All Exams Test series for 1 year @ ₹349 only
Question

Which of the following statement is the correct one?

The correct answer is

A dummy is a type of operation which neither requires time nor any resource.

Project Network Diagram Concepts

Let's break down each statement to understand which one correctly describes a concept related to project network diagrams or activities.

Serial Activities

Statement 1 says: Serial activities can exist simultaneously or concurrently.

Analysis: Serial activities are defined as those activities that must be completed in a strict sequence. One activity must finish before the next one can begin. Therefore, by definition, serial activities cannot happen simultaneously or concurrently relative to each other within the same sequence. Different sequences of activities might run concurrently, but activities *within* a single serial path cannot. This statement is incorrect.

Project Events

Statement 2 says: A tail event or a start event of a project has only incoming arrows.

Analysis: In a project network diagram:

  • A start event (often the first event) has activities beginning from it, meaning it has only outgoing arrows.
  • A tail event (or end event, often the last event) has activities finishing at it, meaning it has only incoming arrows.

The statement incorrectly claims that both a start event and a tail event have only incoming arrows. A start event has only outgoing arrows. This statement is incorrect.

Parallel Activities

Statement 3 says: The activities which can be started one after another is known as parallel activities.

Analysis: Activities that can be started one after another are called serial activities, as explained above. Parallel activities are those that can be performed at the same time, or concurrently, because they do not have a dependency on each other that requires sequential execution. This statement describes serial activities, not parallel activities, making it incorrect.

Dummy Operation/Activity

Statement 4 says: A dummy is a type of operation which neither requires time nor any resource.

Analysis: In project network diagrams, particularly in Activity-on-Arrow (AOA) diagrams, a dummy activity is used to show logical dependencies between activities or events where no actual work, time, or resources are involved. It is represented by a dashed arrow. Its sole purpose is to maintain the correct sequence and relationship between events or activities. This definition perfectly matches the description provided in statement 4. This statement is correct.

Conclusion

Based on the analysis of each statement regarding project activities and events, the correct statement is the one that accurately defines a dummy activity.

Statement 4 is the only correct statement.

Was this answer helpful?

Important Questions from Project Planning

  1. Pick up the correct statement from the following.

  2. Miscellaneous expenses such as office expenses, stationery, postal expenses, etc., falls under _______.

  3. Which of the following phases does NOT come under the project management stages?

  4. The maximum amount of time that an activity can be delayed without extending the completion time of the overall project is called:

  5. A company has 5,000 obsolete toys in inventory at a production cost of $10 each. If the toys were remade for $ 3 each, they could sell for $ 5 each. If the toys are thrown away, they can be sold for $ 2.5 each. Which alternative is more desirable (rework or scrap) and what is the total benefit amount of this alternative?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App