) → Analysis cannot precede measurement or standards.

(3) (B), (A), (D), (C) → Measurement before standards is impractical.

Correct Answer:

Option 4: (C), (B), (D), (A)

Was this answer helpful?

Important Questions from Controlling

  1. From the following statements, identify the limitations of controlling.

    A. Ensuring order and discipline

    B. More cost is involved

    C. Organisational goals can be acquired

    D. No control on external factors

    E. Improves employee motivation

    Choose the correct answer from the options given below:

  2. Mr. Armaan is appointed as a quality control manager in a factory. The list of steps to monitor performance is shared with him. Mr. Armaan is asked to put the following steps in correct order:

    1. A. Employees must be trained to meet the target.
    2. B. Comparing the criteria set with the report of personal observation.
    3. C. Setting the criteria against which actual performance would be measured.
    4. D. Keeping in mind the key result area, the deviation which goes beyond the permissible limit is brought to notice.
    5. E. Personally observe the work done by workers.

    Choose the correct answer from the options given below:

  3. Rakesh is working in a blue pottery industry. His job is to paint the pots. He daily paints 30 pots, out of which two or three get spoiled due to mishandling of the pots. His foreman, Mr. Mohan, knows about the damages made by Rakesh but does not tell him anything. One day, Mohan scolds Rakesh as he had spoiled 5 pots out of 30. Identify the method of analyzing deviations used by Mohan.

  4. "Calling for information by undertaking inspection, conducting inquiries, and audits of stock exchanges and intermediaries." Which function of SEBI is highlighted by this statement?

  5. Which of the following is not a limitation of Controlling?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App