Activity A Activity B Optimistic time ($t_o$) = 4 days Optimistic time ($t_o$) = 4 days Most likely time ($t_l$) = 7 days Most likely time ($t_l$) = 6 days Pessimistic time ($t_p$) = 16 days Pessimistic time ($t_p$) = 22 days
The standard deviation for project activities is calculated using the PERT (Program Evaluation and Review Technique) formula, which estimates the dispersion of activity durations.
The formula for standard deviation ($\sigma$) is:
$ \sigma = \frac{t_p - t_o}{6} $
Where:
Given values for Activity A:
Calculation:
$ \sigma_A = \frac{16 \text{ days} - 4 \text{ days}}{6} = \frac{12 \text{ days}}{6} = 2 \text{ days} $
Given values for Activity B:
Calculation:
$ \sigma_B = \frac{22 \text{ days} - 4 \text{ days}}{6} = \frac{18 \text{ days}}{6} = 3 \text{ days} $
The standard deviation for Activity A is 2 days, and the standard deviation for Activity B is 3 days.
If the data are skewed, which option of central tendency measure is the most unreliable indicator?
Events A, Band C are mutually exclusive events such that \(P(A) = \dfrac{3x + 1}{3}, P(B) = \dfrac{1-x}{4}\)and \(P(C) = \dfrac{1-2x}{4}\)The set of possible values of x are in the interval
Let A, B be two events in a discrete probability space with ℙ(A) > 0 and ℙ(B) > 0. Which of the following are necessarily true?
The Excess Kurtosis of the Geometric distribution with parameter p is:
For a distribution, the mean is 10, variance is 16, γ 1is + 1 and β 2is 4. The distribution is: