All Exams Test series for 1 year @ ₹349 only
Question

______ are the temporary joints left between subsequent concreting operations, their position should be pre - planned before concreting is started.

The correct answer is

Construction joints

Understanding Construction Joints in Concrete

When undertaking large concrete pours, it's often not possible or practical to complete the entire structure in a single continuous operation. There are planned pauses where one section of concrete is poured and allowed to set before the next section is placed. These planned breaks create temporary interfaces between the different pours.

The question asks to identify the type of temporary joints left between subsequent concreting operations that are pre-planned. Let's look at the different types of joints mentioned:

  • Expansion joints: These joints are designed to allow for the expansion and contraction of concrete due to temperature changes, preventing cracking. They are filled with compressible material and isolate sections of the structure. They are not primarily temporary joints used between planned pours.
  • Construction joints: These are joints intentionally placed where concreting is stopped and later resumed. They are essentially planned interfaces between concrete placements. Their location is determined in advance during the planning phase of the project to ensure structural integrity and workability. They are indeed temporary in the sense that they represent the end of one concreting operation and the start of another at a specific location, left between subsequent pours.
  • Contraction joints: Also known as control joints, these joints are created to control the location of cracks caused by concrete shrinkage during curing. They create weakened planes where cracks are encouraged to form neatly. They are typically cut or grooved into the concrete after it has been placed, not left between subsequent pours.
  • Isolation joints: These joints separate concrete slabs from other structural elements like walls, columns, or foundations. They allow for independent vertical and horizontal movement between the slab and the adjacent structure, preventing stress transfer and cracking. They isolate structural components.

Based on the description of temporary joints left between subsequent concreting operations whose position is pre-planned, the correct term is construction joints. They mark the end of one concrete pour and the beginning of the next.

Was this answer helpful?

Important Questions from Concrete

  1. Which one of the following is utilized to determine the long-term deformation of concrete under sustained loading?
  2. Water-cement ratio is the ratio of:

  3. Aerated concrete is produced by the addition of:

  4. Two statements associated with concrete are given. Select the correct option with regard to these statements.

    1: As the compaction factor increases, slump decreases.

    2: Slump test helps in qualitatively understand the setting time of concrete.

  5. From theory of elasticity, the splitting tensile strength f ct is given by -
    Where P is the maximum applied load, d is the diameter and L is the length of the cylinder.

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App