A, B, and C can complete a project alone in 12 days, 18 days, and 24 days, respectively. If they all work together for 4 days, what fraction of the project will remain incomplete?

The correct answer is

\(\frac{5}{18}\)

If a person completes a project alone in n days, the person does \(\frac{1}{n}\) of it in one day; the one-day works of people working together add up.

One-day work of A, B and C together = \(\frac{1}{12} + \frac{1}{18} + \frac{1}{24} = \frac{6 + 4 + 3}{72} = \frac{13}{72}\).

Work done in 4 days = \(4 \times \frac{13}{72} = \frac{52}{72} = \frac{13}{18}\).

So the fraction that remains incomplete = \(1 - \frac{13}{18} = \frac{5}{18}\).

Check: take the project as 72 units (LCM of 12, 18, 24); A, B and C do 6, 4 and 3 units a day, i.e. 13 units a day, so 52 units in 4 days, leaving 20 units, and 20/72 = 5/18.

Hence, \(\frac{5}{18}\).

Was this answer helpful?

Similar Questions

  1. Two people of equal efficiency working together can complete a task in 6 hours. How long would it take one person alone to complete the same task?

  2. A and B can complete a piece of work in 12 days and 18 days respectively. They work together for 4 days, after which A leaves the work. B continues alone for 6 days, and then C joins B. If C alone can complete the whole work in 9 days, find the total time (in days) taken to complete the work.

  3. A group of 6 identical workers can finish a task in 9 days. How many days will it take if only 3 of them work together to complete the same task?

  4. Three friends, Arjun, Kabir, and Neha, can paint a fence in 12 hours, 6 hours, and 4 hours, respectively. If they work together, how long will they take to paint the fence?

  5. Ram can do a job in x days. Mohan is twice as fast as Ram. Raghav is 50% more efficient than Mohan. If Ram, Mohan and Raghav together finish the job in 4 days, what is the value of x?

  6. A can complete a piece of work in 12 days and B can complete the same work in 18 days. They start working together. After 4 days, A leaves the work. In how many more days will B finish the remaining work?


Important Questions from Work Efficiency

  1. Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?

  2. A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?

  3. 24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?

  4. A and B together can do a piece of work in 4 days, B and C can do it in 6 days, A and C can do it in 8 days. Then A, B and C together can do the same work in :-

  5. A can complete 50% of a work in 9 days and B can do 25% of the work in 9 days, if they work alone. If they work together then how much work (in percentage) can be completed in 6 days?

Need Expert Advice?
Upcoming Exams
RRB JE
October 27, 2026
RRB ALP
November 03, 2026
Test Series
RRB Technicians img
Railways
RRB Technician Grade 1 (Signal) 2026 Mock Test Series
270 Tests 3 Tests Free
7598 Attempts
4.8(211)
English, Hindi, Bengali +7 More
More Questions from RRB Technicians

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App