All Exams Test series for 1 year @ ₹349 only
Question

Which method is adopted to develop an approximate or conceptual estimate for perimeter works for buildings from the following?

The correct answer is

Cost per linear metre method

Cost per linear metre method Estimating cost based on the length of the element or work. Why Cost per Linear Metre is Appropriate As seen in the analysis, the "Cost per linear metre method" directly relates the cost to the primary measurement unit of perimeter works – length.

Was this answer helpful?

Important Questions from Measurement

  1. Which of the following is the unit of measurement for the sills of windows?

  2. What percentage of the cost of the estimate is provided for the work charged establishment?

  3. What is the thickness (inches) of the one brick wall made up of traditional brick?

  4. Which one is the CORRECT option for the damp proof course?

  5. What is the density of the mild steel in quintal per cubic meter?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App