All Exams Test series for 1 year @ ₹349 only
Question

Which one of the following factors should be kept in view while fixing the design period for waterworks?

The correct answer is
Life of the pipe and other structural materials used in the water supply scheme

Understanding the Design Period for Waterworks

The design period for waterworks refers to the future period for which the components of the water supply scheme are designed to be adequate in capacity and functionality to meet the projected demands. Selecting an appropriate design period is crucial for the economic and technical feasibility of a water supply project. A shorter design period means frequent expansions, while a longer one means higher initial costs for potentially oversized infrastructure.

Factors Influencing Waterworks Design Period Selection

Several factors influence the selection of the design period for a water supply project. Let's analyze the options provided in the question:

  • Funds available for the completion of the project: While the availability of funds is essential for any project's execution, linking *more* funds directly to a *longer* design period is not the primary technical criterion. Financial feasibility studies are done for the selected design period, not the other way around. The amount of funds might influence the scale or phasing of construction, but not the fundamental duration for which the system is designed to meet needs.
  • Life of the pipe and other structural materials used in the water supply scheme: This is a critically important factor. The design period cannot realistically exceed the useful life of the major, long-lasting, and difficult-to-replace components like pipes, reservoirs, and treatment plant structures. Designing a system for 50 years using pipes expected to last only 30 years would necessitate major replacements midway through the design period, leading to significant disruption and cost. Therefore, the lifespan of these materials acts as a practical upper limit on the design period.
  • As far as possible the design period should be longer than life of materials used in the water supply scheme: This statement contradicts sound engineering principles. If the design period is longer than the lifespan of the materials, the infrastructure will likely fail or require complete replacement before the intended design period is over, rendering the initial design period unrealistic and uneconomical. The design period should generally align with or be limited by the life of the longest-lasting critical components.
  • Rate of interest on the loans taken to complete the project: Financial factors like the interest rate on loans affect the overall economic viability and cost-effectiveness of the project over its life. Higher interest rates might favour phased construction or careful cost management, but they do not directly determine the technical period for which the infrastructure capacity is designed. The technical design period is based on demand forecasts and infrastructure lifespan.

Why Material Life is a Key Factor

The lifespan of the materials used in constructing waterworks infrastructure, particularly the major components like transmission and distribution pipes, reservoirs, and structural elements of treatment plants, is a fundamental constraint on the design period. These components represent a significant portion of the project cost and are expensive and disruptive to replace. Therefore, the chosen design period must be feasible within the expected useful life of these critical materials to ensure the system remains functional and reliable throughout the design horizon without premature major replacements.

Other factors considered when fixing the design period include:

  • Population growth rate and projections.
  • Per capita water demand trends.
  • Availability of land for future expansion.
  • Ease or difficulty of expanding the system in the future.
  • Anticipated rate of development in the service area.

However, among the options provided, the life of the pipe and other structural materials is the most direct and significant technical factor that limits the practical design period for waterworks infrastructure.

Revision Table: Key Concepts in Waterworks Design

Concept Description Relevance to Design Period
Design Period The future time horizon for which a water supply system is planned to meet projected demands. The fundamental period being determined.
Population Forecasting Estimating future population within the service area. Determines future demand, a key input for capacity design.
Water Demand The amount of water required by the population and other users (industrial, commercial, etc.). Capacity of infrastructure must meet projected future demand.
Material Lifespan The expected useful life of components like pipes, pumps, structures. Limits the practical upper bound of the design period.
Economic Analysis Evaluating the cost-effectiveness of different design options over the project's life. Helps choose the most financially feasible design period and capacity.

Additional Information on Waterworks Design Considerations

Designing a water supply system involves projecting future needs and selecting appropriate infrastructure. The design period is a critical parameter in this process. Different components of a water supply scheme might have different design periods based on their lifespan, ease of expansion, and cost:

  • Source and Collection Works: Often designed for a longer period (e.g., 40-50 years) if expansion is difficult.
  • Pumping Machinery: Designed for a shorter period (e.g., 15-20 years) as they are easier to replace or augment.
  • Water Treatment Plants: Designed for an intermediate period (e.g., 20-30 years), with provisions for future expansion.
  • Transmission Mains: Designed for a longer period (e.g., 30-40 years) as they are buried and costly to replace.
  • Distribution System (Pipes): Designed for a longer period (e.g., 30-40 years or more) as they are extensive and buried underground.
  • Service Reservoirs: Designed for an intermediate period (e.g., 20-30 years), often built in phases.

The overall design period for the entire waterworks project is often dictated by the components that are most difficult or expensive to expand or replace, typically transmission and distribution mains, whose lifespan is directly tied to the life of the pipe materials used.

Was this answer helpful?

Important Questions from Miscellaneous-Engineering

  1. Which one of the following lists identifies the wastes from common manufacturing and industrial process, such as solvents that have been used in cleaning or degreasing operations?
  2. When once a pocket of smoke, containing air pollutants, is released into the atmosphere from a source like an automobile or a factory chimney, it gets dispersed into the atmosphere into various directions depending upon the 

    1. prevailing winds 

    2. temperature 

    3. pressure conditions 

    Select the correct answer.

  3. During the compaction test, the weight of compacted soil specimen along with mould is 38.2 N. The volume and weight of mould are 0.95×10-3 m³ and 20.5 N respectively and the water content is 12%. The dry unit weight of the compacted specimen will be nearly

  4. Which one of the following is a time-dependent reversible process in which materials under constant composition and volume soften when remolded?
  5. The compressibility of a saturated, clay-water system is determined by means of the apparatus devised by Terzaghi known as
Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App