An interface between the functional application and the data is
Database management system
The question asks about the component that acts as an interface between a functional application and the data it uses. Let's break down what this means.
A functional application is a software program designed to perform specific tasks, like managing inventory, handling customer records, or processing transactions. This application needs to store and retrieve data.
The data is the raw information that the application uses and manages. This data is typically stored in a structured way, often in files or a database.
The interface is the layer that allows the application to interact with the stored data without needing to know the intricate details of how the data is physically stored or organized. It provides a set of tools and commands for the application to perform operations like storing new data, finding existing data, updating data, or deleting data.
Let's look at the given options:
The Database Management System (DBMS) is precisely the software that serves as the interface between the application and the physical data stored in the database. It handles tasks such as:
An application sends requests to the DBMS (often using a query language like SQL), and the DBMS processes these requests, interacts with the physical data files, and returns the results to the application. This hides the complexity of data storage from the application programmer.
Based on the definitions and roles, the system that acts as the interface between a functional application and the data is the Database management system.
Factors which govern the operating cost of an equipment are :
1. Purchase price of the equipment
2. Depreciation due to regular use
3. Cost of operation, maintenance and repairs
Which of the above statements are correct ?
In Emerson's efficiency plan of wage incentive system, the bonus is paid to-
Match List I with List II
LIST I (Project Network concepts) | LIST II (Underlying meaning) | ||
| A. | Crashing an activity | I. | Length of the longest path through the project network |
| B. | Project Network | II. | It shows the time and cost when the activity is fully crashed |
| C. | Critical path | III. | It consists of a number of nodes and a number of arcs that connects two different nodes |
| D. | Crash point | IV. | Taking special (costly) measures to reduce the duration of an activity below its normal value |
Choose the correct answer from the options given below:
The following statements relate to project network. Choose the correct code for the statements being correct or incorrect.
Statement I: An activity cannot be represented by more than one arrow, but an arrow can represent one or more activities.
Statement II : The activities in a critical path can be preponed or postponed.
A public limited company has 9,00,000 shares outstanding at current market price of Rs. 130 per share. The company needs Rs. 2.25 crores to finance its proposed new project. The board of the company has decided to issue rights shares to raise the required money at Rs. 75 per share (as subscription price) to ensure that the rights issue is fully subscribed. How many rights are required to purchase a new share ?