All Exams Test series for 1 year @ ₹349 only
Question

Which of the following is not one of the principles of agile software development method?

The correct answer is

Rigidly following the original plan despite changed requirements

Agile prioritizes adapting to changing requirements while continuing to plan. Rigid adherence to an obsolete plan conflicts with that approach. Customer participation, frequent incremental delivery and responsiveness to change are consistent with Agile.

Was this answer helpful?

Important Questions from Software Development Models

  1. A simple stand - alone software utility is to be developed in ’C’ programming by a team of software experts for a computer running Linux and the overall size of this software is estimated to be 20,000 lines of code. Considering (a, b) = (2.4, 1.05) as multiplicative and exponention factor for the basic COCOMO effort estimation equation and (c, d)=(2.5, 0.38) as multiplicative and exponention factor for the basic COCOMO development time estimation equation, approximately how long does the software project take to complete ?  

  2. In ______ model, software is developed in a series of incremental releases.

  3. In _______ model, software is developed in a series of incremental releases.

    I. Spiral

    II. Sequential

  4. Among the following, which option describes a functional requirement?

  5. A software development firm is planning a new project involving a data analytics tool. The project is estimated to have $25000$ lines of code. Using the basic COCOMO model, the firm wants to estimate the effort in person-months. For this project type, the multiplicative factor is given as $2.8$, and the exponentiation factor is $1.2$. What is the estimated effort in person-months?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App