The number of management layers in a firm is determined by the
Span of control
The structure of a firm's management hierarchy is influenced by several factors. The question asks about what primarily determines the number of management layers.
Let's look at the given options and how they relate to organizational structure and the number of management layers:
The span of control is the key factor determining the number of management layers. Here's why:
Therefore, the number of management layers in a firm is directly influenced by the span of control adopted throughout the organization.
Based on the analysis, the number of management layers is primarily determined by how many subordinates each manager is responsible for, which is known as the span of control.
An interface between the functional application and the data is
The following statements relate to project network. Choose the correct code for the statements being correct or incorrect.
Statement I: An activity cannot be represented by more than one arrow, but an arrow can represent one or more activities.
Statement II : The activities in a critical path can be preponed or postponed.
A public limited company has 9,00,000 shares outstanding at current market price of Rs. 130 per share. The company needs Rs. 2.25 crores to finance its proposed new project. The board of the company has decided to issue rights shares to raise the required money at Rs. 75 per share (as subscription price) to ensure that the rights issue is fully subscribed. How many rights are required to purchase a new share ?
What are the characteristics of job shop production ?
A. Different product types are produced
B. Very large quantities are produced
C. Single type of product is produced
D. Low quantities of product are produced
Match List I with List II
LIST I (Project Network concepts) | LIST II (Underlying meaning) | ||
| A. | Crashing an activity | I. | Length of the longest path through the project network |
| B. | Project Network | II. | It shows the time and cost when the activity is fully crashed |
| C. | Critical path | III. | It consists of a number of nodes and a number of arcs that connects two different nodes |
| D. | Crash point | IV. | Taking special (costly) measures to reduce the duration of an activity below its normal value |
Choose the correct answer from the options given below: