A Change Point (CP) in levelling signifies a location where the temporary setup of the levelling instrument is changed. This is necessary to extend the survey line or bypass obstructions.
Key actions at a Change Point:
This process ensures continuity in elevation calculations across different instrument setups. Taking both BS and FS readings at the CP allows surveyors to accurately determine height differences between points separated by the instrument's relocation.
Therefore, a Change Point is defined by the procedure involving both backsight and foresight readings.
| Staff readings at station | ||
|---|---|---|
| Instrument set very near to station | A (m) | B (m) |
| A | 1.275 | 2.005 |
| B | 1.040 | 1.660 |