At a fixed instrument location in levelling, if the backsight reading at a point P is more than the foresight reading at a point Q, then

The correct answer is
point P has lower elevation than point Q

Levelling Calculation: Elevation Comparison

In surveying, levelling determines the elevation difference between points using instrument readings.

Let:

  • HI = Height of the Instrument above datum
  • BS = Backsight reading taken on point P
  • FS = Foresight reading taken on point Q
  • Elevation(P) = Elevation of point P
  • Elevation(Q) = Elevation of point Q

With a fixed instrument location:

The height of the instrument (HI) can be calculated using the backsight reading:

$ \text{HI} = \text{Elevation}(\text{P}) + \text{BS} $

The elevation of the next point (Q) can be calculated using the foresight reading:

$ \text{HI} = \text{Elevation}(\text{Q}) + \text{FS} $

Equating the two expressions for HI:

$ \text{Elevation}(\text{P}) + \text{BS} = \text{Elevation}(\text{Q}) + \text{FS} $

Rearranging to find the elevation difference between P and Q:

$ \text{Elevation}(\text{P}) - \text{Elevation}(\text{Q}) = \text{FS} - \text{BS} $

The question states that the backsight reading at P is more than the foresight reading at Q:

$ \text{BS} > \text{FS} $

This implies that the difference (FS - BS) is negative:

$ \text{FS} - \text{BS} < 0 $

Therefore:

$ \text{Elevation}(\text{P}) - \text{Elevation}(\text{Q}) < 0 $

Which means:

$ \text{Elevation}(\text{P}) < \text{Elevation}(\text{Q}) $

Conclusion:

Point P has a lower elevation than point Q.

Was this answer helpful?

Important Questions from Levelling Methods

  1. Which one of the following is the purpose of taking a backsight observation in levelling?
  2. The observations of a reciprocal levelling operation carried out from two stations A and B are given in table. It is known that the instrument has collimation error. The correct staff reading over station B when the instrument is set very near to station A is ________ m (Rounded off to three decimal places).

    Assume all other errors are negligible.

    Staff readings at station
    Instrument set very near to stationA (m)B (m)
    A1.2752.005
    B1.0401.660
  3. A level with the height of the instrument being 2.550 m has been placed at a station having a Reduced Level (RL) of 130.565 m. The instrument reads 3.665 m on a levelling staff held inverted at the bottom of a bridge deck. The RL of the bottom of the bridge deck is __________ m (rounded off to 3 decimal places).
  4. In levelling between two points P and Q on opposite banks of a river, the level was set up near P, and the staff reading on P and Q were 2.165 m and 3.810 m, respectively. The level was then moved and set up near Q and the respective staff readings on P and Q were 0.910 m and 2.355 m. The true difference of level between P and Q is __________ m (rounded off to 3 decimal places).
  5. Change Point (CP) in levelling refers to a location where
Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App