Question

A, B, and C can complete a project alone in 12 days, 18 days, and 24 days, respectively. If they all work together for 4 days, what fraction of the project will remain incomplete?

This question was previously asked in
RRB Technician 2026 Grade 3 Question Paper (7-Oct-2026) (Shift 3)
The correct answer is

\(\frac{5}{18}\)

If a person completes a project alone in n days, the person does \(\frac{1}{n}\) of it in one day; the one-day works of people working together add up.

One-day work of A, B and C together = \(\frac{1}{12} + \frac{1}{18} + \frac{1}{24} = \frac{6 + 4 + 3}{72} = \frac{13}{72}\).

Work done in 4 days = \(4 \times \frac{13}{72} = \frac{52}{72} = \frac{13}{18}\).

So the fraction that remains incomplete = \(1 - \frac{13}{18} = \frac{5}{18}\).

Check: take the project as 72 units (LCM of 12, 18, 24); A, B and C do 6, 4 and 3 units a day, i.e. 13 units a day, so 52 units in 4 days, leaving 20 units, and 20/72 = 5/18.

Hence, \(\frac{5}{18}\).

Was this answer helpful?

Similar Questions

  1. Ram can do a job in x days. Mohan is twice as fast as Ram. Raghav is 50% more efficient than Mohan. If Ram, Mohan and Raghav together finish the job in 4 days, what is the value of x?

  2. Two people of equal efficiency working together can complete a task in 6 hours. How long would it take one person alone to complete the same task?

  3. A can complete a piece of work in 12 days and B can complete the same work in 18 days. They start working together. After 4 days, A leaves the work. In how many more days will B finish the remaining work?

  4. A and B can complete a piece of work in 12 days and 18 days respectively. They work together for 4 days, after which A leaves the work. B continues alone for 6 days, and then C joins B. If C alone can complete the whole work in 9 days, find the total time (in days) taken to complete the work.

  5. A group of 6 identical workers can finish a task in 9 days. How many days will it take if only 3 of them work together to complete the same task?

  6. Three friends, Arjun, Kabir, and Neha, can paint a fence in 12 hours, 6 hours, and 4 hours, respectively. If they work together, how long will they take to paint the fence?


Important Questions from Work Efficiency

  1. M is thrice as efficient as workman as N and therefore is able to finish a job in 264 days less than N. Then in how many days can N finish the entire work?
  2. A can do a piece of work in $1455$ days. B is $25\%$ more efficient than A. Find the number of days taken by B to do the same piece of work.
  3. 45 people take 18 days to dig a pond. If the pond would have to be dug in 15 days, then the number of people to be employed will be
  4. A stock of food is enough for 240 men for 48 days. How long will the same stock last for 160 men?
  5. One contractor had undertaken a construction work. To complete the given job, he sought labour comprising 24 men for 12 days for working 10 hours a day. But due to festival season, as the labour had gone to their respective hometowns, he could get only 15 men and they too were willing to work 8 hours a day. With this much labour, in how many days would he be able to complete the same job?

Need Expert Advice?
Upcoming Exams
RRB Staff Nurse
November 23, 2026
RRB Paramedical
November 23, 2026
Test Series
RRB Technicians img
Railways
RRB Technician Grade 1 (Signal) 2026 Mock Test Series
270 Tests 3 Tests Free
7613 Attempts
4.8(215)
English, Hindi, Bengali +7 More

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App