When the quantities of the work items are difficult to be quantified and the rate analysis is also a complex issue, but still the contractor is willing to undertake a work, then the type of Contract best suited is:
Lump Sum Contract
Also known as a fixed-price contract, in a lump sum contract, the contractor agrees to complete the entire project for a single, fixed price. Therefore, when detailed quantification and rate analysis are challenging, but a contractor is still willing to commit to a total price, a Lump Sum Contract is the most appropriate choice.